Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 15 of 29  Not logged in ELOG logo
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 21 Jun 2017, 14:13 
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 21 Jun 2017, 10:21 
Entry   Access to tunnels updated, posted by Gerd Wellenreuther on 19 Jun 2017, 16:55 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 19 Jun 2017, 10:17 
Entry   WP74 OCD plan update, posted by Jan Grünert on 16 Jun 2017, 18:12 WP74-OCD-plan-6-8-2017.xlsx
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 16 Jun 2017, 10:18 Radiation_Measurments_for_Commissioning.pptx20170615-Components-Detectors.xlsx
Entry   Access to tunnels updated, posted by Gerd Wellenreuther on 15 Jun 2017, 12:18 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 14 Jun 2017, 10:57 
Entry   Tunnel's schedule updated, posted by Monica Aresté on 12 Jun 2017, 13:21 
Entry   Tunnel's schedule, posted by Monica Aresté on 12 Jun 2017, 11:17 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 12 Jun 2017, 10:55 
Entry   Motor in error, posted by Gabriele Giovanetti on 09 Jun 2017, 21:40 
Entry   Information AE OCD June 9 -- 12, posted by Nicola Coppola on 09 Jun 2017, 19:09 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 09 Jun 2017, 12:41 
Entry   XTD10 and XTD9 tunnel opening and closings, posted by Harald Sinn on 08 Jun 2017, 08:24 
Entry   XTD10 open , posted by Tobias Haas on 08 Jun 2017, 08:24 
Entry   Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 14:19 
Entry   Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 12:00 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 07 Jun 2017, 11:43 
Entry   Motion loop update, posted by NEREA JARDON on 06 Jun 2017, 17:39 
ELOG V3.1.4-7c3fd00