Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 13 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Location Severitydown Subject Text Attachments
  248   18 May 2017, 15:30 NEREA JARDONGeneralInformationOCD AE GroupDear all,

The OCD AE numbers for the following
  
  250   18 May 2017, 16:36 NEREA JARDONGeneralInformationMotion loopDear all,
I have already contacted Andreas
Koch, and Alessandro has contacted the BKR
  
  251   19 May 2017, 11:30 Tobias HaasGeneralInformationStatus and plans after SASE1 Readiness MeetingGeneral (T. Haas)

    Due to problems with interlock
cabling the approval date with the TÜV
  
  252   19 May 2017, 12:46 Monica ArestéGeneralInformationUpdate of Instrument component priority list






Normal
0
 170519_Instrument_Components-Priority-list.xlsx 
  253   19 May 2017, 15:42 Nicola CoppolaGeneralInformationAE OCD Mai 19 -- Mai 22AE on call service:
    Contact person:
       
  
  254   21 May 2017, 15:02 David HickinXTD2InformationCAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3Contacted at home 21:30 19.05. Request
for support starting SA1_XTD2_MCP/CDC/MCP3
on cppServer/sa1_utca_17.
  
  255   21 May 2017, 16:28 David HickinXTD2InformationCAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3


   
        
            
  
  256   21 May 2017, 16:29 David HickinXTD2InformationCAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3


   
        
            
  
  257   21 May 2017, 16:50 David HickinXTD2InformationCAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3


   
        
            
  
  259   22 May 2017, 11:06 Tobias FreyermuthGeneralInformationAE PLC OCDFrom now on the PLC OCD contact person
will have always the phone number:
  9 8040
  
  260   22 May 2017, 13:31 Tobias HaasGeneralInformationStatus and Plans after 09:30 Meeting[B]General:[/B]
[LIST]
[*]No break this week on Wednesday. (Wednesday
  
  261   24 May 2017, 09:06 Tobias HaasGeneralInformationReminder: SASE1 Readiness Dispatch @ 0930 todaysee you there    
  262   24 May 2017, 10:39 Tobias HaasGeneralInformationStatus after 0930 meeting General:

    DESY will try to lase
again at higher energies during the next
  
  263   26 May 2017, 18:01 Gabriele GiovanettiGeneralInformationCAS OCD phone numbers for the weekend
    Friday 7 PM - Saturday 8.00 AM   
: 98060
    
  
  264   27 May 2017, 16:31 Harald SinnGeneralInformationStatus of beam commissioningWe got the beam to the end of XTD9 onto
the SPB screen and FXE Pop-in (the SPB pop-in
does not work).
  
  265   29 May 2017, 16:30 Tobias HaasGeneralInformationStatus and Plans after 09:30 meeting General

    Photon tunnels are open
until Wednesday afternoon due to the flooding
  
  266   30 May 2017, 10:56 NEREA JARDONGeneralInformationVacuum LoopDear all,
It is needed to add two digital input
terminals in Rack 1.17 and 1.18 in XTD9 for
  
  267   30 May 2017, 11:08 NEREA JARDONGeneralInformationVacuum LoopDear all,
Sorry, my last message was not correct.
We will do the hardware changes when we have
  
  268   30 May 2017, 15:52 NEREA JARDONGeneralInformationVacuum LoopDear all,
We will run the update of the Vacuum
loop in the next half hour.
  
  269   30 May 2017, 18:14 NEREA JARDONGeneralInformationMotion loopDear all,
I will make an update of the Motion
loop in the next minutes, all the systems
  