ID |
Date |
Author |
Group |
Subject |
140
|
09 Aug 2024, 01:59 |
Jörg Hallmann | MID | Shift summary | optimized the SDL alignment
found timing of the upper (-520 ps) and lower branch (-514.5 ps) of the SDL
moved the upper branch by 3 ps (positive) and lost the beam on the merger crystal - difficult to get it back |
139
|
08 Aug 2024, 00:18 |
Jörg Hallmann | MID | Shift summary | optimization of seeding (still not as good as needed)
set position for the two color mode (difference 3-4 ev)
timing of the direct beam with diode and laser
timing of the direct beam with YAG and laser
alignment of the lower branch of the SDL
timing pf the lower branch beam with YAG and laser
issues:
intensity and spectral purity of the seeded beam not really good
alignment of the mirrors have been tricky (previous values did not work)
|
138
|
29 Jul 2024, 23:22 |
Romain Letrun | SPB | Shift summary | X-ray delivery
- 11.0 keV, 1-351 pulses @ 1.1 MHz, 300-1100 uJ.
- Continuously decaying average intensity through the day.
- Large intensity gradient with long trains.
Optical laser delivery
- 800 nm, 50 fs, 1-113 pulses @ 564 kHz.
- Stable delivery.
Achievements/Observations
- Completed detector programme.
Issues
- Difficulties with AGIPD online calibration. Solved by DOC/CAL.
|
137
|
29 Jul 2024, 06:45 |
Giuseppe Mercurio | SCS | Shift summary | ## Shift summary night July 28th-29th
Achievements:
- we saw signal on both MCPs (with a voltage of around 1500 V). We used the MCPs to measure XAS at Cu L edge at different theta angles from 120 deg (specular to MCPs) to 70 deg (facing hRIXS). At grazing angles the spectrum is a bit distorted, but just to see the edge is perfectly fine. If there is a diode on the way, the MCP sees still some fluorescence.
- we saw the direct beam at APD 8 with transmission 0.02 % and 55 V bias voltage.
- we saw signal also on diode 4 and APD5
- the detectors connected are: diode 2, diode 4, APD 5, MCP_BIG and MCP_SMALL
- we looked for signal at rixs on CoO, but it was too weak so we asked BKR to go to vertical polarization
- beam with vertical polarization was transported to the sample
- continie the optimization of hRIXS at Su and hr grating
Problems:
- XAS processor was not working, tried to change date source, but it didn't help.
- diode 6 could not see any signal, probably because it is obstractad by thte antenna back
Program for next shift:
- finish optimization at Cu edge hr grating
- optimize for Fe, at this geometry or rotated hRIXS. |
136
|
28 Jul 2024, 23:34 |
Romain Letrun | SPB | Shift summary | X-ray delivery
- 11.0 keV, 1-352 pulses @ 1.1 MHz, 600-1100 uJ.
- Even larger intensity gradient with long trains than yesterday.
Optical laser delivery
- 800 nm, 50 fs, 1 pulse.
- Stable delivery.
Achievements/Observations
- Finished AGIPD programme.
- Started JUNGFRAU programme.
Issues
- Poor beam delivery with more than a few bunches per train.
|
135
|
27 Jul 2024, 23:42 |
Romain Letrun | SPB | Shift summary | X-ray delivery
- 9.22 and 11.0 keV, 1-352 pulses @ 1.1 MHz, 600-1400 uJ.
- Large intensity gradient with long trains (>70% drop with 352 pulses @ 1.1 MHz).
- Very unstable delivery from 20:30 until 23:00.
Optical laser delivery
- 800 nm, 50 fs, 1-113 pulses @ 564 kHz.
- Stable delivery
Achievements/Observations
- Instrument alignment.
- AGIPD timing scan.
- AGIPD flat field measurement at 1.1 MHz.
Issues
- Twice more time required to collect AGIPD flat fields due to large intensity gradient in the train.
- XTD2 1.2 mm CVD unusable. Initially stuck in the beam, but could be retracted with the help of DOC/PLC OCD. |
134
|
27 Jul 2024, 09:10 |
Harald Sinn | PRC | Issue | SASE1: Solid attenuator att5 is in error. When it is tried to move it out, the arm lifts, but does not reach the final position before the software time-out. We increased the software time-out from 4 seconds to 7 seconds, which didn't help. We suspect that there is a mechanical problem that prevents the att5 actuator to reach the out position.
