Message ID: 414     Entry time: 25 Oct 2023, 15:10
Author: Sergii, Teguh 
Group: SCS 
Subject: Morning Shift Summary, 24.10.2023 

Morning Shift Summary, 24.10.2023

Achievements:

  1. Re-aligned the beamline after maintenance
  2. Found time zero using SiN at 300 K
  3. Change the He dewar and cooled down back to 20 K
  4. Adjusted the AFS laser parameters to recover the proper experiment settings
  5. Started taking tr-RIXS with several time delay points

Problems:

  1. The AFS laser power is smaller than last week

Next shift plan:

  1. Continue taking tr-RIXS data