  514   18 Apr 2018, 15:06 Gerd WellenreutherGeneralInformationTunnel closing after shutdown

Dear all,

below please find the hottest and most up-to-date times for the closing of the tunnels after the shutdown:

XTD1: 23.04.
XTD2: 23.04.
XTD6: not before 02.07. 
XTD9: 27.04. after lunch
XTD10: 24.04. after lunch

Cheers, Gerd

  297   21 Jun 2017, 14:13 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I extended the tunnel access schedule up to the beginning of the shutdown (3.7.). As always, you can find it under https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Access request to Harald Sinn. Works during the shutdown have to be reported to Harald Sinn and Dirk Nölle for scheduling.

Cheers, Gerd

  301   26 Jun 2017, 15:52 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I tried to update the TAS to include the times for each XTD during the shutdown-week at the beginning of July. It is currently not entirely clear when XTD9 and XTD10 will be searched, and as always this is subject to change...

Link to Tunnel Access Schedule

Cheers, Gerd

  302   27 Jun 2017, 10:26 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

according to Dirk Nölle access to XTD4 during the shutdown will be extended until Thursday.

Link to Tunnel Access Schedule

Cheers, Gerd

  308   03 Jul 2017, 16:03 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

based on the information from todays BKR-meeting and communication with Harald Sinn, I updated the TAS: https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Basically, Harald is trying to keep XTD9 open until middle of next week, he still has to talk to DESY...

Cheers, Gerd

  317   06 Jul 2017, 08:51 Gerd WellenreutherXTD9InformationTunnel access schedule updated

Dear all,

access to XTD9 has been extended until the Friday the 14.7. 14:00. Tunnel access schedule has been updated:

TAS

Cheers, Gerd

  330   13 Jul 2017, 15:45 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I updated and extended the tunnel access schedule (TAS) until the 24th of July. According to Harald, there will be an opportunity to access XTD next Wednesday. Please keep him informed should you require access.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Cheers, Gerd

  337   18 Jul 2017, 10:57 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

an updated TAS is provided: https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

There is potential access to the XTDs on next Tuesday + Wednesday (25+26.7.), as well as on Monday - Wednesday (31.7.-2.8.). Access will be organized by M. Dommach, since H. Sinn will be on vacation - so please send Martin your access request in time.

Cheers, Gerd

  339   20 Jul 2017, 15:19 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

according to the current planning on next Tuesday (25.7.) both XTD9 and XTD10 will be accessible from 7-14:00:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Cheers, Gerd

  340   24 Jul 2017, 10:03 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

access to XTD9 and XTD10 will be available from tomorrow Tuesday the 25.7. 7:00 (Vacuum group will make sure the interlock is broken), until Wednesday 26.7. 14:00:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Please send any additional access requests to M. Dommach and T. Tschentscher.

Cheers, Gerd

  343   25 Jul 2017, 13:26 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I had some minor updates of the TAS during the last days, please check again.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Be reminded that there will be virtually no access to XTD2, XTD4 and XTD10 before the 14.8. shutdown, so plan your work accordingly. Access requests please to M. Dommach, cc T. Tschentscher.

Cheers, Gerd

  350   30 Jul 2017, 23:04 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

on Tuesday, XTD9 will be accessible from 7:00 - 14:00, due to requests by Naresh and Konrad. I updated the TAS:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  364   21 Aug 2017, 16:13 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I updated the tunnel access schedule with the most recent information provided by M. Dommach and H. Sinn. If you plan any works in the tunnels please check their availability on

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  377   04 Sep 2017, 17:33 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I have updated the TAS with the most recent information about Tuesday and Wednesday this week:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  379   08 Sep 2017, 11:55 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I updated the TAS to incorporate the newest dates for the October shutdown (currently 4.10.-23.10.):

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  386   18 Sep 2017, 17:39 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

XTD9 will be accessible tomorrow until the afternoon, but access should be communicated to M. Dommach, H. Sinn and T. Tschentscher. Martin will organize a search team for the afternoon.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  404   16 Oct 2017, 17:11 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I updated the schedule for the tunnel access in the upcoming weeks based on the discussions in the PSO- and the Operation Board-meetings:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  415   06 Nov 2017, 13:58 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I updated the TAS to include the upcoming user runs up to and including the winter shutdown. As you can see, there will only be access to the XTDs in cases of urgency. In these cases, please contact Martin Dommach, Harald Sinn or Thomas Tschentscher.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Cheers, Gerd

  420   14 Nov 2017, 11:05 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I received updates from DESY (M. Hüning) about how the access to the southern tunnels is being restricted in the next months, due to interlock tests etc., and included it in the TAS. Please check, if you have work to be done in these tunnels:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  72   10 Mar 2017, 16:56 Tobias HaasGeneralInformationTunnel Commissioning Schedule for Week 11
Day Motion Vacuum EPS Other 
Monday Loop is up. AE continues tests on MC2 lib Loop up. AE investigates problem with ion pump controller Loop inactive  
Tuesday Loop is up. AE continues tests on MC2 lib Loop down. AE implements fix for ion pump controller Loop inactive  
Wednesday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Thursday Loop down. AE adds ELMO and TECHNOSOFT Loop up for testing AE brings up loop  
Friday Loop up for testing Loop up for testing Loop up for testing  

 

In addition it should be tried to have a so called "Happy Hour" every day from 0800 - 1000. During this time loops should be up if possible. Meaning that in the evening before leaving, developers bring loops back up.