Entry   Vacuum Loop, posted by NEREA JARDON on 05 Apr 2017, 14:27 
Dear all, 
The XGM XTD2 is already into the Vacuum loop and the loop is running. We would continue with the interlock tests today in the afternoon, but would
not affect to other parts of the Vacuum loop.
Entry   Please inform on rack status 1.18, posted by Andreas Koch on 05 Apr 2017, 14:14 
The rack 1.18 in XTD9 is not operational at the moment because Nicola is working on it. Nerea, Tobias or others let me know when it is fully operational
again. This avoids checking it in the tunnel. Alternatively, let me know if I can check remotely.
Entry   Schedule after 0930 Meeting, posted by Tobias Haas on 05 Apr 2017, 10:15 
Tunnel Open.
Vacuum Loop:
Status:
Entry   Vacuum Loop, posted by NEREA JARDON on 04 Apr 2017, 19:25 
Dear all,
Tomorrow at first hour, some hardware modules would added in Rack 1.1 and 1.9 in XTD2 in the Vacuum loop. Therefore the communication would be
interrupted till the firmware is downloaded to the PLC, around 10h-10.30h should be running again to add the XGM XTD2 into the loop. Although, I will post
Entry   UPDATE on Temperature sensors for EPS loop, posted by Alessandro Silenzi on 04 Apr 2017, 18:49 
Here are the updated values for the temperature sensors inn the EPS loop.
Now Thermocouples work!
FXE_XTD9_COLB/TSENS/T1 23.1
Entry   Progress on Vacuum Loop, posted by Tobias Haas on 04 Apr 2017, 18:16 
J. Eidam, V. Bondor, T. Freyermuth checked Ion pump controller settings in XTD2 and XTD9.
Many controllers were found to have incorrect settings. All pumps in XTD2 now respond and give pressure readings. There remains the problem that
the PLC is looking for the wrong channel in the case where 2 pumps are connected to one controller (Is 1 & 3 and PLC looks for 1 & 2). J. Eidam
Entry   Meeting at 17:00 should take place at 17:45, posted by Tobias Haas on 04 Apr 2017, 16:31 
since tunnel access is now possible 
Entry   Access to XTD2 and XTD9 is now possible , posted by Tobias Haas on 04 Apr 2017, 16:29 
Interlocks in the northern fan are broken! 
Entry   Access to XTD2, posted by Tobias Haas on 04 Apr 2017, 15:11 
MPS informed me that they hit some problems and that they still need 30 mins to 1 h until we can go to XTD.  
Entry   Temperatures from EPS loop, posted by Alessandro Silenzi on 04 Apr 2017, 12:28 
This is the list of data coming directly from the PLC via its TCP client connected to the EPS PLC.
Format:
deviceName  temperature  status errorCode
    Reply   Temperatures from EPS loop, posted by Alessandro Silenzi on 04 Apr 2017, 12:43 


    
        
            
            Alessandro Silenzi wrote:
            
        
        
            
            This is the
Entry   Schedule after 09:30 Meeting, posted by Tobias Haas on 04 Apr 2017, 11:21 
 Tunnel closed today. Might re-open around 14:00
Note that that we re-convene briefly at 17:00 today in MCR (Mock-up Control Room)
Vacuum Loop:
Entry   Schedule for PLC and Karabo 3 April after 09:30 Meeting, posted by Tobias Haas on 03 Apr 2017, 10:03 
Tunnels closed today and tomorrow
- AE updates Vacuum and motion loop in the morning
- V. Bondar, J. Eidam and H. Sinn test vacuum in the afternoon (emphasis on understanding interlock conditions)
Entry   SASE1 EPS, posted by NEREA JARDON on 31 Mar 2017, 16:02 
Dear all,
EPS loop is running with the latest hardware updates. Today, when I was trying to update the loop, I have found that someone has powered off the
EPS crate in XTD2 Rack 1.5. Please, if you have to do some work in any part of SASE 1, let us know about it.
Entry   Meeting Minutes 31 March 2017, posted by Frederike Wittmaack on 31 Mar 2017, 15:03 
http://tinyurl.com/lttzrtm 
Entry   Update of component list after weekly meeting, posted by Tobias Haas on 31 Mar 2017, 15:00 170331-Tunnel-Components-Priority-list.xlsx
 
Entry   Web cameras in SASE1 tunnels, posted by Liubov Samoylova on 31 Mar 2017, 07:24 TmpPhCom_CR_2017-03-31-1.pptx
 
Entry   Update of component priority list after weekly meeting, posted by Tobias Haas on 24 Mar 2017, 15:24 170324-Tunnel-Components-Priority-list.xlsx
 
Entry   Schedule for PLC and Karabo Week 13, posted by Tobias Haas on 24 Mar 2017, 13:21 
 


    
        

           Day
            Motion Loop
            Vacuum
Entry   Motion up, posted by NEREA JARDON on 23 Mar 2017, 10:06 
Dear all, 
The Motion loop is up and running again. 
Thank you!
Entry   Pop-In II-45 Karabo test, posted by Andreas Koch on 22 Mar 2017, 16:39 
Trigger signal now available at imager. First Karabo tests of camera device with trigger successful. Detailed
tests continue.