Message ID: 21     Entry time: 09 Feb 2023, 01:11
Author: Jörg Hallmann 
Group:  
Subject: Shift summary Feb 8th 

stable beam at 9kev (about 1.1 mJ)

checks of the sample environment required for the upcoming user experiment

test data aquisition of SiO2 samples  (data analysis still ongoing)

commissioning of Jungfrau detectors & XTD6_ATT (closed loop operation)

test of operation with two different AGIPD triggers - normal one and an early one (leaving out the first 71 cells of AGIPD)

 

issues:

spectrometer motor XTAL_RX still not usable

first arm of XTD1_CRL is interlocked and cannot be used

 