ID |
Date |
Author |
Location |
Severity |
Subject |
145
|
13 Apr 2017, 16:21 |
Tobias Freyermuth | General | Feedback | VAC loop up and running agian | The first EtherCAT coupler in 1.7 VAC was broken and is replaced now. The loop is up and running again.
Cheers,
Tobias |
146
|
18 Apr 2017, 11:14 |
NEREA JARDON | General | Information | Motion loop | Dear all,
The Motion loop would be updated now in order to fix names problems with PSLITs motors. In few minutes would be reachable again.
Than you! |
147
|
18 Apr 2017, 12:09 |
NEREA JARDON | General | Information | EPS loop | Dear all,
The EPS loop is running again with the last modifications concerning devices' names.
Thank you. |
148
|
18 Apr 2017, 13:06 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | XTD Tunnels open until 15:00. Later XTD2 and XTD4 are closed, XTD9/10 remain open
Vacuum Loop:
Status:
- One broken Beckhoff terminal was exchanged before the weekend. This was the first failure of this type in 2 years
- After this the system ran without hickup over the Easter weekend
- The fix applied for ion pumps that avoids triggering an interlock condition when there is a communication failure on the serial output should be also applied now to other vacuum device, e. g. the turbo pumps
EPS Loop:
Status:
- Requires an update to be done asap so that N. Gerassimova can continue tests with the PBLMs afterwards
Motion Loop:
Status:
- Movement of the PBLM motors (ELMO controller) is not satisfactory yet. Motors start and stop but the movement is uneven and stops not always requested
- There is no test set up in the lab. So tests have to be done in the tunnels (XTD9)
PBLMs:
- All systems in XTD2 were tested and cameras calibrated including some at the beginning of XTD9
- Work continues on remaining systems in XTD9
- System with motor movement is still unsatisfactory (see above)
Imagers
Status:
- 2 Imagers in XTD2 have no trigger signal. Suspicion is that this might be configuration problem. P. Gessler will investigate
- One pop-in (245) in XTD9 cannot be reached with IP. Suspicion is incorrect network configuration -> K. Fillipakopoulos
SPB Tunnel components
- Signal pins of the Attenuator crate were tested. DC voltage is seen there at different levels on different pins. This looks problematic -> P. Gessler
Karabo:
Status:
- Ran stably over the weekend
Tasks for today:
Note: All loops should be left running and no changes to Karabo.
- Take equipment and junk out of tunnels
- Check trigger cabling for imagers in XTD2
- Check PBLM motor movement and continue testing in XTD9
Other topics
- Controlled access to tunnels is possible after 1500. Coordination with T. Haas and the DESY run coordination
|
149
|
18 Apr 2017, 13:21 |
Tobias Haas | General | Information | KW16 Accelerator Plans | Author: Decking
Goals:
- Operation with 10 GeV, 500 pC, 5 kA, 30 bunch
- Increase gradient limits in RF stations
- Technical comissioning of north branch
XTIN closed all week
XTL open till Tue, 11:00
XTD2 open till Tue, 15:00
XTD4 open till Tue, 15:00
XTD9&XTD10 open all week
|17/04 Mo M | Easter shutdown
|17/04 Mo A | Easter shutdown
|17/04 Mo N | Easter shutdown
|18/04 Tu M | Interlock pre-test CS8, set XTL interlock at 11:00, Injector beam operation
|18/04 Tu A | A2 calibration after phase shifter change, Beam operation to TLD 10 GeV, set interlock XTD2-XTD4
|18/04 Tu N | Beam operation to TLD 10 GeV, 30 bunches, 0.5 nC
|19/04 We M | Slice emittance in BC2; Magnet PS test XTD2-XTD4
|19/04 We A | BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4
|19/04 We N | BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4
|20/04 Th M | Collimation set-up; Magnet PS test XTD2-XTD4
|20/04 Th A | BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4
|20/04 Th N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC; Magnet PS test XTD2-XTD4
|21/04 Fr M | Collimation set-up with 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|21/04 Fr A | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|21/04 Fr N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|22/04 Sa M | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|22/04 Sa A | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|22/04 Sa N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|23/04 Su M | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|23/04 Su A | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|23/04 Su N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|24/04 Mo M | Beam set-up 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo A | Beam operation to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo N | Beam operation to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz |
150
|
18 Apr 2017, 16:36 |
Andreas Koch | General | Information | Trigger and IP address | All trigger problems in XTD2 and XTD9 solved except for one: spb_xtd9_imgpi, probably a cabling issue on the camera side.
IP address problem for camera of sa1_xd2_imgpii45 solved. |
152
|
19 Apr 2017, 11:49 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open
Vacuum:
- Running stably
- Work continues on M3 in XTD9 and on the vacuum in XTD10
EPS Loop:
- Input from undulator still missing. This requires fixing a cable in balcony rooms and then testing
PBLM/Motion Loop:
- Work on the PBLM motors (ELMO controller) continues.
