Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 20 of 31  Not logged in ELOG logo
ID Date Authordown Location Severity Subject Text Attachments
  552   30 Sep 2024, 09:46 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 30.09.2024General Announcement:
-  
  
  553   02 Oct 2024, 09:41 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 02.10.2024General Announcement:
-  
  
  554   07 Oct 2024, 09:54 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 07.10.2024General Announcement:
- A. Galler informs a power glitch happened
today at around 07:40AM, however machine
  
  555   09 Oct 2024, 09:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 09.10.2024General Announcement:
- Martin Doering informs on the next Winter
Maintenance period: 
  
  556   14 Oct 2024, 09:41 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 14.10.2024General Announcement:
- Currently machine is now operating at 16.3GeV.
- The Winter maintenance task list was published
  
  557   16 Oct 2024, 09:57 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 16.10.2024General Announcement:
- Reminder that Nov. 1st is the deadline
for submitting the Winter Maintenance task
  
  560   28 Oct 2024, 10:03 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 28.10.2024General Announcement:
-  
  
  561   30 Oct 2024, 10:14 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 30.10.2024General Announcement:
- Friday Nov. 1st is the deadline to submit
the winter maintenance task list to XO.
  
  562   04 Nov 2024, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 04.11.2024General Announcement:
- Last Friday was the deadline to submit
the Winter Maintenance task list. We thank
  
  563   06 Nov 2024, 09:38 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 06.11.2024General Announcement:
- Invitation for scheduling meeting was distributed
to some groups. The Winter maintenance period
  
  564   11 Nov 2024, 09:46 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.11.2024General Announcement:
- Last day of the FD taking place and switching
back to 16.3GeV today.
  
  565   13 Nov 2024, 09:47 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 13.11.2024General Announcement:
-  
  
  566   18 Nov 2024, 09:41 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.11.2024General Announcement:
-  
  
  567   20 Nov 2024, 09:47 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 20.11.2024General Announcement:
-  
  
  568   25 Nov 2024, 10:02 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 25.11.2024General Announcement:
- Martin Doering announces on the upcoming
Winter Maintenance period: 
  
  569   27 Nov 2024, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 27.11.2024General Announcement:
- Issues with machine at the cold compressor
happened and the restart is delayed. Expectation
  
  570   02 Dec 2024, 09:56 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 02.12.2024General Announcement:
- A. Galler informs on the changed schedule
for Operation due to the difficulties with
  
  571   04 Dec 2024, 09:41 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 04.12.2024General Announcement:
- A. Galler informs X-rays for cw49 are currently
been tuned today due to the issues with the
  
  572   09 Dec 2024, 09:56 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 09.12.2024General Announcement:
- A. Galler informs two downtimes happened
last two nights totalizing 10-12hs due to
  
  573   11 Dec 2024, 09:43 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.12.2024General Announcement:
- A. Galler comments the maintenance period
started; already yesterday tunnels were opened
  