Progress Beam Transport, posted by Tobias Haas on 10 Feb 2017, 08:31
|
Post on behalf of Harald Sinn
Fortschritte, die ich letzte Woche beobachten konnte, sind:
|
Updated Components List, posted by Tobias Haas on 10 Feb 2017, 15:07
|
| Added Diagnostic Screen for SPB and changed PRIO for DPS - XGM - DPS in XTD9 to high as discussed during the S1R meeting |
Meeting Minutes 10 Feb 2017, posted by Frederike Wittmaack on 10 Feb 2017, 15:15
|
Follow the link below to view the minutes and relating material on Alfresco.
http://tinyurl.com/zc3nvn9 |
Updated Components List, posted by Tobias Haas on 10 Feb 2017, 16:34
|
| |
Current Status, posted by Alessandro Silenzi on 12 Feb 2017, 14:02
|
Vacuum loop:
- Interface between PLC and Karabo is not functioning.
The fault currently resides in the PLC behaviour, the self-description sent out is badly formatted (due to a buffer overrun) |
Beckhoff loop status, posted by Alessandro Silenzi on 14 Feb 2017, 09:59
|
2017.02.13 19:30 Status:
- Self-Description back in shape.
- Bad SelfDescription reproduced in BeckhoffSim (Karabo implemented PLC communication) and solved in BeckhoffCom (Karabo "PLC Client"). |
Current Vacuum Status, posted by Alessandro Silenzi on 15 Feb 2017, 20:10
|
The PLC is still not completely error free.
It is considerably better performing than the last days:
the current average pressure as measured by the Ion Pumps is 4.21e-09 mBar |
Motion loop status, posted by Alessandro Silenzi on 15 Feb 2017, 20:20
|
The motion loop is as of 18:40 online.
the current status of the devices as seen by the Karabo is shown in the attachment:
In summary 63 devices (29 Motors): |
Motion loop feedback, posted by Alessandro Silenzi on 17 Feb 2017, 09:56
|
Quick feedback during the meeting:
- 63 Devices
- 29 Motors |
Updated Component status list, posted by Thomas Tschentscher on 17 Feb 2017, 12:40
|
See the updated component status list for XTD2 and XTD9 tunnels. As discussed at the SASE1 readiness mtg this morning. Yellow fields indicate new/changed
entries. Please let me/THaas know if there are errors or further changes to be reported.
I also entered the SASE1 instruments now a 'High Priority' items.
However, we may need to adapt the table for These entries as the work flow seems different. |
Meeting Minutes 24 Feb 2017, posted by Frederike Wittmaack on 24 Feb 2017, 15:22
|
| http://tinyurl.com/hhu998t |
Update of component list after weekly meeting, posted by Tobias Haas on 24 Feb 2017, 16:33
|
| |
Reminder: Stable operation and development periods, posted by Tobias Haas on 28 Feb 2017, 11:38
|
One word of clarification:
The discussion last Friday left some people uncertain over how to define stable operation and development periods. Hence I had a discussion with
Nerea and Alessandro and agreed on the following: |
PLC work, posted by NEREA JARDON on 02 Mar 2017, 09:52
|
Dear all,
Right now the Motion PLC is up and running. We are still working in the Vacuum one, today by midday should be also working. |
Vacuum PLC, posted by NEREA JARDON on 02 Mar 2017, 11:55
|
Dear all,
The Vacuum PLC is up and running and Karaboo guys have already started to work with it.
Thank you and regards |
Update of Component Priority list after weekly meeting, posted by Tobias Haas on 03 Mar 2017, 16:40
|
| |
Minutes of weekly SASE1 Readiness Meeting, posted by Tobias Haas on 03 Mar 2017, 16:46
|
| Here is the link to the minutes Minutes |
Karabo Deployment Documentation link, posted by Alessandro Silenzi on 08 Mar 2017, 18:26
|
Url to the readthedocs documentation:
https://goo.gl/vsz9hu |
Update of Tunnel Component Priority List after SASE1 Readiness Meeting, posted by Tobias Haas on 10 Mar 2017, 11:15
|
| |
Link to the redmin list of Tasks., posted by Alessandro Silenzi on 10 Mar 2017, 11:34
|
https://in.xfel.eu/redmine/projects/control-support/issues
Short Instructions:
- Add your task |