Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 3 of 29  Not logged in ELOG logo
ID Date Author Location Severity Subject
  537   07 Aug 2024, 09:38 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 07.08.2024
General Announcement:
- A. Galler informs to SQS that the vertical polarization operation is planned for Thursday starting tuning in the afternoon 15:00. Please SQS inform BKR if tuning can start earlier.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- SA2 and SA3 with normal operating parameters.
- SA1 get extra time to work today from SPB/SFX.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Not present.

MID:
- Nothing to report; HXRSS is planned for this week. 

HED:
- Not present.

SCS:
- Yesterday and Monday problems with Interlocks but were fixed.

SQS:
- Nothing to report.

SXP:
- Nothing to report; it was useful to use the beam on Monday.
  536   05 Aug 2024, 09:41 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 05.08.2024
General Announcement:
-	

CTRL:
- Nothing to report.

DA:
- Announcement: tomorrow afternoon a maintenance on online and offline calibration will take place causing a 20min downtime.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.
- Suren K. questions SA3 instruments on the vertical polarization setup done last Saturday. 
Laurent M. and Manuel I. say that beam condition with polarized light was fine but they did not yet performed scans. Shifts in beam positions were seen but not understood. 

SPB:
- Nothing to report.

FXE:
- Tuning for SA2 and SA3 influenced FXE data collection, as it was not aware of tuning activities.

MID:
- All fine at MID.

HED:
- All good at HED.

SCS:
- Not using the shift today - done with X-ray commissioning and prioritizing the laser work.
- Changing number of pulses seemed to affect FXE for a second or so. Agreed to inform FXE when wanted to change pulses.
- XGM position was behaving weirdly. Drifts of the beam in the horizontal was seem by order of 1mm.

SQS:
- Nothing to report.

SXP:
- Will use the beam today instead of SCS.
  535   31 Jul 2024, 09:23 Andreas GallerGeneralInformationNotes XO Integration Meeting 31.07.2024

General Announcement:

CTRL:
- nothing major

DA:
- nothing major

EEE:
- nothing new

VAC:
- see XRO

XPD:
- nothing

DET:

ITDM: 
- all system 

XRO:
-  ZZ for XTD2 solid attenuator
 - limit switches of arm5 got llose and were pushed out of the way

LAS:
- all good

UNSYS:
- SA3 cell 11 solved yesterday

SPB:
- all fine

FXE:
- big printer for all instruments, ideally centrally located --> maybe near the XHCrew Operation Center

MID:
- nothing

HED:
- not present

SCS:
- in comm with EEE

SQS:
- not present

SXP:
- not present

  534   29 Jul 2024, 09:27 Andreas GallerGeneralInformationNotes XO Integration Meeting 29.07.2024

General Announcement:

CTRL:
- nothing

DA:
- nothing

EEE:
- nothing

VAC:
- nothing

XPD:
- nothing

DET:
- AGIPD comm. data taken

ITDM: 
- nothing

XRO:
- attenuator arm 5 is stuck XTD2
 - not yet clear if it is a hardware issue.
 - limit sitches are stuck --> EEE can move the attenuator 

LAS:
- SA1: 

UNSYS:
- SA3 cell 11, ZZ needed
 -

SPB:
- attenuator issue

FXE:
- not present

MID:
- damage in the fastADC channel
- calibration pipeline crashed ...

HED:
- all good 

SCS:
- PLC issues
 - parameters lost on PLC level
 - some motors don't work correctly
 - ELMO motors often go into error states 

SQS:
- not present

SXP:
- not present

  533   24 Jul 2024, 09:29 Andreas GallerGeneralInformationNotes XO Integration Meeting 24.07.2024

General Announcement:

CTRL:
- last bring up days

DA:
- minor issues fixed during bring up days

EEE:
- nothing 

VAC:
- nothing

XPD:
- SA1/2 HiREX working
- Diamond detector small isue 

DET:

ITDM: 
- nothing

XRO:
- ramp up mostly completed --> reports send to all Instruments
- SA3 monochromator back in operation

LAS:
- SA1 all good automatic peak integration of dynamic trigger is being implemented
- SA3: 600 uJ short 

UNSYS:
- SA2 cell 10 issue
 - EtherCAT communication with 

SPB:
- JF4M:
 - last week tghe power supply stopped working, with help of DET and EEE the MPOD was made working, hower read out boards would not power trigger 

FXE:
- nothing

MID:
- no big isues with bring up days, vacuum is ok

HED:
- JF issue was solved yesterday with replacing the board

SCS:
- bakeout commecning

SQS:

SXP:

  532   22 Jul 2024, 09:29 Andreas GallerGeneralInformationNotes XO Integration Meeting 22.07.2024

General Announcement:

CTRL:
- nothing major, proceeding with bring up

DA:
- not present 

EEE:
- bring up days SPB today, MID tomorrow, SEPS interlock today

VAC:
- nothing to discuss

XPD:
- nothing to report

DET:
- issue with a JF at HED
 - one of the ASICS misbehaving
 

ITDM: 
- nothing to report

XRO:
- SA3 Mono

LAS:
- not present

UNSYS:

SPB:
- nothing to report

FXE:
- nothing to report

MID:
- damaged roughing pump, needs to be send in
 - atm not an issue

HED:
- issue with Hexapod --> IT config had to be corrected

SCS:
- Friday: mechanical problem in one of the chambers, spare parts to arrive today?

SQS:
- not present

SXP:
- not present

  531   17 Jul 2024, 09:50 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.07.2024
General Announcement:
- Martin Doering informs today an e-mail will be sent to groups asking for tasks that are cancelled or postponed. The feedback will be required until mid of next week.
- A. Galler informs on a report for non-correct bunch arrival monitors at the instruments. It is requested to instruments to get information on this topic and bring back to XO.
- User Operation Meeting starts next Friday 19.07.

CTRL:
- Nothing to report.

DA:
- Not present.

EEE:
- Nothing to report.

VAC:
- Not present.

XPD:
- Gotthard-II in XTD6 Hirex: today the power supply will be checked and by end of the day info to XO/PRC will be done.

DET:
- SPB/SFX an issue with Jungfrau-4M high voltage power supply system happen and is broken needing a fix.
- Hirex/Gotthard-II the tests with beam is prioritized on Monday/Tuesday next week.

ITDM: 
- Nothing to report.

XRO:
- On the weekend it starts the technical ramp-up of SA3 and Monday/Tuesday the SA2 and SA1;
- On Monday the SEPS interlock tests are happening and hutches will be closed.

LAS:
- Nothing to report.
- Bunch pattern server issue last week: fix was provided. No more info on the effects of it on LAS preparations.

UNSYS:
- Issue with SA3/cell18 undulator did not move and hit the limit. Under investigation.

SPB:
- Nothing to add to the Jungfrau issue.

FXE:
- Nothing to report.

MID:
- Issue with vacuum system at MID - failed yesterday twice.

HED:
- Nothing to report.

SCS:
- Yesterday problem with mechanics in tunnel; will need PLC team; Leandro Z. informs is under investigation.

SQS:
- Nothing to report.

SXP:
- Not present.
  530   15 Jul 2024, 09:39 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.07.2024
General Announcement:
- The User Operation Meetings will restart next Friday 19.07.

CTRL:
- Proceeding with bring up days.

DA:
- Busy with bring up days.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Not present.
- As PRC, Raul Villanueva informs that activities in XTD6 are planned to be finished by tomorrow, Tuesday.

DET:
- HIREX / Gotthard-II inSA2: it is fixed and installation is ongoing.

ITDM: 
- Nothing to report; also involved in bring-up days.

XRO:
- An e-mail will be sent as preliminary tests will be done as preparation for SEPS tests next Monday. It is transparent to the machine.

LAS:
- Not present.

UNSYS:
- All good with undulators.

SPB:
- Nothing to report.

FXE:
- Nothing to add.

MID:
- All fine at MID.

HED:
- All fine at HED.

SCS:
- Today bring up days happening.

SQS:
- Nothing to report.

SXP:
- Not present.
  529   10 Jul 2024, 09:48 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 10.07.2024
General Announcement:
- Frank Poppe asks for an available time for a tour in experimental Hall and tunnels. It will be discussed offline with XO.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- XTD6 was searched yesterday evening for extra interlock tests. This was finished and tunnel will be opened again today for XPD work.

XPD:
- Work on HIREX is progressing and estimate to install back in tunnel is Thursday or Friday.

DET:
- Marco R. is working on the Gotthard-II of Hirex; also DET is preparing for next Run.

ITDM: 
- Migration of XFEL gateway will be done on late Thursday. Karabo database will also be done. Announcement will be sent.

XRO:
- Not present.

LAS:
- Not present.

UNSYS:
- Everything is fine.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Nothing to report; transport with Hall crew is planned for today.

SQS:
- Nothing to report.