SPB states that it is ok to leave the attenuator arm in over the weekend, because they run mostly detector tests and don't require full intensity. |
133
|
24 Jul 2024, 15:22 |
Giuseppe Mercurio | SCS | Shift summary |
Shift summary (Natalia, Giuseppe)
Achievements:
- M1, M2 pitches adjusted
- Grating AX changed value during shutdown, encoder offsets have been recalibrated
- Set up SCS, 9mrad, HEPM, grating configuration
- Set up SCS, 9 mrad, HEPM, blank configuration
Problems:
- at 10am the mono translations gone in error. It was problem with fuse in ELMO crate in tunnel. Repaired (ZZ). Machine was log to set up, till end of shift, we lost ~5 hours from the shift.
|
132
|
24 Jul 2024, 11:35 |
Harald Sinn | PRC | Issue | The control rack of the soft mono at SASE3 has some failure. Leandro from EEE will enter the XTD10 at 12:00.
Beam will be interupted for SAS1 and SASE3.
Estimate to fix it (if we are lucky) is one hour.
Udate 12:30: Problem is solved (fuse was broken, replaced, motors tested)
Update 13:30: Beam is still not back, because BKR has problems with their sequencer |
131
|
24 Jul 2024, 10:26 |
Harald Sinn | PRC | Issue | In SASE2 undualtor cell 10 has issues. Suren K. will do a ZZ at 11:30 to fix it (if possible). Estimated duration: 1-3 hours.
Update 12:30: The problem is more severe than anticipated. Suren needs to get a replacement driver from the lab and then go back into the tunnel at about 14:00
In principle, the beam could be use dby HED until 14:00
Update 13:30: Beam was not put back, because energizing and de-energizing the magnets would take too much time. Whenever Suren is ready, he will go back into XTD1 and try to fix the problem.
Udate 17:30: Suren and Mikhail could do the repair and finish now th zz. A hardware piece (motor driver) had to be exchanged and it turned out that the Beckhoff software on it was outdated. To get the required feedback from Beckhoff took considerable time, but now everything looks good. |
130
|
23 Jul 2024, 17:17 |
Idoia | XRO | Shift summary |
- ZZ access at XTD10
- The LE PM X and HE PM X motors were checked and they are not physically moving. It was also noticed that the encoders numbers aren't changing. -> second ZZ was done and the problem was solved. (check entry https://in.xfel.eu/elog/XRO+Beam+Commissioning/412)
- The SQS exit slit was checked and the blades are moving but the macro to calculate the gap size isn't working. We left the blades in completely open state. The issue was solved, see entry https://in.xfel.eu/elog/XRO+Beam+Commissioning/401
- SA3, SQS alignment (with LE PM in compromised position)
- 20mrad LEPM Blank aligned, https://in.xfel.eu/elog/XRO+Beam+Commissioning/394
- 20mrad LEPM HR grating was aligned, https://in.xfel.eu/elog/XRO+Beam+Commissioning/395
- 13mrad LEPM blank was tested until M2-Pop-In (LE motor does not move to the 13 mrad setpoint), https://in.xfel.eu/elog/XRO+Beam+Commissioning/396
- Checking the components SA3
- SXP alignment
- Attempt to align @ 20 mrad, LE-PM, Blank (could not see reflection on M5 popin)
- LE-PM, blank reflection found on Mono-Popin, LE-PM motor position was changed, https://in.xfel.eu/elog/XRO+Beam+Commissioning/409
- SA2 alignment
- 2.1 mrad alignment to MID, then to HED ==> updated in the XRO setpoints "B" (2.1mrad B4C)
- Beam stability in this configuration recorded in Proposal 900450 run 1 (~ 5min), https://in.xfel.eu/elog/XRO+Beam+Commissioning/399
- SA2 PBLM grating
- Blade Right and Left were inserted at 2.1m rad condition, https://in.xfel.eu/elog/XRO+Beam+Commissioning/397
- no beam transmission ==> likely the grating hole is too low relative to the beam height,
- SA2 vibration tests
- SA1 beam aligned
- beam aligned for FXE and SPB, 2.3mrad offset at 9.3keV, https://in.xfel.eu/elog/XRO+Beam+Commissioning/404, https://in.xfel.eu/elog/XRO+Beam+Commissioning/408
|
129
|
22 Jul 2024, 15:20 |
Antje Trapp | XRO | SASE2 end of shift summary | Beam is now aligned back to HED for hand-over to Naresh (see picture)
points achieved:
-vibometer measurements on M2 at high energy, 2,1 and 3 mrad setting
-tried again to find beam through pblm grating, but no success |
Attachment 1: HED_beam__2024-07-22_15-19-15.png
|
|
128
|
22 Jul 2024, 15:27 |
Antje Trapp | XRO | SASE3 end of shift summary | this morning, ZZ was done together with Sylvia Huynh (EEE) to solve softmono pre-mirror motor issue https://redmine.xfel.eu/issues/177392
The issue was solved and also mechanical functionality of the stage was checked.
