  145   11 Aug 2024, 14:33 Romain LetrunSPBShift summarySummary 06.08
- 10.08

X-ray
  
  144   11 Aug 2024, 02:15 Wonhyuk JoMIDShift summaryFound the spatial overlap on the Suna microscope
with Zyla.
Found the SDL motor position giving
  
  143   11 Aug 2024, 00:13 Andreas GallerPRCAttentionEPS Interlock change for Mode30:
the 3 HIREX Interlock conditions had
been disabled
 Screenshot_2024-08-11_at_00.12.04.png 
  142   10 Aug 2024, 07:19 Romain LetrunSPBIssueThe SASE1 HIREX interlock is not working
as expected.

At the position 'OUT' (step
 Screenshot_from_2024-08-10_07-17-38.png 
  141   10 Aug 2024, 01:17 Jörg HallmannMIDShift summaryFound the delay time from upper and lower
branches of SDL with a frosted-YAG.
The upper branch is -512.8 and the
  
  140   09 Aug 2024, 01:59 Jörg HallmannMIDShift summaryoptimized the SDL alignment

found timing of the upper (-520
ps) and lower branch (-514.5 ps) of the SDL
  
  139   08 Aug 2024, 00:18 Jörg HallmannMIDShift summaryoptimization of seeding (still not as good
as needed)

set position for the two color
  
  138   29 Jul 2024, 23:22 Romain LetrunSPBShift summaryX-ray
delivery


11.0 keV, 1-351 pulses
  
  137   29 Jul 2024, 06:45 Giuseppe MercurioSCSShift summary## Shift summary night July 28th-29th

Achievements:
- we saw signal on both MCPs (with
  
  136   28 Jul 2024, 23:34 Romain LetrunSPBShift summaryX-ray
delivery


11.0 keV, 1-352 pulses
  
  135   27 Jul 2024, 23:42 Romain LetrunSPBShift summaryX-ray delivery
- 9.22 and 11.0 keV, 1-352 pulses
@ 1.1 MHz, 600-1400 uJ.
  
  134   27 Jul 2024, 09:10 Harald SinnPRCIssueSASE1: Solid attenuator att5 is in error.
When it is tried to move it out, the arm
lifts, but does not reach the final position
  
  133   24 Jul 2024, 15:22 Giuseppe MercurioSCSShift summary
Shift
summary (Natalia, Giuseppe)

Achievements:


M1, M2 pitches adjusted
Grating
  
  132   24 Jul 2024, 11:35 Harald SinnPRCIssueThe control rack of the soft mono at SASE3
has some failure. Leandro from EEE will enter
the XTD10 at 12:00. 
  
  131   24 Jul 2024, 10:26 Harald SinnPRCIssueIn SASE2 undualtor cell 10 has issues.
Suren K. will do a ZZ at 11:30 to fix it
(if possible). Estimated duration: 1-3 hours. 
  
  130   23 Jul 2024, 17:17 IdoiaXROShift summary

ZZ
access at XTD10


The
LE PM X and HE PM X motors were checked and
  
  128   22 Jul 2024, 15:27 Antje TrappXROSASE3 end of shift summarythis morning, ZZ was done together with
Sylvia Huynh (EEE) to solve softmono pre-mirror
motor issue https://redmine.xfel.eu/issues/177392
  
  129   22 Jul 2024, 15:20 Antje TrappXROSASE2 end of shift summaryBeam is now aligned back to HED for hand-over
to Naresh (see picture)

points achieved:
 HED_beam__2024-07-22_15-19-15.png 
  127   18 Jun 2024, 13:03 Kelin TascaXROCompensation of M2 RY motor for the case of Piezo offWe plan to put the piezos of M2 off, in
the (unprobable) case that this is the reason
of the "jumps" in SASE3 trajectory.
 Screenshot_from_2024-06-18_13-16-14.pngScreenshot_from_2024-06-18_13-18-15.pngScreenshot_from_2024-06-18_13-20-06.png 
  126   14 Jun 2024, 01:53 Jörg HallmannMIDShift summarycontinue with Tempus tests
continue with PAM commissioning (first
results of the working device at MID)
  