SXP:
- Not present.
  528   08 Jul 2024, 08:46 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 08.07.2024
General Announcement:
- Eric Boyd comments on Interlock tests: today FXE and MID hutches are being searched for ~30 mins. Please contact Eric in case you find lights ON. 
For tomorrow, Tuesday: OFF buttons will be tested and jumped in SA1/SA3 instruments and on Wednesday the SA2 instruments. Access is restricted and e-mail will be sent to communicate when people are 
allowed to resume access/work. 
Also please clean up the hutches for the inspection and tests.

CTRL:
- Nothing to report; Karabo redeployment went well last week.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- XTD6 tunnel access is needed for HIREX.

DET:
- Intervention at SPB AGIPD: modules were swept, severe effect due to radiation (one module not working). One module was swept in the quadrant. It was successful.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Some surprises but under control.

UNSYS:
- All fine.

SPB:
- All fine.

FXE:
- Software and firmware updates with detectors taking place.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
  527   03 Jul 2024, 09:54 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 03.07.2024
General Announcement:
- Tunnels have been closed and the Interlock Tests required by the legislators are ongoing.
- Eric Boyd informs that next Monday two hutches have to be searched for the Interlock Tests, one at MID and one at FXE. An e-mail will be sent to the instruments.
- J. Sztuk-Dambietz asks on the DAQ for DET to do not close the proposals yet; Steffen H. informs that a fix is on the way and will be fixed and running. Proposals will not be closed until the deployment.

CTRL:
- Deployment of Karabo last week.
- Announcement: re-deploy Karabo Beckhoff devices to rollback have to be done as new feature was causing problems (related to the unit values). 
Today 2PM for tunnels and Laser topics; for instruments will be later organized. A brief restart is expected.

DA:
- Nothing to report.

EEE:
- Working with CTRL to re-deploy Karabo devices for digitizers. This is ongoing and will be available later today or tomorrow.

VAC:
- Not present.

XPD:
- Completed tasks on tunnels.
- Yesterday work in Gotthard-II detector at SA2 (Hirex) was found detector does not work. CTRL and DET helped and detector was moved out of tunnel. There is no HIREX available in SA2. 
Also power supply for HIREX in SA1 has to be worked.

DET:
- Working on the Gotthard-II with XPD.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- All good so far.

UNSYS:
- Everything is fine.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Not present.

SXP:
- Nothing to report.
  526   01 Jul 2024, 09:40 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 01.07.2024
General Announcement:
-	 

CTRL:
- Done with updates in tunnels, BKR and instruments. Today continue with lab areas accordingly to schedule;
- Update of Beckhoff version with introducing units for datalog inputs. Working on a fix for some middle layer devices. A rollback can be done in few minutes if desired.

DA:
- Need to do fine tuning deployment for some packages in Maxwell, but not critical.

EEE:
- Nothing to report.

VAC:
- Well in time going with schedule. Tasks in XTD9 to be finished today.

XPD:
- Finishing last tasks;
- Bring Gotthard detector in XTD6 to work with Hirex. If needed access in XTD6 may be requested after Interlock tests.

DET:
- Inspection of AGIPD-1M at SPB/SFX happening with Desy colleagues.

ITDM: 
- Nothing to report.

XRO:
- Everything fine.
- Couple of tasks ongoing in XTD6 (needed manual restart).

LAS:
- Not present.

UNSYS:
- Everything is fine.

SPB:
- Bug in the PLC for the chiller controllers.
- Problem with digitizers - in contact with Bruno F.
FXE:
- Broken Ion pump controller to be fixed with help from VAC.

MID:
- Nothing to report.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Not present.

SXP:
- Nothing to report.
  525   26 Jun 2024, 09:52 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 26.06.2024
General Announcement:
- Water leak in one of the racks (3.13 / XTD10) in the tunnels that needs attendance. The power for this rack will be cut to investigate and exchange the heat exchanger. Possibly happening at 11:00AM 
today. 
Groups affected are VAC, IT and EEE. Repair is necessary as quickly as possible. Please check for components to that rack and switch them down before the power cut at 11:00.
- Andreas G. informs on the Monday's emergency power off task proposed to take place today at SA3: This work is postponed to the winter maintenance period. 
Only two new search buttons will be installed at SCS this week however it does not need emergency power OFF, meaning no effects on electricity and/or interlocks.

CTRL:
- Proceeding with Karabo update.

DA:
- Nothing to report.

EEE:
- Progressing with maintenance tasks.

VAC:
- Not present due to tunnel activities.

