Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 7 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject
  101   04 Apr 2017, 18:49 Alessandro SilenziGeneralInformationUPDATE on Temperature sensors for EPS loop

Here are the updated values for the temperature sensors inn the EPS loop.

Now Thermocouples work!

FXE_XTD9_COLB/TSENS/T1 23.1
FXE_XTD9_COLB/TSENS/T2 23.2
FXE_XTD9_PBLM/TSENS/BLADE_BOTTOM 22.94
FXE_XTD9_PBLM/TSENS/BLADE_LEFT 23.0
FXE_XTD9_PBLM/TSENS/BLADE_RIGHT 23.0
FXE_XTD9_PBLM/TSENS/BLADE_TOP 22.98
SA1_XS3_SHUT/TSENS/T1 4.0
SA1_XS3_SHUT/TSENS/T2 4.0
SA1_XS3_SHUT/TSENS/T3 4.0
SA1_XS3_SHUT/TSENS/T4 4.0
SA1_XTD2_ABS/TSENS/T1 19.5
SA1_XTD2_ABS/TSENS/T2 19.6
SA1_XTD2_ATT/TSENS/A1 30.7
SA1_XTD2_ATT/TSENS/A2 1372.0
SA1_XTD2_ATT/TSENS/A3 30.3
SA1_XTD2_ATT/TSENS/A4 31.02
SA1_XTD2_ATT/TSENS/A5 31.96
SA1_XTD2_ATT/TSENS/A6 31.11
SA1_XTD2_ATT/TSENS/A7 30.75
SA1_XTD2_ATT/TSENS/A8 31.0
SA1_XTD2_ATT/TSENS/A9 31.4
SA1_XTD2_COLA/TSENS/T1 1372.0
SA1_XTD2_COLA/TSENS/T2 1372.0
SA1_XTD2_COLB/TSENS/T1 27.8
SA1_XTD2_COLB/TSENS/T2 1372.0
SA1_XTD2_CRL/TSENS/LENS_10_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_10_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_1_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_1_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_2_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_2_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_3_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_3_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_4_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_4_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_5_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_5_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_6_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_6_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_7_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_7_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_8_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_8_T2 850.0
SA1_XTD2_CRL/TSENS/LENS_9_T1 850.0
SA1_XTD2_CRL/TSENS/LENS_9_T2 850.0
SA1_XTD2_DPS1/TSENS/FLOW 20.3
SA1_XTD2_DPS1/TSENS/RETURN1 20.3
SA1_XTD2_DPS1/TSENS/RETURN2 20.1
SA1_XTD2_DPS3/TSENS/FLOW 44.2
SA1_XTD2_DPS3/TSENS/RETURN1 41.6
SA1_XTD2_DPS3/TSENS/RETURN2 44.2
SA1_XTD2_PBLM/TSENS/BLADE_LEFT 32.8
SA1_XTD2_PBLM/TSENS/BLADE_RIGHT 33.7
SA1_XTD2_PSLIT/TSENS/BLADE_BOTTOM_B4C 19.7
SA1_XTD2_PSLIT/TSENS/BLADE_BOTTOM_W 19.4
SA1_XTD2_PSLIT/TSENS/BLADE_LEFT_B4C 18.6
SA1_XTD2_PSLIT/TSENS/BLADE_LEFT_W 18.6
SA1_XTD2_PSLIT/TSENS/BLADE_RIGHT_B4C 19.3
SA1_XTD2_PSLIT/TSENS/BLADE_RIGHT_W 19.2
SA1_XTD2_PSLIT/TSENS/BLADE_TOP_B4C 19.4
SA1_XTD2_PSLIT/TSENS/BLADE_TOP_W 19.4
SA1_XTD9_PBLM/TSENS/BLADE_LEFT 23.68
SA1_XTD9_PBLM/TSENS/BLADE_RIGHT 24.13
SPB_XTD9_COLB/TSENS/T1 22.9
SPB_XTD9_COLB/TSENS/T2 1372.0
SPB_XTD9_DPS1/TSENS/FLOW 850.0
SPB_XTD9_DPS1/TSENS/RETURN1 850.0
SPB_XTD9_DPS1/TSENS/RETURN2 850.0
SPB_XTD9_DPS2/TSENS/FLOW 850.0
SPB_XTD9_DPS2/TSENS/RETURN1 850.0
SPB_XTD9_DPS2/TSENS/RETURN2 850.0
SPB_XTD9_PBLM/TSENS/BLADE_BOTTOM 23.21
SPB_XTD9_PBLM/TSENS/BLADE_LEFT 23.01
SPB_XTD9_PBLM/TSENS/BLADE_RIGHT 23.19
SPB_XTD9_PBLM/TSENS/BLADE_TOP 23.12
SPB_XTD9_SHUT/TSENS/T1 1372.0
SPB_XTD9_SHUT/TSENS/T2 1372.0
SPB_XTD9_SHUT/TSENS/T3 1372.0
SPB_XTD9_SHUT/TSENS/T4 1372.0

