Group Selection Page
HELP
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Operation
PSPO
XO
TS
Migrated2Zulip
OPERATION-2025
OPERATION-2024
OPERATION-2023
OPERATION-2022
OPERATION-2021
OPERATION-2020
OPERATION-2019
SASE1-2018
SASE1-2017
Experiment data
OPERATION-2025 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn
Not logged in
List
|
Message ID:
53
Entry time:
17 Apr 2025, 01:39
Author:
Chan Kim
Group:
SPB
Subject:
Shift summary
X-ray delivery
18.8 keV, 260 uJ pulse energy
Optical laser delivery
No optical laser
Achievements/Observations
Experimental setup optimized, both instrumental side and PIXIE side
X-ray beam focused to the PIXIE and transmission measurement was done with several different PIXIE operation conditions.
Issues
No beam for ~4.5 hours due to ZZ.
X-ray beam not found with IRDa InlineMic after focusing X-ray beam to IRDa sample plane.
InlineMic Y motor is in error states. It has to be fixed during the day.
upstream kapton window for the downstream vacuum pipe broken. The glue has become loose. No damage by X-ray was visible.