519
|
27 Apr 2018, 10:21 |
Adriano Violante | General | Information | Lasing SASE3 | INFO
As reported by the PRC (J. Gruenert) during the operation meeting this morning, due to the first lasing attempt in SASE2 no lasing of SASE3 is to be expected until the middle of next week. |
62
|
07 Mar 2017, 11:09 |
Andreas Koch | XTD2 | Information | Karabo testing on Wednesday | As discussed with Wajid, I am availalbe tomorrow Wednesday the whole day to continue testing Karabo, motion loop. Wajid checked with Narea. I understand that there may be interruptions and that I have not first priority. Thanks, Andreas |
64
|
08 Mar 2017, 16:08 |
Andreas Koch | XTD2 | Problem | Karabo testing | End switch testing: the in-position end switch stopped devices working, also stopped gateway connection. Stroke of motor is not correct, parameter list to be checked. More details in "Improvements / bug list". |
65
|
08 Mar 2017, 16:18 |
Andreas Koch | XTD2 | Information | Karabo testing | Here the link to the detailed list of issues: https://docs.xfel.eu/share/page/site/xfelwp74/document-details?nodeRef=workspace://SpacesStore/1733b825-e62e-47af-abba-fdef1ff9485d |
310
|
03 Jul 2017, 20:53 |
Alessandro Silenzi | General | Information | Karabo for SASE1 topic restarted | Here attached the main SASE1 panel |
Attachment 1: 07.png
|
|
366
|
22 Aug 2017, 09:48 |
Hugo Silva Santos | General | Problem | Karabo down in tunnel | Dear All,
We have a issue on the control servers and we are already working on it...
Best,
Hugo |
367
|
22 Aug 2017, 10:24 |
Hugo Silva Santos | General | Problem | Karabo down in tunnel | Dear All,
We solved the incident and the services are running normally. We are still try to investigate, as far as we know we have some "zumbies" process running in the GUI servers and it was not consuming the HEATBEATs.
Hugo Silva Santos wrote: |
Dear All,
We have a issue on the control servers and we are already working on it...
Best,
Hugo
|
|
502
|
09 Apr 2018, 14:37 |
Adriano Violante | General | Information | Karabo deployment dates | FYI
Below the E-Mail from Hugo Santos with the Karabo deployment dates.
Dear All,
I would like to call your attention to the fact that we made Karabo 2.2.3 available last Monday (04/04, and the changelog 06/04). From the last Readiness Meeting, I got informed that we agreed and are allowed to proceed with the Karabo rollout planning on SASE3 and SASE2. (SASE1 still needs agreement):
- SASE3
- PRE-CONDITION: (AE) PLC version and (ITDM) DAQ should be interface-compatible, otherwise, the deployment will not be able to be performed. (No Karabo-DAQ and Karabo-PLC interface issues)
- Date: 13/04/2018 (Friday)
- Should be the first one because of the completeness of this system: VAC, PES, XGM and GAT loops, for instance, that have to be checked and run properly afterward.
- Downtime expected: 9:00 to 14:00.
- (AE) PLCs version and (ITDM) DAQ should be interface-compatible, otherwise, the deployment will not be able to be performed.
- No major change regarding DET systems
- CAS Members for this specific task: Chris and Wajid.
- SASE2
- PRE-CONDITION: SASE3 Deployment task must be done and Karabo 2.2.3 running with PLC and DAQ (No Karabo-DAQ and Karabo-PLC interface issues)
- Date: 16/04/2018 (Monday)
- Downtime expected: 11:00 to 13:00.
- (AE) PLCs version and (ITDM) DAQ should be compatible, otherwise, the deployment will not be able to be performed.
- No major change regarding DET system.
- CAS Members for this specific task: Chris and Wajid.
- SASE1
- PRE-CONDITION: SASE2 and SASE3 Deployment tasks must be done and Karabo 2.2.3 running with PLC and DAQ (No Karabo-DAQ and Karabo-PLC interface issues).