 

  102   04 Apr 2017, 19:25 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

Tomorrow at first hour, some hardware modules would added in Rack 1.1 and 1.9 in XTD2 in the Vacuum loop. Therefore the communication would be interrupted till the firmware is downloaded to the PLC, around 10h-10.30h should be running again to add the XGM XTD2 into the loop. Although, I will post a new entry to let you know.

Thank you,

  103   05 Apr 2017, 10:15 Tobias HaasGeneralInformationSchedule after 0930 Meeting

Tunnel Open.

Vacuum Loop:

Status:

  • Communication problem with Ion pump controllers is fixed after adjusting controller settings
  • Loop is now down to allow inclusion of XGM

EPS Loop:

Status:

  • Temperature sensors return reasonable values after EPS loop fix
  • EPS to MPS interface is working but fiber to central desy interface still lacking

Motion Loop:

Status:

  • Should be up for testing PBLMs and Imagers

Imagers

Status:

  • Test of FEL imager ok, but hampered by occasional slow response of the system
  • SR Imager needs work on the driver

Tasks for today:

  • Include XGM in Vacuum loop (N. Jardon, M. Planas, T. Matsopoulos, V. Bondar)
  • Test updated MC2 lib with PBLM in the tunnels (N. Gerasimova, M. Jidda)
  • Work on camera driver for SR imager (A. Koch and W. Ehsan)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers
  • Set up monitoring of temperatures and pressures overnight
  • Push DESY to get fiber connection to MPS (P. Gessler)

Tasks for tomorrow:

  • Terminals need to be added and firmware adjustments made in motion loop (take loop down as early as possible for one hour)
  • Test EPS inputs to MPS system with DESY people
  • Power down crate 1.15 for grounding. Could take longer than one day

Other topics

  • N. Jardon needs complete info of motor names in rack 1.18
  105   05 Apr 2017, 14:27 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

The XGM XTD2 is already into the Vacuum loop and the loop is running. We would continue with the interlock tests today in the afternoon, but would not affect to other parts of the Vacuum loop.

Also was requested to change the Karaboo names of the devices in XGM XTD2, therefore a firmware updated would be necessary and would be performed today in the afternoon after VAC-MPS communication tests.

Thank you!

  106   05 Apr 2017, 16:24 Nicola CoppolaXTD9Informationalio monocromator tests

test finshed.

both stages were moved.

voltage value and position read out from encoder opposite in directionality

some strange limitation on the postiion range seen.

both stages are now at around the 0 position with few mm error.

XD to ask alio/nanoomotion on the matter

XD will provide few lines of comment

  107   05 Apr 2017, 16:40 Tobias HaasGeneralInformationDESY wants to close XTD2 & XTD4 over the weekend...

I expect that some of us may need the weekend as a reserve (e. g. mirror installation). So we should probably say no. Let's discuss more tomorrow at 09:30 

  108   06 Apr 2017, 09:16 Andreas KochXTD2InformationImager

-

XTD2, FEL imager with Wajid

Screen, motor, switches - ok, minor braking switch issue.

