Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 14 of 29  Not logged in ELOG logo
Entry   EPS loop, posted by NEREA JARDON on 07 Jul 2017, 13:24 
Dear all,

We need to update EPS SASE1 loop in order to finish the interlock communication for the experiments. I will do the update around 14h.

Thank you!
Entry   Karabo K-Mono-scenes, posted by Wolfgang Freund on 07 Jul 2017, 08:24 
I am working this morning on following projects:

SA1_KMONO_SYSTEM
SA1_XTD2_KMONO
Entry   Vacuum Loop, posted by NEREA JARDON on 06 Jul 2017, 12:49 
Dear all,

Sorry for the short notice, but we have to do an update of the Vacuum loop in order to get the neecssary interlock for the experiments done.
I will contact know WP74 and Vacuum group so they can be awared about their equipments.
    Reply   Vacuum Loop, posted by NEREA JARDON on 06 Jul 2017, 15:03 
Vacuum Loop is running again.

Thank you!




NEREA
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 06 Jul 2017, 08:51 
Dear all,

access to XTD9 has been extended until the Friday the 14.7. 14:00. Tunnel access schedule has been updated:

TAS
Entry   Motion loop update, posted by NEREA JARDON on 05 Jul 2017, 17:48 
Dear all,

In order to finish the configuration of part of Hirex devices, we need to make an update of the Motion loop tomorrow morning at 10am. Please
drive your devices to safe position before this hour.
Entry   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 10:12 
Dear all,

I have received a request from Konstantin Sukharnikov to break the Motion loop in XTD2 from Rack 1.5 in order to do checks in the CRLs. So you
will loose communication with almost the whole Motion loop in SASE1. I will let you know when they are finished.
    Reply   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 11:23 
We are finished. One encoder terminal has failed and needs replacing: rack 1.5 EC14




NEREA
JARDON wrote:



Dear all,
       Reply   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 11:47 
It will be replaced today around 1pm.Therefore Motion loop will be broken from this rack position.




NEREA
JARDON wrote:



We are finished. One encoder terminal has failed and needs replacing:
          Reply   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 14:07 
The encoder terminal in rack 1.5 has been replaced.




NEREA
JARDON wrote:



It will be replaced today around 1pm.Therefore Motion loop will be
Entry   Motion loop, posted by NEREA JARDON on 04 Jul 2017, 09:41 
Dear all,

Today we are planning to integrate part of Hirex motors into the Motion loop of SASE1. Therefore, the loop will be break, so you will loose communication
with whole XTD9 Motion part. I will back again to you when we are done,
Entry   Karabo for SASE1 topic restarted, posted by Alessandro Silenzi on 03 Jul 2017, 20:53 07.png
Here attached the main SASE1 panel
Entry   control servers maintenance, posted by Janusz Szuba on 03 Jul 2017, 18:22 
All control servers, brokers, dl and finally gateway were updated and restarted.
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 03 Jul 2017, 16:03 
Dear all,

based on the information from todays BKR-meeting and communication with Harald Sinn, I updated the TAS: https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Basically, Harald is trying to keep XTD9 open until middle of next week, he still has to talk to DESY...
Entry   Motion loop update, posted by NEREA JARDON on 03 Jul 2017, 11:01 
Dear all,

We will be working in the Motion loop till this afternoon. So as I said in the morning meeting, I will let you know when we have finished.

Thank you
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 03 Jul 2017, 10:26 
General


Accelerator was down all weekend due to cold compressors that were damaged in conjunction with the power outage on Friday
Since
0700 all interlocks are broken and tunnels are open.
Tunnels except XTD9 stay open until Thurday.
XTD9 can remain open longer


Availability
Entry   Network upgrade /information and problem, posted by Krzysztof Wrona on 03 Jul 2017, 10:13 
The upgrade of the switches is finished to the extend that it allows Advanced Electronic group to work on KMono (Nerea is informed)

However, during the upgrade of the network one switch got stuck and this is the switch in XTD2 tunnel. The IP network in the XTD2 tunnel is not
reachable at the moment (Beckhoff loops are fine) and we are going top the tunnel soon.
Entry   Network and servers maintenance, posted by Janusz Szuba on 30 Jun 2017, 15:33 
As discussed offline with NOC, Monday schedule was already fixed and not movable to Tuesday. Therefore, the network maintenance will take place on Monday
7:00 - 9:00.

During that time, no stable network is guaranteed.
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 30 Jun 2017, 11:33 
Data Acquisition and Data Archiving


K. Wrona summarised the basic ingredients of the system.
All components are ready and tested individually
Integration
in the instrument environment is needed and will be done first in the context of commissioning LPD in FXE starting from 5 July
DAQ and archiving
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 27 Jun 2017, 10:26 


Dear all,

according to Dirk Nölle access to XTD4 during the shutdown will be extended until Thursday.
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 26 Jun 2017, 15:52 
Dear all,

I tried to update the TAS to include the times for each XTD during the shutdown-week at the beginning of July. It is currently not entirely clear
when XTD9 and XTD10 will be searched, and as always this is subject to change...
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 26 Jun 2017, 10:57 
General:


​Beam was brought to all SASE1 hutches on Friday. Beam was available to both instruments splitting it with M3 until Sunday morning.
Afterwards SASE tuning was done and the beam should be back in the hutches some time today. Beam operation will continue this week with very low intensity.
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 23 Jun 2017, 11:11 




General


A low intensity beam is being put into the SASE1 intrument hutches in this order: SPB Optics, FXE Instrument, SPB Instrument
No
special precautions outside the hutches are needed due to the low intensity. 
The work will most likely not finish today. If necessary
Entry   Schedule for first beam SASE1 hutches, posted by Tobias Haas on 22 Jun 2017, 15:15 
It was just decided to put a very low intensity beam into the SASE1 hutches starting tomorrow morning at 8 AM. Both instruments declared that they are
ready to accept it. Due to the very low intensity no special measures need to be taken outside the hutches. SRP and D3 shall be in the experiment hall.
Harald Sinn shall coordinate beam activities from the BKR. Please note that the TC and S1R meetings take place as announced.