Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 29 of 30  Not logged in ELOG logo
ID Date Author Location Severity Subject
  37   03 Feb 2017, 08:48 Jan GrünertXTD2InformationUpdate WP74 cabling status (w5)

Information posted on behalf of Torben Falk (WP74 cabling)

Wir haben nun alle Kabel für den XGM in XTD2 am Beckhoff angeschlossen.

Alle Leitungen sind bereit zum einstecken in die jeweiligen Komponenten.
Es sind alle "valve connection boxes" angeschlossen, bis auf eine. Da besteht noch klärungsbedarf mit Florian. (ist aber auch schon am Beckhoff angeschlossen, nur device-seitig noch nicht)
 
Dementsprechend wäre der lokale Beckhoff Test möglich.
 
Ich habe mit Tobias Freyermuth geredet und der hat für den lokalen Beckhoff Test leider erst mitte / ende nächster Woche zeit..
 
Außerdem haben wir in XTD9 Kabel für den HiREX gewechselt. Da waren ein paar Kabel zu kurz. Die haben wir nun mit passenden ersetzt.

Andreas hat sich für die Timing verkabelung um die nötigen Kabel / Material gekümmert, die gebrauchten Längen habe ich ausgemessen und ihm zukommen lassen. Das Material soll Anfang nächster Woche da sein.
 
  36   02 Feb 2017, 18:29 Bernard BaranasicXTD2InformationWP74 components in XTD2 - electrical connections
Status of WP74 components testing and wiring this week:
 
On Monday we tested SR Imager and K-Mono:
- issue with motor connect pinouts was discovered and I wanted to correct pinout today, but K-Mono and SR imager motor connectors are Lemo with soldering pins, which make pin changing more difficult than crimp version...
- this is still not done (we can exchange all connectors to crimp version or temporary change pins on crate side).
 
This week done:
- connected SR imager EPS switch (on the imager - not yet in the crate)
- On XGM Gas Panel is installed new HUBA gauge, and I connected it to the crate (now everything from Gas Panel is connected to Beckhoff terminals in WP73_VAC crate - Rack 1.3).
- FEL imager - EPS switch is connected properly, but Digital Input terminal in WP73 EPS crate - Rack 1.5 is defect (doesn't work at all).
- I placed cable for EPS switches of MCP detector, but not placed in the Rack (Rack needs to be opened - Roxtec feedthrough is closed)
 
To be done:
- K-Mono - switch pins 1 and 2 on Motor connectors (Y-1, Y2 and X).
- SR imager - switch pins 1 and 2, and switch pins 7 and 8 on all Motor connectors.
- SR imager - EPS switch connect from WP74 crate to WP73_EPS crate (one cable inside crate).
- XGM vacuum to HV crate interlock (inhibit) is still not connected (I am waiting for Beckhoff terminal, but this connection was not tested yet).
- MCP detector - EPS switch cable needs to be laid inside Rack 1.7 (Rack needs to be opened - Roxtec feedthrough is closed).

- MCP detector - vacuum to HV crate interlock (inhibit) needs to be connected - Beckhoff crate is prepared - missing cable from MPOD to Beckhoff terminals.

  35   02 Feb 2017, 17:54 Jan GrünertGeneralInformationXGM resistors - progress w5

Presentation for SASE1readiness-Meeting

on XGM resistor issue progress (w5) and plan (w6)

Attachment 1: XGM-resistors.pptx
  34   02 Feb 2017, 17:46 Tobias HaasGeneralInformationStatus of component list as of 17:45
Attachment 1: Componets-XTD2-9.xlsx
  33   02 Feb 2017, 16:56 Tobias HaasGeneralInformationInstallation List Update

 Updates as of 2 Feb 16:30

Attachment 1: Components-XTD2-9.xlsx
  32   02 Feb 2017, 14:29 Richard BeanXTD9InformationSPB/SFX updates to component table

Table updated with status of SPB/SFX devices at end of XTD9 in preparation for SASE1 readiness meeting on 03.02.17

Attachment 1: Components-XTD2-9.xlsx
  31   01 Feb 2017, 17:42 Jan GrünertGeneralProblemXGM resistor issue - analysis progress

This is the current (w5) progress at DESY concerning the analysis of the serious XGM resistor issue (summary; a detailed report by DESY is available):