LED, camera power – ok.

Filter, motor, parameter issue, should be solved now, to be tested again today.

EPS tests and SR imager tests, to be done.

 

XTD9 cameras, no power, will check today with Bernard.

 

  109   06 Apr 2017, 11:27 Tobias HaasGeneralInformationStatus and Schedule after 09:30 meeting

 Tunnel Open.

Mirrors:

Status:

  • Vacuum will be closed on M1
  • M2 installation tomorrow or latest on Monday

Vacuum Loop:

Status:

  • Loop is up
  • XGM was integrated but tests needed on the interlocks. Hence valves to DPS now in manual mode (overrides interlock)
  • Interface to MPS has been successfully tested
  • Need to test fast valve connection to VAC and to MPS (Status re cabling was unclear this morning)
  • A few pumps still  have communication problems (to be discussed between AE and CAS)

EPS Loop:

Status:

  • AE did most of the missing wiring
  • Description of EPS interlock still missing. It is planned to start with just one imager in for first beam commissioning
  • One fiber connection from Balcony room to DESY still to be done by DESY

Motion Loop:

Status:

  • Problem on ELMO motors with linear drive persists. Needs additional testing

Imagers

Status:

  • Both motors working on FEL imager
  • Work should now concentrate on SR imager

Karabo:

Status:

  • Problem in TCP implementation identified that is suspected to cause the long delays observed e. g. with the imagers. Now needs extensive testing
  • Still no data recording achieved
  • Stability still needs monitoring

 

 

Tasks for today:

  • Work on GUI for the vacuum loop (J. Eidam, V. Bondar)
  • Test XGM interlocks (N. Jardon, M. Planas, T. Matsopoulos)
  • Continue tests with PBLM in the tunnels (M. Jidda)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers (A. Silenzi)
  • Set up monitoring of temperatures and pressures overnight (A. Silenzi)
  • Push DESY to install fiber connection from Balcony rooms to MPS (P. Gessler)

Tasks for tomorrow:

  • Put XGM into the vacuum interlock
  • Perform careful testing of all interlock conditions for the vacuum

Other topics

  • Regular SASE1 readiness meeting at 09:00 tomorrow in XHQ E1.173
  • Need to perform tests with EPS interlock conditions
  • Need to test fast valve connection to VAC and to MPS
  • Gas system for diagnostics needs to be flushed
  110   06 Apr 2017, 13:36 Andreas KochXTD2Information motion loop not working !?

Has anyone an idea why the motion loop is not working? Thanks Andreas

  111   06 Apr 2017, 14:32 Andreas KochXTD2Information motion loop not working !?

Andreas Koch wrote:

Has anyone an idea why the motion loop is not working? Thanks Andreas

Hello Andreas,
please use redmine for bug reports. I opened a redmine issue for this:

https://in.xfel.eu/redmine/issues/16265

Please log in and give more details on what you experienced.

In case of emergency contact your main contact person Wajid.

Cheers

Alessandro

  112   06 Apr 2017, 14:45 Andreas KochXTD2Information motion loop not working !?

Andreas Koch wrote:

Andreas Koch wrote:

Has anyone an idea why the motion loop is not working? Thanks Andreas

Hello Andreas,
please use redmine for bug reports. I opened a redmine issue for this:

https://in.xfel.eu/redmine/issues/16265

Please log in and give more details on what you experienced.

In case of emergency contact your main contact person Wajid.

Cheers

Alessandro

 Thanks, Alessandro,

It's working again.
It was the Wifi that slowed down.
Andreas
 
  113   07 Apr 2017, 10:31 NEREA JARDONGeneralInformationMotion loop

I have made an update for the Motion loop requested to test correctly the Attenuators. Now the loop is running again.

Thank you and sorry for inconvenience.

  114   07 Apr 2017, 11:12 NEREA JARDONGeneralInformationEPS loop

Dear all, I will update EPS loop in order to integrate new hardware changes. I will post a new entry when the work is done.

