ID Date Author Group Subjectdown Text Attachments
  25   13 Feb 2024, 08:55 Konopkova ZuzanaHEDExperiment summary*Achievements :
- Generally rather successful with
very high quality beam parameters
  
  95   05 May 2024, 00:25 Konopkova ZuzanaHEDExperiment summary
proposal 5700 finished on 04.05.
The experiment used 352 pulses at
4.5 MHz and 18 keV to X-ray heat
  
  127   18 Jun 2024, 13:03 Kelin TascaXROCompensation of M2 RY motor for the case of Piezo offWe plan to put the piezos of M2 off, in
the (unprobable) case that this is the reason
of the "jumps" in SASE3 trajectory.
 Screenshot_from_2024-06-18_13-16-14.pngScreenshot_from_2024-06-18_13-18-15.pngScreenshot_from_2024-06-18_13-20-06.png 
  143   11 Aug 2024, 00:13 Andreas GallerPRCAttentionEPS Interlock change for Mode30:
the 3 HIREX Interlock conditions had
been disabled
 Screenshot_2024-08-11_at_00.12.04.png 
  68   30 Mar 2024, 00:17 Björn Senfftleben (Resolved) Issues with DAQWe had some trouble with the DAQ. It was
not able to start runs properly.

We got the following error messages:
  