XPD:
- Tasks ongoing as planned.
- Message for CTRL and DA: Gotthard-II was installed in SA2 and water connections made. It is ready to be deployed as soon as SA2 Karabo is back. Please CTRL inform XPD/Naresh K. when Karabo is back.

DET:
- Nothing to report.

ITDM: 
- Ongoing with maintenance.
- No news for Maxwell yet; needs a follow up.
- Needs to restore components when power is back in rack 313.

XRO:
- Not present.

LAS:
- Tasks ongoing as planned.
- Lasermet installations are done.

UNSYS:
- Try to understand the level of hardware that needs to be replaced in the long maintenance. The power cycling of the cabinets brings problems for the terminals. 
One needs to replace all linear encoders in the undulators or at least the ones that does not work.
- Currently all ready for starting next Run 2024_02.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Incident with Jungfrau detector: together with DET checking of repair can be done in modules.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Nothing to report.
  524   24 Jun 2024, 10:11 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 24.06.2024
General Announcement:
- Eric Boyd and Torsten Schoen: work by MPS / Wille company in SA3 radiation protection hutches will trigger emergency OFF button on Wednesday. Rack rooms connected to these hutches are also affected.
Decision if task takes place to be done after internal discussions between parts. XO will coordinate together with Eric Boyd.

CTRL:
- Start with summer maintenance: today with SA1 area.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Not present.

XPD:
- Not present.

DET:
- Nothing to be reported.

ITDM: 
- Continuing with maintenance activities: today Maxwell cluster is updated; all activities are going accordingly to the plan.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Not present.

SPB:
- Nothing to report.

FXE:
- Not present.

MID:
- Nothing to report.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
  523   19 Jun 2024, 09:48 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 19.06.2024
General Announcement:
-	 

CTRL:
- Perform tests on watchdogs with XPD after this meeting.

DA:
- Nothing to report.

EEE:
- Today start with cable installations at SQS - be careful with cables when walking.
- Many tasks are ongoing.

VAC:
- Nothing to report.

XPD:
- Ramp down day yesterday by XRO and XPD; issues were identified and solved. Time was useful and successful.
- Tests with Imagers without X-ray beam are being done today.

DET:
- Start with maintenance tasks.

ITDM: 
- First day with activities on servers and clusters at balcony room.
- Maxwell update on 24.06 will be advertised by e-mail today.

XRO:
- Not present.

LAS:
- Start with shutting down lasers today.
- Safety interlock work in SA3 laser areas takes up to end of next week that requires Electrical expert present (see e-mail from Torsten S.). 
Emergency OFF button is only valid for the laser rooms/hutches in SA3.

UNSYS:
- Replace SA1 cell22 PS motor from today.

SPB:
- Not present.

FXE:
- Nothing to report.

MID:
- All fine at MID; going accordingly to the schedule.

HED:
- Nothing to report.

SCS:
- Moving experimental chamber today through the Hall.

SQS:
- Not present.

SXP:
- Not present.
  522   17 Jun 2024, 09:38 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.06.2024
General Announcement:
- Summer maintenance is about to start on Wednesday; tomorrow the XRO and XPD ramp down activities are planned. 
- The XO Integration meeting continues to happen during the summer maintenance period.

CTRL:
- Nothing to report; preparing for the summer maintenance.

DA:
- Nothing to report and quiet on the OCD side.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing major to report.

ITDM: 
- Nothing to report.
- Maxwell maintenance: Likely to be done Monday/Tuesday of last week of June is the deployment. E-Mail will be sent.

XRO:
- Nothing to report.

LAS:
- Nothing to report.
- SA1 issue of last weeks with drifting: sync system maintenance was not announced and found to be the reason for it. Right now it is fixed. Also master time was reset by EEE.

UNSYS:
- Everything fine apart of the SA1/cell22 PS motor to be replaced when tunnels are open.

SPB:
- Not present due to the ongoing retreat.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Not present.

SCS:
- Start with maintenance tasks.

SQS:
- Nothing to report.

SXP:
- Not present.
  521   12 Jun 2024, 10:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.06.2024
General Announcement:
- This is the last operation week with beam delivery for users for this Run.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Yesterday afternoon an issue with V0 closing was solved.

XPD:
- A. Galler informs that on SPB/SFX branch the XGM was switched OFF by Theo M. as part of preparation for the summer maintenance that triggered the V0 valve.

DET:
- Nothing to report.

