No Radiation Measurements in SASE 1 This week, posted by Eric Boyd on 03 Aug 2017, 10:52
|
Do to repairs that need to be made with the cold compressor. We will be unable to perform Radiation Hutch Commissioning for SASE 1 this week. We will
attempt to reschedule the Measurments for Thursday or Friday (10.08 or 11.08) of next week, depending on if it can be coordinated with all involved parties.
There is no restricted access to SASE 1 until then. |
Radiation Measurements of FXE Monday 07.08, posted by Eric Boyd on 04 Aug 2017, 13:41
|
The control room thinks that they will be able to very easily provide us the desired parameters for commissioning the FXE EXP Hutch this coming
Monday. If that is the case we will be restricting access in SASE 1 in accordance to the attached presentation from 8:00 am until completion of the radiation
measurements. A SASE 1 log book entry will be made when restrictions go into effect and are lifted. |
Time Schedule change in Radiation Measurements for Monday, posted by Eric Boyd on 04 Aug 2017, 15:24
|
Dear All,
We have just changed the time that the Radiation Protection Measurements will take place on Monday. This will now begin at 15:00. The time has
been pushed back so that the DESY Radiation Protection group will be able to also be there. |
Status after 9:30 disptach meeting, posted by Monica Aresté on 07 Aug 2017, 12:45
|
General
The Radiation measurement test will be postponed until the beam reach the 30 bunches.
SPB |
Radiaiton Measurements Complete for SASE 1, posted by Eric Boyd on 07 Aug 2017, 18:30
|
Radiaiton Measurements are complete for SASE 1 Normal access is restored.
|
KARABO 2.1.13, posted by wajid ehsan on 08 Aug 2017, 13:10
|
As previously announced we will deploy KARABO 2.1.13 in tunnel under topic SA1. The system will go down in 10 mins. I will announce it
again as soon the system is up again.
Regards, |
KARABO 2.1.13, posted by wajid ehsan on 08 Aug 2017, 15:25
|
The system is up and running.
Regards,
Wajid |
Status and Plans after 09:30 meeting, posted by Tobias Haas on 09 Aug 2017, 10:23
|
General
Main focus for Vacuum Group and AE next week will be to get as much done in XTD10/SASE3 as possible. Conflicts with activities
in SASE1 need to be carefully monitored |
Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 11 Aug 2017, 10:07
|
General
The focus of activities next week for the AE and vacuum groups is on getting as much done in XTD10 as possible. There is a conflict with
the aim to bring AGIPD to SPB and start commissioning. A lot of preparatory work was done for the latter this week already. Nevertheless this conflict |
Office network in XTD10, posted by Krzysztof Wrona on 17 Aug 2017, 07:59
|
Dear All,
In XTD10 there are now office network ports available in each rack. These can be used to connect your regular laptops with a network cable without
special configuration and registration of your laptop. |
Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 18 Aug 2017, 11:23
|
Software:
CAS meets with SPB and FXE on a daily basis to fine tune progression towards user operation
A list of required deliverables
for user operation has been agreed between CAS and SPB/FXE (see slide 5 in presentation by H. Santos attached to these minutes)
The list |
Tunnel access schedule updated, posted by Gerd Wellenreuther on 21 Aug 2017, 16:13
|
Dear all,
I updated the tunnel access schedule with the most recent information provided by M. Dommach and H. Sinn. If you plan any works in the tunnels
please check their availability on |
Status and Schedule after 09:30 meeting, posted by Tobias Haas on 21 Aug 2017, 16:26
|
General
Access to tunnel XTD10 ends today around midday and beam is expected back for the instruments on Thursday
SPB
Good progress was made over the weekend with AGIPD. On Saturday first dark images were recorded
Today the detector hybrids |
Karabo 2.1.15 in Test , posted by Hugo Silva Santos on 22 Aug 2017, 10:53
|
Dear All,
I would like to report that we started today to test (internally in CAS) the Karabo 2.1.15 version.
We got delayed to prioritise and solve a showstopper issue related to GUI Client. If our tests succeed, we are foreseeing to finish the tests |
Status and Schedule after 09:30 meeting, posted by Tobias Haas on 23 Aug 2017, 10:20
|
CAS
Finishing tests for KARABO 2.1.15. Deployment should start today during the middle of the day for SPB
SPB asks for additional
slow data to be included in the DAQ. This requires tests after 2.1.15 is deployed
For the moment 2.1.15 will only be deployed for SPB. Once |
Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 25 Aug 2017, 13:42
|
General
T. Haas conveys the congratulations of the management
for the achievements in installing and commissioning the AGIPD in
SPB
for the progress made with installations in XTD10/SASE3
There will be a meeting next week in order to determine |
TAS updated, posted by Gerd Wellenreuther on 28 Aug 2017, 16:00
|
Dear all,
I updated the tunnel access schedule - as you can see there will be no access tomorrow. Any access requests regarding next weeks Tuesday as usual
to M. Dommach, cc to Harald Sinn and T. Tschentscher. |
Status and plans after SASE1/3 Readiness Meeting, posted by Monica Aresté on 30 Aug 2017, 09:53
|
Normal
0
21
false
false
false
|
Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 01 Sep 2017, 10:34
|
General:
The length of the shut down in October is still under discussion. Currently it appears that it is shortenend to 8 working days
The
management reviewed the readiness of the instruments for first users on 14 September:
Very good progress was made over the last weeks
Data |
WP74 - OCD contacts for this weekend, posted by Jan Grünert on 01 Sep 2017, 20:14
|
02.09. from 08:00 until 03.09. 08:00 - Wolfgang Freund 9-5630
03.09. from 08:00 until 04.09. 08:00 - Florian Dietrich 9-6968
|