  • The new “pulser test” was verified at an operational XGMD at FLASH. The test method is (unfortuately) OK. This means that the test results with issues from last week on all our XGMs are REAL.
  • 25% of all resistors in XBPMs affected, 0% of resistors in HAMPs affected, no capacitors affected.
  • Since no HAMP resistors are damaged, damage by environmental conditions (venting, humidity etc.) can be excluded. The main differences to the affected resistors are the HV-conditioning and the experienced HV-values of the resistors (typically XBPM resisotors are tested up to 12kV, HAMP resistors each see much lower voltages).
  • An XGMD chamber at FLASH was tested-to-destruction-of-resistor by applying a large differential voltage (>3kV) between neighboring electrodes, e.g. on mesh_e and FC_e. These resistors (Caddock MS220) have a nominal voltage breakthrough rating of ~500V but never had issues. They are used in all our XGMs.
  • New, other resistors (Ohmite MOX-1N-13) with higher voltage breakthrough rating of 10kV were procured and arrived tuesday
  • The new resistors were built into the tested-to-destruction XGMD at FLASH, unit is now pumping, will be retested with applying pulsed HV (on both Caddoc and Ohmite resistors) when at suitable pressure.

Further plan (w5end + w6) concerning the XGM resistor issue:

  • If the new resistors survive the test, then next monday the XGM01 at HERA-S will be opened, the tested-defect resistors will be checked and replaced with the new resistors.
  • If all tests on XGM01 are then ok including an acceptable RGA, all other XGMs (XBPM chambers) will be opened and resistors exchanged. Even ok-tested resitors would be exchanged to avoid future unexpected failures. HAMP chamber resistors will not be exchanged (large number >20 of resistors, no failures).
  • If the RGA is not acceptable, the resistor Ohmite MOX-1N-16 is another alternative, but has increased delivery time.
  30   01 Feb 2017, 17:26 Jan GrünertXTD2InformationStatus of several XTD2 wiring tasks - on behalf of Bernard Baranasic
Dear all,

 

today I connected XGM Gas Supply to Beckhoff terminals in WP73 Vacuum crate in Rack 1.3.
On Gas Panel, HUBA gauge is still not replaced, so it is not connected, I talked to Florian yesterday and give him an idea how we can connect this gauge and other signals for Gebäudeleittechnik (trough wago terminals).
Next step for this crate should be connection to all pump controllers and other vacuum equipment, after this crate should be connected to the tunnel vacuum loop. I assume that Torben and Marc can do this together with AE and Vacuum group, so I didn't take any actions...

 

Additionally in this crate we should connect Inhibit signal from HV iseg crate, for this we need to add:
Proposal from NC:
"I did not test it, to 'create' a TTL we can use either
es9505+es2624 or es9505+es2124
the only difference is that the ES2124 is short-circuit proof, the ES2624  is not, that means that in this case a Flink fuse ~0.3A-0.5A should be inserted."
- WP74 don't have these terminal here and if we order now it will take some time (I am not sure what to do because we don't have proven connection).

 

In Rack 1.7 I connected Inhibit connection to WP73 vacuum crate (terminals EL9505 & EL2624), but cable from MPOD crate to Beckhoff crate is still not there. Torben said that he has connectors so I believe he can connect according to electrical drawings (these pages are added to XTD2 MCP drawings on Alfresco)

 

In Rack 1.5 I tested FEL imager EPS switch and find out that Beckhoff terminal DI (ES1008) is not working (24V is on input, but there is no light on LED, all channels are the same).
EPS switch is removed From FEL imager, and I will reconnect it to Normal Open connection.

 

Best Regards,

___________________________________________

Bernard Baranasic

  29   27 Jan 2017, 10:22 Thomas TschentscherXTD2InformationComponent table update
Attachment 1: Components-XTD2-9.xlsx
  28   27 Jan 2017, 09:25 Tobias HaasGeneralInformationSoftware Report

Post on behalf of S. Brockhauser

 Since I am in Grenoble and visiting ESRF, I will not be able to give you the report in person. Instead Alessandro can give you a Summary.

In fact:
- we did collect the full list of the Karabo names for all the equipments involved
- we have started our sprint and we are on track
As next things:
- we are collecting all the required Karabo(!) default parameters
- we plan to finish the sprint as planned and presented last time.
Until now we have not experienced and obstacle.

Best wishes
Sandor

  27   26 Jan 2017, 17:02 Tobias HaasXTD2ProblemXGM at XTD2 / issue with in-vacuum-resistor

Post on behalf of Jan Grünert:

 

during HV-tests on the installed XGMs, our DESY colleagues from Kai Tiedtkes team have found an issue with one of the electrodes / resistors inside one XGM vacuum chamber at XTD2.

 

Roughly, we know the following:

1)      If not repaired, we would lose at least the capability of monitoring shot-to-shot horizontal beam position at this XGM location. This is a lower-priority info.

2)      However, it’s not yet fully tested if other functionalities could be affected. In case the absolute calibrated intensity info is affected, then clearly we would have to repair.

3)      Since the cause of the resistor-irregularity is not understood, there is a risk to damage the other (operational) remaining resistors in the other chambers of the same XGM.

