Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 9 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Locationdown Severity Subject Text Attachments
  70   10 Mar 2017, 12:53 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness MeetingNote that due to a bug in the elog the
name appeared wrongly in my previous message.
In general: Avoid underscores in the file
 170310-Tunnel-Components-Priority-list.xlsx 
  72   10 Mar 2017, 16:56 Tobias HaasGeneralInformationTunnel Commissioning Schedule for Week 11
    
        

           Day
  
  73   13 Mar 2017, 15:47 NEREA JARDONGeneralInformationVacuum and Motion downTomorrow, 14th of March, Vacuum and Motion
loop will be down at least during morning
due to technical reasons .
  
  74   14 Mar 2017, 13:55 NEREA JARDONGeneralInformationVacuum and Motion downDear all,
Finally today the Vacuum and Motion
will still running the hole day and I would
  
  76   15 Mar 2017, 11:31 NEREA JARDONGeneralInformationVacuum and MotionToday Denis has to make some changes in
the Vacuum and Motion hardware loop, therefore
they would be down some time. 
  
  77   15 Mar 2017, 17:00 NEREA JARDONGeneralInformationVacuum and MotionVacumm and Motion are running again after
the hardware changes.
  
  78   16 Mar 2017, 13:34 Torben FalkGeneralFeedbackWiring statusWiring status SASE 1:
Wiring progress:

    Internal wiring of the
  
  79   16 Mar 2017, 16:54 NEREA JARDONGeneralInformationFuses replacementDear all,
Tomorrow in the morning is needed
to add some fuses in the PLCs crate, therefore
  
  80   17 Mar 2017, 10:49 NEREA JARDONGeneralInformationLoops upDear all, Vacuum and Motion loops are running
again.
Thank you,
  
  81   17 Mar 2017, 12:11 Thomas TschentscherGeneralInformationUpdated Tunnel component status listUpdated list of tunnel high priority components
after SASE1 Readiness mtg this morning. The
list has also been sent for comments/clarifications
 170317-Tunnel-Components-Priority-list.xlsx 
  82   17 Mar 2017, 15:21 Adriano ViolanteGeneralInformationLoop status schedule for KW12Dear all,
find here the foreseen loop status
for KW12. The schedule could change. All
  
  83   22 Mar 2017, 15:05 NEREA JARDONGeneralInformationMotion LoopFYI. The Motion loop is again up and running.   
  84   22 Mar 2017, 16:28 NEREA JARDONGeneralInformationMotion loopDear all, 
tomorrow morning at 10h am, we will
need the Motion PLC for roughly half hour
  
  86   23 Mar 2017, 10:06 NEREA JARDONGeneralInformationMotion upDear all, 
The Motion loop is up and running
again. 
  
  87   24 Mar 2017, 13:21 Tobias HaasGeneralInformationSchedule for PLC and Karabo Week 13 

  
  88   24 Mar 2017, 15:24 Tobias HaasGeneralInformationUpdate of component priority list after weekly meeting   170324-Tunnel-Components-Priority-list.xlsx 
  89   31 Mar 2017, 07:24 Liubov SamoylovaGeneralInformationWeb cameras in SASE1 tunnels   TmpPhCom_CR_2017-03-31-1.pptx 
  90   31 Mar 2017, 15:00 Tobias HaasGeneralInformationUpdate of component list after weekly meeting   170331-Tunnel-Components-Priority-list.xlsx 
  91   31 Mar 2017, 15:03 Frederike WittmaackGeneralInformationMeeting Minutes 31 March 2017http://tinyurl.com/lttzrtm    
  92   31 Mar 2017, 16:02 NEREA JARDONGeneralInformationSASE1 EPSDear all,
EPS loop is running with the latest
hardware updates. Today, when I was trying
  