  OPERATION-2025 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn, Page 4 of 5  Not logged in ELOG logo
ID Date Authordown Group Subject Text Attachments
  43   07 Apr 2025, 15:35 Jan GruenertPRCStability IssueSASE1 pulse energy drops slowly
three times

SASE1
XGM detects three times during the morning
 JG_2025-04-07_um_15.34.41.png 
  44   09 Apr 2025, 09:41 Jan GruenertPRCIssueSASE1 XTD2 attenuator arm issue

On monday 7.4.2025, one of the
SASE1 attenuator arms (SA1_XTD2_ATT/PNACT/A9)
  
  45   09 Apr 2025, 10:22 Jan GruenertPRCSA3 statusSASE3 Apple-X undulator cell 26
issue - SOLVED

During the night, an issue appeared
  
  51   14 Apr 2025, 09:50 Jan GruenertXPDStatusBeam Downtime

During last night, apparently the
photon beam was down in all SASE beamlines
 JG_2025-04-14_um_09.43.03.png 
  69   14 May 2025, 09:39 Jan GruenertPRCStatusDelayed start of SA1 (and SA3) beam delivery

The
beam delivery to the North branch (SASE1
/ SASE3) was delayed by 24h compared to the
 JG_2025-05-14_um_09.37.38.png 
  37   15 Mar 2025, 19:49 Harald SinnPRCStatusMID called and reported issue with Dachs
terminals at the user labs (probably no power).
TS was informed. Because the lab are
  
  40   03 Apr 2025, 07:34 Harald SinnPRCSA1 status7:20 FXE reports a problem with laser synchronisation
(yellow warning light and could not change
delay). BKR informs the DESY laser sync group. 
  
  41   06 Apr 2025, 06:33 Harald SinnPRCSA2 status5:49 HED called and they have problems
with the Laser Sync signal. A change of laser
delay is not possibe. We supsect that it
 LBsync1.jpgLBsync2.jpgLBsync3.jpgLBsync4.jpgLBsync5.jpg 
  42   07 Apr 2025, 07:19 Harald SinnPRCSA1 status7:15 SPB reports large background from
non-lasing SASE3 bunches. BKR is informed.  

7:50 BKR analysed situation. Everything
  
  4   30 Jan 2025, 13:59 Frederik Wolff-FabrisPRCSA3 statusOn 29.01 evening the SA3 pre-absorber was
interlocked due to M5 mirror.

With the help of Maurizio V., it
  
  7   31 Jan 2025, 12:43 Frederik Wolff-FabrisPRCSA3 statusA ZZ is organized to happen now, 31.01
at ~12:40, in order to reset a cabinet belonging
to one of the Apple-X undulators.
  
  9   01 Feb 2025, 15:40 Frederik Wolff-FabrisPRCStatusSaturday 01.Feb around 2AM machine went
down due to problems with cold magnet at
A20:
  
  80   12 Jun 2025, 07:35 Frederik Wolff-FabrisPRCStatusTHURSDAY 12..06:

At ~1:00AM on the night Wed-Thu the
cold compressors had an issue with their
  
  5   30 Jan 2025, 23:08 Chan KimSPBShift summaryX-ray delivery


11.0 keV, up to 178 pulses
at 564 kHz, 650 uJ.


Optical
  
  8   31 Jan 2025, 21:24 Chan KimSPBShift summaryX-ray delivery


11.0 keV, up to 352 pulses
at 1.1 MHz, 900 uJ.


Optical
  
  25   19 Feb 2025, 21:25 Chan KimSPBShift summaryX-ray delivery
-12.4 keV, 202 pulses, 0.5 MHz, 1mJ/pulse

Optical laser delivery
  
  26   20 Feb 2025, 23:29 Chan KimSPBShift summaryX-ray delivery


12.4 keV, 1.1mJ/pulse,
202 pulses/train at 0.56MHz
Focused
  
  53   17 Apr 2025, 01:39 Chan KimSPBShift summaryX-ray delivery


18.8 keV, 260 uJ pulse
energy


Optical
  
  72   23 May 2025, 23:34 Chan KimSPBShift summary**X-ray delivery**
- 9.34 keV, 1400-1600 uJ pulse energy

**Optical laser delivery**
  
  1   14 Jan 2025, 07:38 Andreas KochXPDSA3 statusThe image intensifier in the SQS Exit Slit
imager had been exchanged on request of SQS,
Thomas Baumann.
  