Message ID: 154     Entry time: 25 Aug 2024, 22:37
Author: Tokushi Sato 
Group: SPB 
Subject: Shift summary 

X-ray delivery

-12.40 - 12.82 keV, XDT9 XGM ~0.85 mJ, 3 hours interruption by vacuum issue on XTD9

Optical laser delivery

-800 nm laser for jet visualization
-487 nm ns laser for pumping

Achievements/Observations

-Focus IRD
-Collected SFX data
 

Issues

-AGIPD chiller was down
-Issue with tunnel vacuum valves, at around 7 pm, ended shift early