 

It is not yet fully clear 

a)      what is the cause for the irregular behavior (it concerns a resistor inside vacuum which dramatically changed its resistance, which apparently possibly might happen even during a correct dry-nitrogen venting),

b)      the entire consequences for operation with this XGM

c)       the effort/details of a potential repair (could include up to removing one of the four chambers off the girder out of the tunnel into a lab, certainly needs re-survey)

d)      if another XGM chamber is affected (so far tested 2 of 6).

 

The DESY colleagues are running various tests with us on the XGMs, also extending to all the other XGMs, to get answers to the above questions in order to allow a decision on “repair/not repair”. 

 

Since this concerns the internals of the high-prio XGM in XTD2, we could ask Kai Tiedtke to give us his brief 10min report and recommendation in the tomorrow SASE1Readiness Meeting. Should we request his presence / will you add him to the agenda ?

 

Best regards,

Jan

________________________________________

Dr. Jan Grünert

Group Leader X-ray Photon Diagnostics (WP74)

European XFEL GmbH

Holzkoppel 

  26   26 Jan 2017, 13:10 Tobias FreyermuthXTD2InformationModification of the vacuum PLC loop

The PLC program was modified and downloaded to the PLC, due to allow work on the XGM crate in rack 1.3.

The PLC vacuum loop includes now all vacuum crates in the racks from rack 1.1 to rack 1.7 except rack 1.3 (XGM)

  25   24 Jan 2017, 18:36 Alessandro SilenziGeneralInformationMore items in the master equipment list

Master Component list is being updated.

https://docs.xfel.eu/share/proxy/alfresco/api/node/content/workspace/SpacesStore/1c6c10cd-d741-410d-bd05-bb00944514dc/MasterEquipmentList.xlsx?a=true

Best regards

Alessandro

  24   24 Jan 2017, 08:23 Tobias HaasGeneralInformation Karabo Names in Vacuum component list

 Post on behalf of Alessandro Silenzi:

 

please find below the link to the first version of the master component list and the link to the direct download:
 
 
 
Please give your comments directly to me to avoid confusion.
 
The next steps after collecting your input, will be to implement a test in the Firmware project generation that will test the deviceIds against this list.
 
Best regards
 
Alessandro Silenzi
 
  23   24 Jan 2017, 08:21 Tobias HaasGeneralInformationKarabo Names in Vacuum component list

Post on behalf of Harald Sinn:

 for the non-vacuum part of WP73 we have the following situation: 

Last Friday Alessandro and myself had a meeting and agreed to use the names given in the document
 
 
(CAS inbox for software requirement documents)
 
The only change will be in the naming of the power supplies for the hard X-ray mono 
(which will be changes to analog input /output)
 
You can use the names is this document therefore already. However, Alessandro will 
create Excel tables out of it, which will be then used in the future for reference. 
Also the extension to SASE3/2 will be done in this Excel document. 
 
Best regards 
 
Harald
 
  22   24 Jan 2017, 08:17 Tobias HaasXTD2InformationSTATUS UPDATE: XTD2 Differential Pumping Modules running under interlock control

 Post on behalf of Raul Villanueva:

As we just finished the exhaustive testing and final adjustments of local
test and the interlock program for each of the turbopumps at each
Differential Pumping Sections in XTD2 Tunnel, we are happy to announce
that the system has been released and is up and running smoothly and under
control.  That means that the isolation gate valves in front of each
turbopump is open and therefore the latter is pumping already the beamline
as expected during the upcoming operation phase of the facility. That also
means that WP74, after having already received the wiring documentation
from the Vacuum Group can proceed with the same protocol to keep the whole
gas section in XTD2 in a consistent fail-safe status.

With this positive news, we wish you to have a nice evening,

Regards,

Raúl, Tobias and Nerea,

 

  21   09 Jan 2017, 10:47 Sabine CunisXTD2InformationVCTF-list updated

The VCTF-components-list  has been updated. Labels on components, as far as visible, are in accordance with names in list.

... please, check for consistency, when naming and labeling XGM components!

  20   03 Jan 2017, 08:46 Frederike WittmaackGeneralInformationMeeting Minutes 23 Dec 2016
Please follow the link to view the minutes: http://tinyurl.com/h3qspzz
  19   19 Dec 2016, 09:44 Frederike WittmaackGeneralInformationXGM Safe State Definition
as defined by Jan Grünert: available on Alfresco: XGM-safe-state.docx and available at N:\4all\intern\User data\wp74\Devices\11-1_XGMD\03 - Components\XGM-safe-state.docx
  18   19 Dec 2016, 09:32 Frederike WittmaackGeneralInformationMeeting Minutes 16 Dec 2016
http://tinyurl.com/zzzy7sd
ELOG V3.1.4-7c3fd00