- It appears that the uneven movement is due to improper setting of motor parameters
Imagers
- Trigger problem reported yesterday was due to a cabling issue. Apparently during work on the relevant rack cables were unplugged and then wrongly put back
- Network issue with pop-in (245) in XTD9 solved
SPB Tunnel components
- Crate with "problem on signal pins" was brought to the lab and checked. Everything was ok. Problem was due to spurious measurement.
Karabo:
- PSLIT was tested successfully yesterday
- Behaviour of Karabo when a loop goes down needs to be made more graceful.
- Cleanup continues
Tasks for today:
Note: All loops should be left running and no changes to Karabo.
- Prepare mirror M3 installation
- Continue testing of PBLMs in XTD9
- Continue testing of SPB tunnel loop
Other topics
|
153
|
20 Apr 2017, 10:25 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open
Vacuum:
- PLC/Karabo Running stably
- Local tests of ion pumps in XTD9 being done by J. Eidam
- Work continues on M3 in XTD9 and on the vacuum in XTD10
- DPS in XTD9 should be integrated into the vacuum loop. This requires a cycling of the loop. Timing should be coordinated with WP74 because of XGM in XTD2. Unfortunately nobody from WP74 attended the meeting. Hence it was decided to perform the work tomorrow morning.
EPS Loop:
- Checks for the signal from the undulators and for the fast valve will be done with DESY MPS today
PBLM/Motion Loop:
- Work on the PBLM motors (ELMO controller) continues.
- Yesterday it was possible to align the screens
- There is a resource problem when trying to read out the cameras. For this reason an additional server needs to be set up dedicated to acquiring the images from the cameras.
SPB Tunnel components
- Crate that was checked in the lab yesterday was moved back into the tunnel
- The unstable support of the imager was fixed
- B. Weinhausen and M. Messerschmidt are testing
- All modules necessary for loops 1 & 2 were received from Poland
- Waiting for the "Freigabe" of the cables for SPB Optics
FXE
- Loops 1,2 and 4 are waiting for input from EETF
- Loops 3&5 are running
- No visible testing activity from FXE team
Karabo:
Tasks for today:
Note: All loops should be left running and no changes to Karabo.
- Prepare mirror M3 installation
- Continue testing of PBLMs in XTD9
- Continue local tests of ion pumps in XTD9
- Continue testing of SPB tunnel loop
Tasks for tomorrow:
- Cycle vacuum loop for inclusion of DPS in XTD9
Other topics
- Weekly SASE1 Readiness meeting tomorrow at 09:00 in XHQ 1.173
- L. Samoylova requests access to XTD2 to install another webcam
- Magnet current tests will likely continue through Wednesday in XTD2. Maintenance day to be shifted accordingly probably to Thursday/Friday. More information later
|
154
|
20 Apr 2017, 17:18 |
Tobias Haas | General | Information | Maintenance/Access in KW17 | In KW17 there will be NO maintenance day on Tuesday (25.04.)
On Monday (24.04.) morning up to about 11:00 we will have the TÜV approval of CS8. During that time NO access of "other people" to the XTL tunnel is possible. After the TÜV approval up to 13:00 there will be the possibility for URGENT access to the XTL. Access requests have to written to the logbook/access requests entry. The tunnel XTL/XTIN will stay in interlock, access will be possible by ZZ only. The northern branch XTD2->XS3->XTD4->XDU2 will stay closed, in order not to interrupt the magnet commissioning. This elogbook entry was sent to following experts: xfel-opl@desy.de RC mailing list |
155
|
21 Apr 2017, 09:59 |
Jan Grünert | General | Information | XGM status | XGM status 21.4.2017
During Easter break, the two XGMs in the control system (XTD2+9) had no issues.
XGM@XTD10 however had an issue: tuesday morning it was found that all pumps had stopped. The scroll pump showed an error. UPS apparently had excess load sunday evening 19h30 but couldn't send email (network error). Possibly vented with tunnel air up to 10mbar since that time. Investigation is ongoing.
Thursday enabled DOOCS pressure reading of XGM in XTD10, UPS rechecked
System surveillance on coming weekend: Jan and Theo 1 day
Other remarks:
- WP74 staff have received their dosimeters for ZZ access if required
- some automatic monitoring and info system is needed soon, e.g. karabo to NAGIOS connection
|
159
|
21 Apr 2017, 13:54 |
Jan Tolkiehn | General | Problem | Access to control PC | exflplcgwSA1 seems not reachable. This inhibits support for the PLC systems. |
161
|
21 Apr 2017, 15:22 |
NEREA JARDON | General | Information | OCD | Dear all,
The service of On-call Duty will be available from AE group during weekend in this number: 6442
Please make a post with the OCD numbers from CAS, WP74 and WP73.