After ZZ, the beamline remained interlocked. Hutches will be searched and closed tonight to allow final checks on Tuesday |
127
|
18 Jun 2024, 13:03 |
Kelin Tasca | XRO | Compensation of M2 RY motor for the case of Piezo off | We plan to put the piezos of M2 off, in the (unprobable) case that this is the reason of the "jumps" in SASE3 trajectory.
Therefore, I measured the change on RY and RZ motors, to correct all the positions
Fig 1: initial position, Motors Ry=10.5425 and RZ=-14.7200 Piezo Ry =5 and Rz=5
Fig 2: Ry is compensated, Motors Ry=10.4990 and RZ=-14.72 Piezo Ry =0 and Rz=5
Fig 3: Rz is compensated, Motors Ry=10.4990 and RZ=-14.7574 Piezo Ry =0 and Rz=0
Differential values: RY needs to be adjusted by -0.0435 and Rz by -0.0374
|
Attachment 1: Screenshot_from_2024-06-18_13-16-14.png
|
|
Attachment 2: Screenshot_from_2024-06-18_13-18-15.png
|
|
Attachment 3: Screenshot_from_2024-06-18_13-20-06.png
|
|
126
|
14 Jun 2024, 01:53 |
Jörg Hallmann | MID | Shift summary | continue with Tempus tests
continue with PAM commissioning (first results of the working device at MID)
comments:
changed to 10 keV in order to use only one focussing lens in CRL2 and generating a smaller focus
issues:
vacuum issues in the MPC (reason: open roughing valve)
FSSS (hall sensor broken - exchange of the entire device planned for tomorrow) |
125
|
13 Jun 2024, 01:46 |
Jörg Hallmann | MID | Shift summary | alignment of the instrument including collimation and beam shaping
test of the tempus detector using standard samples with different rep rates, intensities & # of pulses
start commissioning of the PhotonArrivalMonitor (temporal & spatial overlap, white light spectrum) |
124
|
11 Jun 2024, 00:43 |
Abhisakh Sarma | SPB | Shift summary | **X-ray delivery**
- 7.0 keV, up to 202 pulses at 564 kHz, 1.0 mJ.
**Optical laser delivery**
- ns laser for jet illumination
**Achievements/Observations**
- Data collection completed for all the requested samples from user.
**Issues**
- Run repeater behave once abnormally. Run repeater started with 30 minutes duration, but the first run (run #238) stopped after 40 seconds and next run (run #239) started.
|
123
|
09 Jun 2024, 22:45 |
Chan Kim | SPB | Shift summary | X-ray delivery
- 7.0 keV, up to 202 pulses at 564 kHz, 1.0 mJ.
Optical laser delivery
- ns laser for jet illumination
Achievements/Observations
- Data collection for user sample through column
Issues
- Pressure spike while rotating nozzle tripped AGIPD
- Temperature of ASICs of Q2M1 module too low and not easy to turn it on (issue solved after changing the bath temperature to -27 degreeC)
- Julabo chiller issue again (In the end, set temperature changed to -29.5 degreeC and continued the experiment)
- Another 2 ASICs in Q2M2 and Q2M3 seem unhappy
|
122
|
09 Jun 2024, 22:21 |
Giuseppe Mercurio | SCS | Shift summary | Late Shift summary
Achievements:
- recovered the beam overlap
- changed lens position to have larger OL beam
- spatial overlap on YAG
- measured RIXS data delay scan at fixed photon energy
Problems:
- none |
121
|
08 Jun 2024, 23:20 |
Abhisakh Sarma | SPB | Shift summary | X-ray delivery
- 7.0 keV, up to 202 pulses at 564 kHz, 1.0 mJ.
- X-ray beam pointing changed at around 18:12 and it affects nano KB focus (from ~200nm to ~1um).
Optical laser delivery
- ns laser for jet illumination
Achievements/Observations
- Detector moved the most upstream position (~1.5 m sample to detector distance)
- BG measurement with water, buffer low salt
- Silver Behenate measurement for geometry file (mostly for detector distance)
- Data collection for different sample (pure) concentrations
|
|