Thank you!

  115   07 Apr 2017, 11:57 NEREA JARDONGeneralInformationEPS loop

Dear all, EPS loop is again up and running.

Thank you!

  116   07 Apr 2017, 16:02 Alessandro SilenziGeneralInformationTest on Karabo trunk show promising results

I have deployed the Karabo master (the HEAD of our development) in the control network for the Vacuum loop device server.

During last weeks Karabo was not able to cope with the data coming from the PLC for this loop (our biggest to date)
and would become unresponsive after 5 to 10 minutes.

The current system is online since 3.5 hours and is still responsive.

Please note:
This is a partial release and the GUI might show unwanted behaviour.
Please leave the vacuum loop untouched during the weekend.

In attachment you can find an example of unwanted behaviour and the DPS gui

Thank you very much and have a nice weekend!

Alessandro

Attachment 1: 02.png
02.png
Attachment 2: 12.png
12.png
  117   07 Apr 2017, 16:41 Tobias FreyermuthGeneralInformationHotfix for all loops (VAC, MOV, EPS)

Dear collogues,

we have added a hotfix to the framework, to make sure, that no motor can be moved if the feedback signals are missing. This update will be done due to the mentioned issue in the readiness meeting this morning.

We will update the loops again after the weekend, with a proper solution.

The hotfix will send all devices of a loop into error if the feedback of a terminal in the loop is missing.

I will write a new entire in the Logbook, if we are done with the updates.

 

Cheers,

    Tobias

  120   07 Apr 2017, 19:13 wajid ehsanXTD2InformationAcceptance test IMAGERS (FRIDAY 07-04-2017)

 

SA1_XTD2_IMGPII45:
 
1) MOTOR/SCREEN(DONE)
2) Check operation of range of movement, defined by end switches (DONE
3) Check repeatability (DONE)
4) Switch on/off LED (DONE)
5) Switch on/off camera (DONE)
6) Acquire images with a camera (DONE)
7) Hardware Trigger of camera (DONE)
8) EPS switch (DONE)

SA1_XTD2_IMGFEL:
 
1) Move all motors (DONE)
 1.1) MOTOR/SCREEN (DONE)
 1.2) MOTOR/FILTER (DONE)
3) Check operation of range of movement, defined by end switches (DONE)
 3.1)  END_ Switches/SCREEN (DONE)
 3.2) END_Switch/FILTER (DONE
4) Check repeatability (DONE)
5) Switch on/off LED. (DONE)
6) Switch on/off camera. (DONE)
7) Take images with a camera. (DONE)
8) Trigger of camera (DONE)
9) ESP switch (NOT WORKING, hardware issue, to be tested)
10) Braking switch_SCREEN_MOTOR (NOT WORKING, to be tested)

SA1_XTD2_IMGSR:
1)  Test motors.  (DONE)
 1.1) Motor/Screen (DONE)
 1.2) Motor/y (DONE)
 1.3) Motor/ Focus (DONE)
 1.4) Motor / IRIS (DONE)
2) End Switches:
 2.1 Motor/Screen (DONE)
 2.2 Motor/y (DONE)
3. Check repeatability(DONE)
4. Switch on/off LED (DONE)
5. Switch on/off camera (DONE)
6. Acquire images (NOT DONE, Photonic science camera device is not working but acquired images with eBus(low level driver))
7) EPS (DONE)
8) Braking switch_SCREEN_MOTOR (NOT WORKING)

 

  121   10 Apr 2017, 09:36 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

I will update the Vacuum loop in order to add the XGM XTD9 into it. It will be running in few minutes again.

Thank you.

  122   10 Apr 2017, 10:09 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

The Vacuum loop is running again, now with XGM XTD9 included. We will be testing interlocks in XGM XTD2, so could be needed another upload.

Thank you,

  123   10 Apr 2017, 10:47 Tobias HaasGeneralInformationSchedule after 09:30 Meeting

Tunnel Open.

