ID |
Date |
Author |
Group |
Subject |
Text |
|
29
|
22 Feb 2024, 06:13 |
Peter Zalden | FXE | Shift summary | Beam conditions:
Used photon energies between
6 and 7 keV, including short undulator scans
Continuously |
|
28
|
21 Feb 2024, 23:00 |
Tokushi Sato | SPB | Shift summary | X-ray delivery: stable and flat over 250
pulses per train. 1.1 MHz with 400 uJ
Optical laser delivery: NA |
|
27
|
17 Feb 2024, 08:15 |
Tommaso Mazza | SQS | Issue | The cross on the FEL imager, which we use
as a reference for BKR crew, is not centred
on the GATT aperture. when was this changed, |
|
26
|
15 Feb 2024, 09:32 |
Romain Letrun | SPB | Shift summary | X-ray delivery
1 to ~332 pulses at 6 keV,
4.5 mJ
Stable delivery
Number |
|
25
|
13 Feb 2024, 08:55 |
Konopkova Zuzana | HED | Experiment summary | *Achievements :
- Generally rather successful with
very high quality beam parameters |
|
24
|
13 Feb 2024, 08:52 |
Romain Letrun | SPB | Issue | Like after the previous winter maintenance
period, the shutter of FXE appears as opened
in DOOCS panels even though it is closed |
|
23
|
13 Feb 2024, 06:38 |
Giuseppe Mercurio | SCS | Shift summary | shift
summary
Andreas, Giuseppe |
|
22
|
13 Feb 2024, 01:02 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
1-350 at 12.45 keV, 1600
uJ. Stable delivery
Optical |
|
21
|
11 Feb 2024, 23:04 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
1-350 at 12.45 keV, 1700 uJ. Stable
delivery |
|
20
|
11 Feb 2024, 06:28 |
Giuseppe Mercurio | SCS | Shift summary | Night
shift summary
Andreas, Giuseppe |
|
19
|
10 Feb 2024, 23:32 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
1-350 at 12.45 keV, 1750
uJ. Stable delivery
Optical |
|
18
|
10 Feb 2024, 00:12 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
1-350 at 12.45 keV, 1700
uJ. Stable delivery
Optical |
|
17
|
09 Feb 2024, 07:15 |
Giuseppe Mercurio | SCS | Shift summary |
night
shift summary
achievements: |
|
16
|
08 Feb 2024, 23:14 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
1-350 at 12.45 keV, 1700
uJ. Stable delivery
Optical |
|
15
|
08 Feb 2024, 07:00 |
Giuseppe Mercurio | SCS | Shift summary | Late shift
07.02.24
Laurent, Martin |
|
14
|
06 Feb 2024, 07:17 |
Giuseppe Mercurio | SCS | Shift summary |
|
|
13
|
05 Feb 2024, 23:10 |
Jörg Hallmann | MID | Shift summary | check of the optimized focussing options
at 10 keV using only one arm in CRL2 - results
still to be evaluated |
|
12
|
04 Feb 2024, 23:36 |
Wonhyuk Jo | MID | Shift summary | Goal Achieved.
- Finished flat field measurement
for AGIPD at different scenarios for upcoming |
|
11
|
03 Feb 2024, 23:51 |
Jörg Hallmann | MID | Shift summary | goals achieved:
alignment of the beam in tunnel and
hutches including refinement of the beam |
|
10
|
02 Feb 2024, 23:31 |
Romain Letrun | SPB | Shift summary | X-ray delivery
1-64 pulses at 10 keV,
~1.1 mJ.
Overall stable delivery.
Optical |
|
|