- Date: (17/04/2018 - Tuesday - to be agreed)
- Downtime expected: to be defined.
- (AE) PLCs version and (ITDM) DAQ should be compatible, otherwise, the deployment will not be able to be performed.
- No major change regarding DET systems.
- CAS Members for this specific task: Alessandro and Wajid
Finally, please, also see that as soon as we have the Karabo 2.2.3 running during the shutdown, we will have the most comfortable time to perform the setup, configurations and stabilize it, still, during the shutdown. This way we can handover the control system properly to the operators.
Please, if you do not agree or are not comfortable with something in this message, let me know as soon as possible. Otherwise, I will assume that it does not contain any showstopper and we (CAS) can proceed.
H.S. |
23
|
24 Jan 2017, 08:21 |
Tobias Haas | General | Information | Karabo Names in Vacuum component list | Post on behalf of Harald Sinn:
for the non-vacuum part of WP73 we have the following situation:
Last Friday Alessandro and myself had a meeting and agreed to use the names given in the document
(CAS inbox for software requirement documents)
The only change will be in the naming of the power supplies for the hard X-ray mono
(which will be changes to analog input /output)
You can use the names is this document therefore already. However, Alessandro will
create Excel tables out of it, which will be then used in the future for reference.
Also the extension to SASE3/2 will be done in this Excel document.
Best regards
Harald
|
320
|
07 Jul 2017, 08:24 |
Wolfgang Freund | General | Information | Karabo K-Mono-scenes | I am working this morning on following projects:
SA1_KMONO_SYSTEM
SA1_XTD2_KMONO
SA1_XTD2_IMGSR
SA1_XTD2_FLT
Please don't save these projects ! |
8
|
07 Nov 2016, 19:15 |
Alessandro Silenzi | XTD2 | Information | Karabo Installation back to normal | Karabo to PLC communication has been tested successfully in the SA1 Vacuum installation.
in attachment:
OK.png -> Initial Status, all OK
interlocked.png -> pump P10300I is turned off -> Setpoint -> off -> Valve automatically close and set "Interlock OK" to false
afteron.png -> pump P10300I is turned on again but-> Setpoint -> off -> Valve automatically close and set "Interlock OK" to false
backToNormal.png -> Like initial status but valves stay closed
|
Attachment 1: OK.png
|
|
Attachment 2: interlocked.png
|
|
Attachment 3: backToNormal.png
|
|
Attachment 4: afteron.png
|
|
66
|
08 Mar 2017, 18:26 |
Alessandro Silenzi | General | Information | Karabo Deployment Documentation link | Url to the readthedocs documentation:
https://goo.gl/vsz9hu |
537
|
25 Jun 2018, 09:45 |
Hugo Silva Santos | General | Information | Karabo 2.2.4 released (mainly for ITDM, AE and DET) + Deployment dates | Dear All,
I would like to inform that we released last Friday (22.06) the Karabo 2.2.4 version. We got around five days delayed to prioritize issues regarding Karabo-DAQ integration and MDL devices that were found in the last steps of the test cycle. However, fortunately, those issues are solved.
Based on this run, the new dates that we (CAS) are proposing to start the deployment in operation will be:
- SA3: 28.06, Thursday (CAS references: Chris, Wajid, and Valerii)
- SA2: 02.07, Monday (CAS references: Chris, Wajid, and Valerii)
- SA1 + SPB + FXE: 03.07, Tuesday (CAS references: Alessandro, Dennis, Gabriele, Wajid)
- SPB deployment should not impact AGIPD firmware test week, as agreed before.
- BKR: 28.06? (Wajid and Jan, could you please agree offline?)
- LAS, SQS and SCS dates have to be agreed with the respective contact persons.
-
Hugo
|
505
|
13 Apr 2018, 07:50 |
Adriano Violante | General | Information | Karabo 2.2.3 installation | Hi all, for your information below a message from Chris Youngman concerning Karabo 2.2.3 installations in SASE3.