ITDM: 
- Announcement: upgrades of some systems will happen in last week of June after agreement with Desy-IT.
- Dcache system will also be updated in the same days, for about 2 days.
- General announcements will be sent around in due time.

XRO:
- Nothing major to report.

LAS:
- Unexplained issue in SA1 by oscillator shifted against the triggers. Under investigation.

UNSYS:
- Nothing to report.

SPB:
- Issue with AGIPD with intervention on chiller + modules exchanges and will not take beam this Run.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Not present due to Fusion workshop.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.
  520   10 Jun 2024, 10:03 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 10.06.2024
General Announcement:
- Martin Doering presents the summer maintenance plan: 
1. Complete task lists was released last Friday; 
2. ITDM and CTRL dates: a. Karabo down from 24.06 to 02.07 depending on the topic; b. DAQ unavailable from Jun 18th to Jul. 2nd; c. replacement of exflgateway on Jun 28; d. upgrade of operations elog on 
Ju. 2nd. 
3. No major intervention cooling water apart of fluctuations on flow and temperature; 
4. No interruptions of electricity; 
5. Safety tests: a. interlock tests in experimental hutches on July 9-10.; b. SEPS and AIBS tests on July 22.  
- As PRC, Martin Dommach says everything went quiet last week.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Yesterday at SPB/SFX operation was interrupted due to Julabo chiller in AGIPD 1-M. Managed to put system back online after few hours.

ITDM: 
- Nothing to report.

XRO:
- Everything fine.

LAS:
- Not present.

UNSYS:
- Issue with phase shifter SA1/ cell22: needs a ZZ to replace parts today due to availability of people. To be discussed later.

SPB:
- Chiller issue; in discussion with DET.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
  519   05 Jun 2024, 09:55 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 05.06.2024
General Announcement:
- On Monday 10.06 a few slides on the Summer maintenance will be presented by Martin Doering in this meeting series. The task list will be released next Friday 07.June.

CTRL:
- Working on the all watchdog: hotfix was released last Monday and follow up is being done. Will get in touch with instruments for deployments if needed.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Everything is running fine.

XPD:
- In a retreat.

DET:
- Nothing to report; as info: DAC meeting is taking place this week at XFEL.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Sync issues seen at SCS last weekend were fixed and did not happen again.

UNSYS:
- On SA1 cell#21, two ZZs were needed on Monday: first power distribution was replaced; 
after switching on cabinet the linear encoders were not communicated and after placing controller to the rotary encoders the motor of the PS was found broken and was replaced.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Problem with on a spectrometer camera: ticket was sent to CTRL and needs further help. 
Wajid E. says DOC was also contacted and seems to be an issue with the hardware/camera as controls side it seems fine. A test with a spare camera is needed.

SCS:
- 400nm laser issue: follow up on the info regarding this failure is appreciated to be shared to other instruments that perform pump-probe experiments.

SQS:
- Not present.

SXP:
- Not present.
  518   03 Jun 2024, 09:54 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 03.06.2024
General Announcement:
- As PRC, Maurizio V. informs on: 1. Fire alarm in tunnels / SA2 cost beamtime on Saturday as beam permission was removed; 2. PP-laser synchronization seems solved; 3. HED setting point was slightly 
changed but assumed to be fine. 


CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- It was observed at SA2 XGM too large a background synchrotron radiation signal. It was removed when Graphite filter was inserted in SA2 and it may relate to the attempt to delivery 9keV at 11.5GeV.

DET:
- Nothing to report.

ITDM: 
- Network update: move of the rack in room 27 is finished and network is running again. Please users check the system and report back to IT-support ticket system in case something is found to be wrong.

XRO:
- Nothing to report.

LAS:
- Sync issue in SCS: PP-laser went out of LOCK and Desy Sync group adjusted the internal clock and is currently optic synchronized.

UNSYS:
- Limit switch of cell3 in SA2 was activated while attempting to reach minimum gaps; fixed by UNSYS-OCD.
- Fire alarm was related to a fire extinguisher system in an undulator rack as the fan was broken.
- Wrong phase shifter gaps related to middle layer server; people working on it.

SPB:
- Preparing for Tuesday starting with beam.

FXE:
- Not present.

MID:
- Broken nano-second laser system at MID: chiller pump of the laser broke two days before user beamtime and a new order is ordered but arrives this week. 

HED:
- Nothing to report.

SCS:
- The 400nm laser use was cancelled due to damage optics.

SQS:
- Nothing to report.

SXP:
- Not present.
ELOG V3.1.4-7c3fd00