Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2023 logbook, Contact: F.Wolff-Fabris, A.Galler, L.Samoylova, H.Sinn, Page 19 of 24  Not logged in ELOG logo
Entry   HED summary 25.3., posted by Lisa Randolph on 25 Mar 2023, 21:01 
This day we had lots of issues.


Nightshift noticed that the mirror 2 feedback was not running anymore since about 22hrs; PBLM2 cam was unknown; powercycling recovered
the camera, feedback operational again.
Continued shooting until ~9:00
At ~9:30 the whole Karabo, online cluster were dead. No control
Entry   Shift end, posted by Jayanath Koliyadu on 24 Mar 2023, 23:14 
X-ray delivery


1-165 pulses, 1.1 MHz - 28.2 kHz, upto 350  uJ @ 50 pC


Optical laser delivery


ns laser for imaging


Achievements/Observations
Entry   HED shift summary 23.-24.3., posted by Lisa Randolph on 24 Mar 2023, 21:46 
8.2 keV, 1-2 bunches, 600uJ

23.3.


did timing runs and optimized the beamline alignment
Karabo was working very slow
continued with sample alignment
performed
Entry   Status, posted by Naresh Kujala on 24 Mar 2023, 19:42 
Reply to elog103:

Spoke with Machine RC Thomas Wamsat and SQS.

Machine RC has some ideas to try. SQS have agreed that they can give 30 min for the machine to optimize the intensity.
Entry   Stability Issue, posted by Tommaso Mazza on 24 Mar 2023, 18:27 Screenshot_from_2023-03-24_18-25-31.pngScreenshot_from_2023-03-24_18-26-18.png
the pulse energy in XTD10 is lowered by ~30% when SASE1 changes photon energy, compare att. 1 and 2.

In addition, the intra-train pulse energy stability gets much lower. Potentially, there is an impact on the pointing as well, which is critical
for the pump-probe experiment.
Entry   Shift end, posted by Jayanath Koliyadu on 23 Mar 2023, 23:24 
X-ray delivery


1-165 pulses, 1.1 MHz - 28.2 kHz, upto 400  uJ @ 50 pC


Optical laser delivery


ns laser for imaging


Achievements/Observations
Entry   Status, posted by Romain Letrun on 23 Mar 2023, 14:31 20230323_HIREX_integral2.png20230323_HIREX_mean_spectrum2.png20230323_HIREX_peaks2.png
After SASE1 HIREX GOTTHARD reconfiguration, we now get a single pulse per frame. This was verified by comparing data from HIREX recorded with 564 kHz
and 1.13 MHz X-ray repetition rates. Both intensity and number of peaks is comparable for the two repetition rates.
Entry   Status, posted by Naresh Kujala on 23 Mar 2023, 13:07 Screenshot_from_2023-03-23_13-04-58.pngScreenshot_from_2023-03-23_13-17-05.png
Update for elog 99:

Now Gotthard timing is changed to new setting for 0.5 MHz.

attached screenshot with gothard timing setting
Entry   Issue, posted by Romain Letrun on 23 Mar 2023, 11:38 20230323_HIREX_integral.png20230323_HIREX_mean_spectrum.png20230323_HIREX_peaks.png
When using 1.13 MHz X-ray repetition rate, SASE1 HIREX is capturing two pulses in a single frame giving the impression that there are more peaks within
the spectrum than there are in reality.

This was verified by recording data with one and  two pulses per train, which are shown in attachment.
Entry   Shift summary - night shift, posted by JP, Hauke, Samuele on 23 Mar 2023, 00:27 7x
22 Mar 2023, 23:30 Handover from late shift

Tasks for the night:


source point measurement
Sample alignment
timing


23 Mar 2023, 00:39 Source point measurement
Entry   HED shift summary 22.03., posted by Lisa Randolph on 22 Mar 2023, 23:57 
During the night we worked on the temporal overlap between Relax laser and XFEL.

In the morning we noticed that the beam jitter is quite large (in and out of the aperture of the CRL4 lenses). There seems to be a correlation
with the HED popin. We adjusted the TCC with x-ray and laser. Performed transmission scans.
Entry   HED shift summary 22.03., posted by Lisa Randolph on 22 Mar 2023, 23:57 
During the night we worked on the temporal overlap between Relax laser and XFEL.

In the morning we noticed that the beam jitter is quite large (in and out of the aperture of the CRL4 lenses). There seems to be a correlation
with the HED popin. We adjusted the TCC with x-ray and laser. Performed transmission scans.
Entry   Shift end, posted by Adam Round on 22 Mar 2023, 21:49 
X-ray delivery


9 keV 1 to 165 pulses ~ 300 mj per pulse - stable delivery during the day


Optical laser delivery


ns lasers for illumination only


Achievements/Observations
Entry   Late shift summary, posted by Konstantin / Lisa / Carsten / Rahul / Toma / Masruri on 22 Mar 2023, 17:07 7x
22 Mar 2023, 17:08 started the log, the aim for the shift is the alignment of the sample and source point measurement. In addition to that, we also plan
to check the Greateyes camera.

22 Mar 2023, 17:53 continuing the sample alignment
Entry   HED Summary 21.3., posted by Lisa Randolph on 21 Mar 2023, 23:39 
Got the beam, aligned it up to the TCC, mirrors in 3 mrad configuration, checked positions for the CRLs. Energy up to 500 uJ at 8.2 keV, 2
bunches. 
Feedback M2 PBLM-2 camera was UNKNOWN. Power cycle (just switch off >> on) solved the issue. Also, the screen was extracted. Insert the screen.
Entry   Shift end, posted by Jayanath Koliyadu on 21 Mar 2023, 23:36 
Staff: JB, PV, TS, RL, RdW, JK, AR

X-ray delivery


1-165 pulses, 1.1 MHz, upto 400  uJ @ 50 pC


Optical laser delivery
Entry   Finding t0 with the PAM, posted by Terry Mullins on 21 Mar 2023, 19:35 7x
After setting timing witht he diode, we look at the PAM spectrometer and scan the laser timing a bit.  We found a clear change in the spectrum -
at >t0, the spectrum was very attenuated and at t<t0, the spectrum was larger.  This persisted for many 10s of ps (very unexpected behaviour).

In attachment are the LA3 timing scene, the SQS delay stage, the BAM, and the spectrometer signal from Metro at t0. att. 1 - 4.  The averaged
Entry   Late shift summary 19.03.23, posted by Robert Carley on 20 Mar 2023, 01:24 
Activities:


Measured tr-RIXS spectra on user sample in silane solvent


Problems:


Sometimes the PPL shutter cannot be opened from the control room after searching the hutch.
Entry   moning shift summary, posted by Nahid, Ben on 19 Mar 2023, 15:03 
Achievements:


measured the new sample, Silane, with different time delays


Problems


Tuning of SASE2 led to a 50% decrease in the SCS XGM intensity without affecting the SASE3 intensity. It also caused a jump in the BAM
Entry   shift summary, posted by Johannes Moeller on 19 Mar 2023, 02:01 Screenshot_from_2023-03-19_02-11-16.png

upper and lower branch of SDL aligned

beamsizes and angular mismatch characterized


vacuum leak of flight
path fixed
side view microscope re-aligned
problems with replaced MPC diamond detector. issue with in-vacuum cabeling suspected
misconfigured
timing of AGIPD fixed
splitting ratio of SDL detuned while HXRSS intensity decreased significantly. Possibly correlated.


With
ELOG V3.1.4-7c3fd00