Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 13 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject Text Attachments
  248   18 May 2017, 15:30 NEREA JARDONGeneralInformationOCD AE GroupDear all,

The OCD AE numbers for the following
  
  250   18 May 2017, 16:36 NEREA JARDONGeneralInformationMotion loopDear all,
I have already contacted Andreas
Koch, and Alessandro has contacted the BKR
  
  251   19 May 2017, 11:30 Tobias HaasGeneralInformationStatus and plans after SASE1 Readiness MeetingGeneral (T. Haas)

    Due to problems with interlock
cabling the approval date with the TÜV
  
  252   19 May 2017, 12:46 Monica ArestéGeneralInformationUpdate of Instrument component priority list






Normal
0
 170519_Instrument_Components-Priority-list.xlsx 
  253   19 May 2017, 15:42 Nicola CoppolaGeneralInformationAE OCD Mai 19 -- Mai 22AE on call service:
    Contact person:
       
  
  254   21 May 2017, 15:02 David HickinXTD2InformationCAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3Contacted at home 21:30 19.05. Request
for support starting SA1_XTD2_MCP/CDC/MCP3
on cppServer/sa1_utca_17.
  
  255   21 May 2017, 16:28 David HickinXTD2InformationCAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3


   
        
            
  
  256   21 May 2017, 16:29 David HickinXTD2InformationCAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3


   
        
            
  
  257   21 May 2017, 16:50 David HickinXTD2InformationCAS OCD: Support requested starting SA1_XTD2_MCP/ADC/MCP3


   
        
            
  
  259   22 May 2017, 11:06 Tobias FreyermuthGeneralInformationAE PLC OCDFrom now on the PLC OCD contact person
will have always the phone number:
  9 8040
  
  260   22 May 2017, 13:31 Tobias HaasGeneralInformationStatus and Plans after 09:30 Meeting[B]General:[/B]
[LIST]
[*]No break this week on Wednesday. (Wednesday
  
  261   24 May 2017, 09:06 Tobias HaasGeneralInformationReminder: SASE1 Readiness Dispatch @ 0930 todaysee you there    
  262   24 May 2017, 10:39 Tobias HaasGeneralInformationStatus after 0930 meeting General:

    DESY will try to lase
again at higher energies during the next
  
  263   26 May 2017, 18:01 Gabriele GiovanettiGeneralInformationCAS OCD phone numbers for the weekend
    Friday 7 PM - Saturday 8.00 AM   
: 98060
    
  
  264   27 May 2017, 16:31 Harald SinnGeneralInformationStatus of beam commissioningWe got the beam to the end of XTD9 onto
the SPB screen and FXE Pop-in (the SPB pop-in
does not work).
  
  265   29 May 2017, 16:30 Tobias HaasGeneralInformationStatus and Plans after 09:30 meeting General

    Photon tunnels are open
until Wednesday afternoon due to the flooding
  
  266   30 May 2017, 10:56 NEREA JARDONGeneralInformationVacuum LoopDear all,
It is needed to add two digital input
terminals in Rack 1.17 and 1.18 in XTD9 for
  
  267   30 May 2017, 11:08 NEREA JARDONGeneralInformationVacuum LoopDear all,
Sorry, my last message was not correct.
We will do the hardware changes when we have
  
  268   30 May 2017, 15:52 NEREA JARDONGeneralInformationVacuum LoopDear all,
We will run the update of the Vacuum
loop in the next half hour.
  
  269   30 May 2017, 18:14 NEREA JARDONGeneralInformationMotion loopDear all,
I will make an update of the Motion
loop in the next minutes, all the systems
  
ELOG V3.1.4-7c3fd00