Message ID: 176     Entry time: 25 Sep 2024, 23:36
Author: Chan Kim 
Group: SPB 
Subject: Shift summary 

X-ray delivery

  • 6 keV, ~2.8 mJ, stable delivery

Optical laser delivery

  • ns laser for particle visualization

Achievements/Observations

  • NKB focus optimized
  • particle injection tested with gold nanoparticles
  • ns laser roughly aligned with particle beam
  • Julabo chiller (AGIPD) is still on target (-32 degree)

Issues

  • XTD2_ATT Arm4 (600um thick CVD) is damaged (most probably last week)