Message ID: 406     Entry time: 23 Oct 2023, 01:38
Author: Sergii , Giacomo 
Group: SCS 
Subject: Late shift summary 22.10.2023 

Achievements
-Check XAS and static RIXS after the beam was back
-Do the warm up cycle to remove ice from the sample surface
-Check coarse timing after the beam drop
Problems
-Could not see the fine timing signal so far