Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
OPERATION-2024
OPERATION-2023
OPERATION-2022
OPERATION-2021
OPERATION-2020
OPERATION-2019
SASE1-2018
SASE1-2017
Experiment data
OPERATION-2024 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn
Not logged in
List
|
Message ID:
29
Entry time:
22 Feb 2024, 06:13
Author:
Peter Zalden
Group:
FXE
Subject:
Shift summary
Beam conditions:
Used photon energies between 6 and 7 keV, including short undulator scans
Continuously got 1 mJ despite the short pulse mode that's running
Bandwidth was found to be 18 eV FWHM at 6.07 keV (0.3%) by monochromator scan against fixed undulator setpoint
Achievements:
Cr foil scan for energy calibration of the FXE mono
Prepared setpoints for XAS scans during next week's user expts. at: Ce L3 (5.72 keV), Ce L2 (6.16 keV) and Mn K (6.54 keV)
IPM calibration against XGMD
Issues:
ATT MDL (class JJAttenuator) got stuck in INIT state and then did not show that absorber was inserted in the beam path (ticket to be submitted to Ctrls)
DA3 of FXE DAQ (FXE_DAQ_DATA/DA/3) got stuck in changing state (it got too many parameters inserted). The restart by shutting down the server and waiting for the device to come back up took around 20 mins, see 22.2.2024, 4:24 am to 4:43 am.