Thank you and bests. |
164
|
21 Apr 2017, 17:22 |
Sandor Brockhauser | General | Information | CAS OCD April 22-23 | In case of any problems, please, call the CAS personnel on 9-6443, 9-5630, or 9-6840.
Have a nice week-end, Sandor |
165
|
24 Apr 2017, 11:08 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting |
Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open
Karabo:
- Bad crash of GUI server occured on Friday.
- System running over the weekend but performance of the GUI was sluggish
- There appears to be a resource leak. Experts are working on it.
- Fix is urgently needed for continued testing
Vacuum:
- Systematic tests of ion pumps start again since V. Bondar is back
- Fix for the interlock of the gas section in XTD9 to be deployed today.
- Gas system tests to be done starting tomorrow
PBLM/Motion Loop:
- There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.
SPB Tunnel components
- The Renishaw encoders can not be read out via the PLC
- The problem appears to be that the signal level is not TTL.
- T. Freyermuth is working on a fix
- Work can continue once the encoder problem is solved
- The same problem also affects FXE components
FXE
Tasks for today:
- Re-deploy vacuum loop for the tests of the gas section tomorrow
- Identify a fix/workaround for the GUI server resource problem
- Find a solution for the Renishaw encoder problem
- Restart testing of ion pumps in XTD9
Tasks for tomorrow:
- Test of gas section interlock
Other topics
- J. Grünert requests to put the XGM in XTD10 under PLC/Karabo control
- This would require extensive work by several groups (ITDM, AE, CAS) and cannot be done at the moment in view of established priorities
|
|
166
|
25 Apr 2017, 10:49 |
Adriano Violante | General | Information | Status and Plans after the 9:30 meeting | XTDs Info:
Tunnel XTD2 will be accessible this Thursday, 27.04. between 9 and 12. Dosimeter and General radiation training required. Access requests should go to T.Haas.
XTD10 will be closed starting from this Thursday, 27.04. at 12:00
Provided that the authorities give the "go ahead", DESY plans to put beam in XTD2 on Thursday's evening.
Karabo:
- System running but performance of the GUI still sluggish
- There appears to be a resource leak. Second server will be set up tomorrow as workaround. Experts are working on it.
- In parallel experts are working on a definitive solution
- Deployment today on a new beckhoff device for the decodification of PLC error messages.
Vacuum:
- Systematic tests of ion pumps started again
PBLM/Motion Loop:
- There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.
- ASilenzi will ask Natalia for acceptance test definition for PBLM
- Motion loop will be down until 10:30 for update. An entry will be written when the loop is again up.
SPB Tunnel components
- The Renishaw encoders can be read and positions are reliable. An error message is coming from the encoder and is probably due to a wrong voltage level delivered to the encoder. The encoders can be operated in this condition.
- T. Freyermuth is in contact with the encoder company tu understand the problem and work on a fix
- The same problem also affects FXE components
- The cameras operated at 1Hz deliver delayed images. 1/3 Hz operation (almost live mode) is OK - probably related to GUI memory issues
FXE
- Encoders of Loop1 have the same error message as SPB - the encoder positions are reliable - local components test can go on (e.g. OGT1)
- Encoders of loop2 are not powered - AE to investigate
Tasks for today:
- Identify a fix/workaround for the GUI server resource problem
- Deployment of a beckhoff device for the decodification of the error messages.
- Find a solution for the Renishaw encoder problem SPB Tunnel/ FXE Loop1
- Investigation of the FXE Loop2 encoders power
- Continue testing of ion pumps in XTD9
- Test of gas section interlock in XTD9
Tasks for tomorrow:
- Setup of the second server for karabo GUI
|
167
|
25 Apr 2017, 10:51 |
NEREA JARDON | General | Information | Motion loop | Dear all.
Motion loop is running again.
Thank you |
169
|
25 Apr 2017, 14:20 |
NEREA JARDON | General | Information | Motion loop | Dear all,
We have to make some changes again into the Motion loop. Therefore I will do an update at 14.45h.
I will keep you inform when it is running again.
Thanks! |
170
|
26 Apr 2017, 09:10 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
We need to update the Vacuum loop in order to correct and add some configuration to the interlock conditions.
It would be running in few minutes again.
Thank you! |
171
|
26 Apr 2017, 09:14 |
NEREA JARDON | General | Information | Motion and Vacuum | Vacuum is running again and Motion also, yesterday I forgot to update you about the Motion PLC.
Sorry and best regards, |
173
|
26 Apr 2017, 11:44 |
NEREA JARDON | General | Information | Motion loop | Dear all,
I will do an update of the motion loop so the PBLM could be tested. I will do it know and the PLC will be again available in few minutes.
Thank you! |
|