Message ID: 25     Entry time: 13 Feb 2024, 08:55
Author: Konopkova Zuzana 
Group: HED 
Subject: Experiment summary 

*Achievements :
- Generally rather successful with very high quality beam parameters
- We had a nearly steady 800 uJ+ HXRSS flux during the user run and ~ 4mJ SASE during the setup at HED.
- Beampointing was rather stable throughout the HXRSS operation.
- Users took several shots (>2600 FEL and FEL+ReLAX shots) on target. The beamline setup was very quick prior to that and users were able to get preliminary data to prototype parameters already a day before formal handover to them and could straight go to harvest mode on Saturday morning.  
-----------------------------------
* Issues :
- Users still found large Bremsstrahlung fluxes on their background, but this is rather on our side, in conjunction with the users.
- On the last day, we had issues with JF calibrations due to the high run numbers in the proposal. DOC promptly helped out.  
- Initially, we observed fluctuations in the FEL flux. BKR was very prompt to correct for this and user operation was not impacted seriously. Slow drifts in pulse energy were also observed, but again, could be compensated from time to time by them.
-----------------------------------