Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 9 of 30  Not logged in ELOG logo
ID Date Author Locationdown Severity Subject Text Attachments
  70   10 Mar 2017, 12:53 Tobias HaasGeneralInformationUpdate of Tunnel Component Priority List after SASE1 Readiness MeetingNote that due to a bug in the elog the
name appeared wrongly in my previous message.
In general: Avoid underscores in the file
 170310-Tunnel-Components-Priority-list.xlsx 
  72   10 Mar 2017, 16:56 Tobias HaasGeneralInformationTunnel Commissioning Schedule for Week 11
    
        

           Day
  
  73   13 Mar 2017, 15:47 NEREA JARDONGeneralInformationVacuum and Motion downTomorrow, 14th of March, Vacuum and Motion
loop will be down at least during morning
due to technical reasons .
  
  74   14 Mar 2017, 13:55 NEREA JARDONGeneralInformationVacuum and Motion downDear all,
Finally today the Vacuum and Motion
will still running the hole day and I would
  
  76   15 Mar 2017, 11:31 NEREA JARDONGeneralInformationVacuum and MotionToday Denis has to make some changes in
the Vacuum and Motion hardware loop, therefore
they would be down some time. 
  
  77   15 Mar 2017, 17:00 NEREA JARDONGeneralInformationVacuum and MotionVacumm and Motion are running again after
the hardware changes.
  
  78   16 Mar 2017, 13:34 Torben FalkGeneralFeedbackWiring statusWiring status SASE 1:
Wiring progress:

    Internal wiring of the
  
  79   16 Mar 2017, 16:54 NEREA JARDONGeneralInformationFuses replacementDear all,
Tomorrow in the morning is needed
to add some fuses in the PLCs crate, therefore
  
  80   17 Mar 2017, 10:49 NEREA JARDONGeneralInformationLoops upDear all, Vacuum and Motion loops are running
again.
Thank you,
  
  81   17 Mar 2017, 12:11 Thomas TschentscherGeneralInformationUpdated Tunnel component status listUpdated list of tunnel high priority components
after SASE1 Readiness mtg this morning. The
list has also been sent for comments/clarifications
 170317-Tunnel-Components-Priority-list.xlsx 
  82   17 Mar 2017, 15:21 Adriano ViolanteGeneralInformationLoop status schedule for KW12Dear all,
find here the foreseen loop status
for KW12. The schedule could change. All
  
  83   22 Mar 2017, 15:05 NEREA JARDONGeneralInformationMotion LoopFYI. The Motion loop is again up and running.   
  84   22 Mar 2017, 16:28 NEREA JARDONGeneralInformationMotion loopDear all, 
tomorrow morning at 10h am, we will
need the Motion PLC for roughly half hour
  
  86   23 Mar 2017, 10:06 NEREA JARDONGeneralInformationMotion upDear all, 
The Motion loop is up and running
again. 
  
  87   24 Mar 2017, 13:21 Tobias HaasGeneralInformationSchedule for PLC and Karabo Week 13 

  
  88   24 Mar 2017, 15:24 Tobias HaasGeneralInformationUpdate of component priority list after weekly meeting   170324-Tunnel-Components-Priority-list.xlsx 
  89   31 Mar 2017, 07:24 Liubov SamoylovaGeneralInformationWeb cameras in SASE1 tunnels   TmpPhCom_CR_2017-03-31-1.pptx 
  90   31 Mar 2017, 15:00 Tobias HaasGeneralInformationUpdate of component list after weekly meeting   170331-Tunnel-Components-Priority-list.xlsx 
  91   31 Mar 2017, 15:03 Frederike WittmaackGeneralInformationMeeting Minutes 31 March 2017http://tinyurl.com/lttzrtm    
  92   31 Mar 2017, 16:02 NEREA JARDONGeneralInformationSASE1 EPSDear all,
EPS loop is running with the latest
hardware updates. Today, when I was trying
  
ELOG V3.1.4-7c3fd00