"preparation work has concluded and we will definitely try to deploy Karabo 2.2.3 on SA3 machines TODAY 13.04.. SA3 s/w will not work from 8:00 on. Hopefully we will finish during the morning.
SA1 and SA2 installations should continue as normal." |
368
|
22 Aug 2017, 10:53 |
Hugo Silva Santos | General | Information | Karabo 2.1.15 in Test | Dear All,
I would like to report that we started today to test (internally in CAS) the Karabo 2.1.15 version.
We got delayed to prioritise and solve a showstopper issue related to GUI Client. If our tests succeed, we are foreseeing to finish the tests and release tomorrow.
Best,
Hugo |
149
|
18 Apr 2017, 13:21 |
Tobias Haas | General | Information | KW16 Accelerator Plans | Author: Decking
Goals:
- Operation with 10 GeV, 500 pC, 5 kA, 30 bunch
- Increase gradient limits in RF stations
- Technical comissioning of north branch
XTIN closed all week
XTL open till Tue, 11:00
XTD2 open till Tue, 15:00
XTD4 open till Tue, 15:00
XTD9&XTD10 open all week
|17/04 Mo M | Easter shutdown
|17/04 Mo A | Easter shutdown
|17/04 Mo N | Easter shutdown
|18/04 Tu M | Interlock pre-test CS8, set XTL interlock at 11:00, Injector beam operation
|18/04 Tu A | A2 calibration after phase shifter change, Beam operation to TLD 10 GeV, set interlock XTD2-XTD4
|18/04 Tu N | Beam operation to TLD 10 GeV, 30 bunches, 0.5 nC
|19/04 We M | Slice emittance in BC2; Magnet PS test XTD2-XTD4
|19/04 We A | BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4
|19/04 We N | BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4
|20/04 Th M | Collimation set-up; Magnet PS test XTD2-XTD4
|20/04 Th A | BCM, BAM EO, commissioning; Magnet PS test XTD2-XTD4
|20/04 Th N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC; Magnet PS test XTD2-XTD4
|21/04 Fr M | Collimation set-up with 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|21/04 Fr A | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|21/04 Fr N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|22/04 Sa M | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|22/04 Sa A | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|22/04 Sa N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|23/04 Su M | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|23/04 Su A | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|23/04 Su N | Beam operation to TLD 12 GeV, 30 bunches, 0.5 nC, 5 kA; Magnet PS test XTD2-XTD4
|24/04 Mo M | Beam set-up 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo A | Beam operation to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz
|24/04 Mo N | Beam operation to TLD 12 GeV, 1 bunches, 0.1 nC, 1 Hz |
124
|
10 Apr 2017, 12:31 |
Alessandro Silenzi | General | Information | KARABO Update maintainance | The karabo services will be down for an upgrade for an hour.
The access will resume at 13:30. |
358
|
08 Aug 2017, 13:10 |
wajid ehsan | General | Information | KARABO 2.1.13 | As previously announced we will deploy KARABO 2.1.13 in tunnel under topic SA1. The system will go down in 10 mins. I will announce it again as soon the system is up again.
Regards,
Wajid Ehsan |
359
|
08 Aug 2017, 15:25 |
wajid ehsan | General | Information | KARABO 2.1.13 | The system is up and running.
Regards,
Wajid |
324
|
10 Jul 2017, 14:35 |
Wolfgang Freund | XTD2 | Information | K-Mono control | During the first K-Mono test with Karabo on Friday the first goniometer THETA1 (Elmo controller) moved beyond the CW limit switch and stopped at the CCW switch. So the goniometer was trapped between both switches with a movement range of a few degrees. Movement of encoder and motor were opposite. This behaviour is not understood and under investigation.
Now the goniometer is back within the nominal range and movement of motor and encoder reading is consistent. CCW limit switch at 117.5° / CW limit switch at ~182°. |
|