The control rack of the soft mono at SASE3 has some failure. Leandro from EEE will enter the XTD10 at 12:00.
Beam will be interupted for SAS1 and SASE3.
Estimate to fix it (if we are lucky) is one hour.
Udate 12:30: Problem is solved (fuse was broken, replaced, motors tested)
Update 13:30: Beam is still not back, because BKR has problems with their sequencer |