Mirrors:

Status:

  • Both mirrors M1 & M2 installed
  • Vacuum being closed in M2 today should be ready for ion pumps tomorrow
  • Surveying work going on (see email by M. Schlösser below)

Vacuum Loop:

Status:

  • Needs reconfig for XGM in XTD9
  • Interlock tests on XGM in XTD2 should go on. 
  • 2 Turbopumps still have a communication problem (J. Tolkiehn is working on this)
  • 6 Ion pumps in XTD9 still have communication problems (list was given by AS to JE)
  • Systematic testing according to the list by J. Eidam with V. Bondar starting this afternoon

EPS Loop:

Status:

  • One terminal needs to be exchanged for FEL Imager 
  • Description of EPS interlock still missing. It is planned to start with just one imager in for first beam commissioning
  • One fiber connection from Balcony room to DESY still to be done by DESY. AFter this testing of communication should start

Motion Loop:

Status:

  • Quick fix for motors not stopping was deployed on Friday. Now TF is working on a better fix to be deployed this evening

Imagers

Status:

  • EPS switch on FEL imager should be checked after exchange of terminal
  • Photonics camera driver still not working but not critical for tunnel closure
  • Work should now concentrate on SR imager

Karabo:

Status:

  • New version with TCP fix needs to be deployed. This should also be done to the local software run by users.

 

Tasks for today:

 

Note: Loop reconfiguration and updates of Karabo to be done in the morning. Testing can resume after lunch. Status updates should please be recorded in the log

  • Reconfigure vacuum and motion loops (updates for XGM interlock, motors not stopping)
  • Replace broken terminal in EPS loop for FEL imager 
  • Continue test XGM interlocks (N. Jardon, M. Planas, T. Matsopoulos)
  • Go through systematic test of the vacuum components (J. Eidam, V. Bondar)
  • Continue tests with PBLM in the tunnels (M. Jidda)
  • Test motion system of the imagers in the tunnels (A. Koch and W. Ehsan)
  • Monitor stability and responsiveness of GUI Server and Log Servers (A. Silenzi)
  • Set up monitoring of temperatures and pressures overnight (A. Silenzi)
  • Test communication between XFEL and DESY MPS once fiber connection from Balcony rooms to MPS is available (B. Fernandes)

Tasks for tomorrow:

  • Put XGM into the vacuum interlock
  • Continues testing of all interlock conditions for the vacuum

Other topics

  • Surveying is going on for mirror chambers M1 and M2 in XTD2
  • We need a well defined startup configuration of PLC, Karabo, Parameters, List of devices (A. Silenzi)

Email by M. Schlösser re alignment

Hi Tobias, hi Markus, Hi Winni,

Tobias, we discussed briefly the schedule for the T9 and T10 beamlines for the next few days, when we met in the tunnel yesterday.

From what i understand it is impossible to finish T10 until April 11th from the alignment and vacuum side. And probably more important, this also holds true for T9. There is at least one major problem with the alignment of the mirror chambers of T9 in XTD2, which will need some additional days to solve.
From my understanding at least the T9 beamline should be closed and aligned before putting SASE1 in operation. While it will of course be possible to send electrons down to the XSDU2 dump, it will not be possible to send photons to the experimental hall with the current state of the beamline.

Since it is not possible to work in XTD10 while the SASE1 electron beamline is in operation, i would propose to also finish this beamline before SASE1 electron startup. Since there is major work to do in XTD10 to finish the beamline, there is no hope to  do the remaining work during maintenance days. Finishing the beamline would require a major shutdown of the SASE1 branch later.

Since there will be no alternative to send the beam to (e.g. SASE2) for the next year (?), it does not make sense to stop work in XTD10 now, just to continue later then, without any overall benefit for the machine.

Of course i don't have a complete overview of all the machine schedule, but from my point of view it would make more sense to finish work in the northern branch, at least to align all components and to close the vacuum system, even if that means some more weeks before the SASE1 startup.

cu
Markus