Sergii, Giacomo | SCS | Late shift summary 21.10.2023 | Achievements:
-Collecting TR-RIXS data for different
fluencies and delay range |
|
403
|
22 Oct 2023, 07:34 |
Laurent, Phuong | SCS | night shift summary, 22.10.2023 |
Night
shift summary 22.10.2023
Laurent,
Phuong |
|
404
|
22 Oct 2023, 13:21 |
Benjamin van Kuiken | SCS | Shift summary | Morning shift
Summary 22.10.2023
Achievements
Checked beam alignment |
|
406
|
23 Oct 2023, 01:38 |
Sergii , Giacomo | SCS | Late shift summary 22.10.2023 | Achievements
-Check XAS and static RIXS after the
beam was back |
|
408
|
23 Oct 2023, 06:46 |
Laurent Mercadier | SCS | Night shift summary, 23.10.2023 |
|
|
414
|
25 Oct 2023, 15:10 |
Sergii, Teguh | SCS | Morning Shift Summary, 24.10.2023 |
Morning
Shift Summary, 24.10.2023
Achievements:
Re-aligned the beamline |
|
415
|
25 Oct 2023, 15:18 |
Sergii, Teguh | SCS | Morning Shift Summary, 25.10.2023 |
Morning
Shift Summary, 25.10.2023
Achievements:
Re-aligned FEL beam pointing |
|
417
|
26 Oct 2023, 07:13 |
Andreas Scherz / Eugenio Paris | SCS | night shift summary | Night shift summary
Achievements:
- Recovered time0 on SiN (time0 moved |
|
418
|
26 Oct 2023, 15:03 |
Sergii, Teguh | SCS | Morning shift summary, 26.10.2023 |
Morning
shift summary, 26.10.2023
Achievements:
Continued measuring tr-RIXS |
|
420
|
26 Oct 2023, 23:25 |
Robert Carley | SCS | Late shift summary, 26.10.2023 |
Achievements:
Continued with tr-RIXS
No
problems |
|
444
|
12 Nov 2023, 07:24 |
Benjamin van Kuiken | SCS | Night shift summary | # Shift Summary
Achievements
- Found RIXS signal from CuO |
|
445
|
13 Nov 2023, 07:16 |
Loic Le Guyader | SCS | shift summary | # Shift Summary
Achievements
- Measured elastic line with |
|
3
|
16 Jan 2023, 19:50 |
Jan Gruenert | PRC | Issue | Problem: Beam operation in SASE2
is prohibited by SEPS / MPS
Origin of problem: HED-CRL3 |
|
4
|
17 Jan 2023, 10:25 |
Jan Gruenert | PRC | Issue | SASE3 peration issue - SOLVED
Controls
issue, the machine cannot make beam in SASE3.
From
BKR / DOOCS the problem description is: Big |
|
6
|
22 Jan 2023, 18:40 |
Jan Gruenert | PRC | Issue | SASE1 blocked to 1 bunch/train
by EPS interlock (sic, not 2 but 1)
--- PARTIALLY RESOLVED |
|
7
|
23 Jan 2023, 10:43 |
Jan Gruenert | PRC | Status | Status of machine SASE tuning
(just before switching off for monday maintenance):
|
|
8
|
25 Jan 2023, 08:40 |
Raśl Villanueva-Guerrero | PRC | All SASE's - SEPS Interlock Test - Results, Status & Upcoming Schedule | Dear all,
please find here a summary of the
status on this critical topic provided yesterday |
|
9
|
25 Jan 2023, 08:44 |
Raśl Villanueva-Guerrero | PRC | ZZ Access on 24th January (19:30h) - Replacement of Motor on SASE2 Undulator - Cell 17 Phase Shifter | Dear all,
last evening Suren Karabekyan and
myself did a short notice ZZ access to XTD1. |
|
17
|
05 Feb 2023, 15:18 |
Harald Sinn | PRC | Issue | 15:15 SCS called and reported an
issue with one of the motors of the SCS exit
slit. DOC already looked at the problem and |
|
26
|
11 Feb 2023, 13:55 |
Andreas Galler | PRC | Status | Gun Modulator Problems
Gun Trip at 11:23 and since then
the Modulator trips after each restart. |
|