Entry   Issue, posted by Frederik Wolff-Fabris on 12 Nov 2024, 10:07 Screenshot_2024-11-12_100032.png

- While FEL IMG with YAG screen was inserted in SA1, EPS/MPS was not limited to the expected 2 bunches, but to 30 bunches; 
- It was found
the condition #3 ("SA1_XTD2_VAC/Switch/SA1_PNACT_Close") at the EPS Mode-S was disabled which should be always enabled; 
- Condition
#3 has been enabled again and now SA1 is limited to 2 bunches, as expected when YAG screen is inserted. 

Further investigations will be done to
Entry   Issue, posted by Frederik Wolff-Fabris on 15 Nov 2024, 10:50 
SA2 cell#5 undulator segment moved at ~09:45AM Fri to 25mm without aparent reason and undulator experts need a ZZ to exchange power supply; FEL
instensity dropped from 230uJ to 60uJ s consequence.

RCs are preparing south branch for the iminent ZZ. HED is informed.
Entry   Status, posted by Dirk Raiser on 17 May 2024, 10:42 
Laser status:

After the laser issues listed in https://in.xfel.eu/elog/OPERATION-2024/99 the
late shift was finally able to find a timing setting for the amplifier trigger that was beyond stable settings under usual conditions, but which allowed
Entry   Shift summary, posted by Chan Kim on 31 Jan 2024, 23:26 
31.01.2024 (Day shift)

X-ray delivery


10 keV
1200 - 400 uJ (significant pulse energy slope within train)


Optical laser delivery
Entry   Shift summary, posted by Chan Kim on 13 Mar 2024, 23:41 
X-ray delivery


6 keV, 2.6 mJ/pulse, stable delivery


Optical laser delivery


800nm PP laser, stable delivery


Achievements/Observations
Entry   Shift summary, posted by Chan Kim on 15 Mar 2024, 00:16 
X-ray delivery

6 keV, 2.4 mJ/pulse, stable delivery

Optical laser delivery
Entry   Shift summary, posted by Chan Kim on 15 Mar 2024, 23:43 
**X-ray delivery**

- 6 keV, 3.2 mJ/pulse, stable delivery

**Optical laser delivery**
Entry   Shift summary, posted by Chan Kim on 28 Mar 2024, 14:54 
X-ray delivery


12.72 keV, 10 Hz, NOT stable delivery, pointing drastically changed in the afternoon, presumably due to the train-on-demand operation
at SASE2


Optical laser delivery
Entry   Issue, posted by Chan Kim on 28 Mar 2024, 14:56 Screenshot-from-2024-03-28-14-26-18_1.png
Pulse energy fluctuation observed after full train operation in SA2 starts.
Entry   Shift summary, posted by Chan Kim on 29 Mar 2024, 22:38 
X-ray delivery
- 12.72 keV, 10Hz, ~1.4 mJ/pulse, stable delivery 

Optical laser delivery
Entry   Issue, posted by Chan Kim on 30 Mar 2024, 22:02 Screenshot_from_2024-03-30_21-59-03.pngScreenshot_from_2024-03-30_21-09-11.png
Continuous pointing drift in horizontal direction.

It may trigger a vacuum spike at SPB OH (MKB_PSLIT section) at 21:07 pm.

 
Entry   Shift summary, posted by Chan Kim on 30 Mar 2024, 22:50 
X-ray delivery

- 12.72 keV, 10Hz, ~1.4 mJ/pulse, continuous beam drift in the horizontal direction observed

Optical laser delivery
Entry   Shift summary, posted by Chan Kim on 07 Jun 2024, 23:12 
X-ray delivery
- 7.0 keV, up to 202 pulses at 564 kHz, 1.0 mJ.
- Average pulse energy was about 1.9 mJ on Tuesday and Wednesday. It has to be discussed with BKR tomorrow morning.
Entry   Shift summary, posted by Chan Kim on 09 Jun 2024, 22:45 
X-ray delivery


7.0 keV, up to 202 pulses at 564 kHz, 1.0 mJ.


Optical laser delivery


ns laser for jet illumination


Achievements/Observations
Entry   Shift summary, posted by Chan Kim on 24 Aug 2024, 23:09 
X-ray delivery

-12.40 - 12.82 keV, XDT9 XGM ~0.81 mJ@ end of shift

Optical laser delivery
Entry   Shift summary, posted by Chan Kim on 27 Aug 2024, 12:17 
X-ray delivery


12.78 keV, ~1.3 mJ


Optical laser delivery


800 nm laser for jet visualization


Achievements/Observations
Entry   Issue, posted by Chan Kim on 25 Sep 2024, 16:53 Screenshot_from_2024-09-25_16-50-57.pngScreenshot_from_2024-09-25_16-51-21.png
600um thick CVD diamond (XTD2 attenuator) seems damaged

 

Attachment 1: 600um thick CVD diamond (Arm 4) OUT
Entry   Shift summary, posted by Chan Kim on 25 Sep 2024, 23:36 
X-ray delivery


6 keV, ~2.8 mJ, stable delivery


Optical laser delivery


ns laser for particle visualization


Achievements/Observations
Entry   Shift summary, posted by Chan Kim on 26 Sep 2024, 23:12 
X-ray delivery


6 keV, ~2.7 mJ, stable delivery


Optical laser delivery


ns laser for particle visualization


Achievements/Observations
Entry   Shift summary, posted by Chan Kim on 27 Sep 2024, 23:13 
X-ray delivery


6 keV, ~3.0 mJ, stable delivery


Optical laser delivery


ns laser for particle visualization


Achievements/Observations