| ID |
Date |
Author |
Group |
Subject |
Text |
 |
|
28
|
12 Feb 2023, 06:53 |
Tokushi Sato | SPB | Shift summary | X-ray delivery
9.3 keV, 1-85 pulses, 1
mJ, stable delivery
Optical |
| |
27
|
12 Feb 2023, 01:56 |
Jörg Hallmann | | Shift summary Feb 11th | intense data taking on various samples
2 main issues:
- data collection using the optimize |
| |
26
|
11 Feb 2023, 13:55 |
Andreas Galler | PRC | Status | Gun Modulator Problems
Gun Trip at 11:23 and since then
the Modulator trips after each restart. |
| |
25
|
11 Feb 2023, 07:06 |
Jayanath Koliyadu | SPB | Shift end | X-ray delivery
9.3 keV, 1-85 pulses, 1
mJ, stable delivery
Optical |
| |
24
|
11 Feb 2023, 01:09 |
Jörg Hallmann | MID | Shift summary | sucessfull data taking for user samples
beam loss for ~15 min and a small
issue with scannerX of the FSSS (could be |
| |
23
|
10 Feb 2023, 08:17 |
Jayanath Koliyadu | SPB | Shift end |
X-ray delivery
9.3 keV, 1-85 pulses, 1 |
| |
22
|
09 Feb 2023, 07:14 |
Jayanath Koliyadu | SPB | Shift end | X-ray delivery
9.3 keV, 1-85 pulses, 1.3
mJ, stable delivery
Optical |
| |
21
|
09 Feb 2023, 01:11 |
Jörg Hallmann | | Shift summary Feb 8th | stable beam at 9kev (about 1.1 mJ)
checks of the sample environment
required for the upcoming user experiment |
| |
20
|
08 Feb 2023, 11:14 |
Andreas Koch | XPD | SA3 status | Bunch number control - SA3 FEL
imager
As announced today in the XO meeting |
| |
17
|
05 Feb 2023, 15:18 |
Harald Sinn | PRC | Issue | 15:15 SCS called and reported an
issue with one of the motors of the SCS exit
slit. DOC already looked at the problem and |
| |
18
|
05 Feb 2023, 12:32 |
Natalia, Zhong | SCS | morning shift summary | achievements:
- Viking spectrometer set up in 8th
order around 1280eV and calibrated |
| |
16
|
05 Feb 2023, 08:40 |
karen appel | HED | Shift summary | Start up of HED ongoing for the three shifts
Day shift:
work on the new X-ray alignment |
| |
15
|
04 Feb 2023, 08:34 |
karen appel | HED | Shift summary | We took the beam from 7 am, 24 h operation
in three shifts.
We set up a new scheme for aligning |
| |
14
|
02 Feb 2023, 09:25 |
Peter Zalden | FXE | Shift summary | FXE bring-up, summary of shifts 31.1. and
1.2.:
Beam delivery (11.5 GeV) |
| |
13
|
02 Feb 2023, 06:37 |
Chan Kim | SPB | Issue | SPB_IRU_DPA/MOTOR issue
X stage looks okay, but Y, AX,
and AY values have been changed by 2-3mm. |
    | |
11
|
30 Jan 2023, 19:06 |
Maurizio Vannoni | XRO | SASE2 Summary of Maintenance Period and Ramp up activities | SASE2 Summary of Maintenance
Period and Ramp up activities
Maintenance |
| |
10
|
30 Jan 2023, 16:31 |
Maurizio Vannoni | XRO | SASE1 Summary of Maintenance Period and Ramp up activities | SASE1
Summary of Maintenance Period and Ramp up
activities |
| |
12
|
30 Jan 2023, 15:21 |
Maurizio Vannoni | XRO | SASE3 Summary of Maintenance Period and Ramp up activities | SASE3
Summary of Maintenance Period and Ramp up
activities |
| |
9
|
25 Jan 2023, 08:44 |
Raúl Villanueva-Guerrero | PRC | ZZ Access on 24th January (19:30h) - Replacement of Motor on SASE2 Undulator - Cell 17 Phase Shifter | Dear all,
last evening Suren Karabekyan and
myself did a short notice ZZ access to XTD1. |
| |
8
|
25 Jan 2023, 08:40 |
Raúl Villanueva-Guerrero | PRC | All SASE's - SEPS Interlock Test - Results, Status & Upcoming Schedule | Dear all,
please find here a summary of the
status on this critical topic provided yesterday |
|
|