337
|
09 Sep 2023, 07:00 |
Erik Brambrink | HED | Shift summary |
Data taken from 11 to cryo failure
Beam
conditions stable
Timing scan
for different energy
Operation |
|
357
|
23 Sep 2023, 07:59 |
Oliver Humphries | HED | Shift summary | Shift summary from Monday 18th 7am until
Saturday 7am
MONDAY
Aligned |
|
362
|
23 Sep 2023, 23:31 |
Motoaki Nakatsutsumi | HED | Shift summary | During the morning shift (7am - 3pm), we
couldn't take any meaningful data due
to the issue of power glitch which caused |
|
390
|
15 Oct 2023, 04:43 |
Konopkova Zuzana | HED | Shift summary |
the initial 600-700 uJ of pulse
energy at the beginning of the user beamtime
dropped down to 300-350 uJ over night from |
|
391
|
16 Oct 2023, 05:05 |
Konopkova Zuzana | HED | Experiment summary | Beam parameters: 18.8 keV, 350-600 uJ,
1 pulse
Experiment: Shock compression experiments |
|
409
|
24 Oct 2023, 19:26 |
Thomas Preston | HED | Issue | Vacuum issue at HED
At 18:26 the vacuum failed in the
HED CRL3 chamber in the OPTs hutch. The vacuum |
|
423
|
28 Oct 2023, 14:52 |
Konopkova Zuzana | HED | Shift summary | Beam parameters: 18 keV, 1 pulse, 600 uJ
- user beamtime started Friday,
the 27th and going smoothly until now and |
|
433
|
03 Nov 2023, 02:08 |
Johannes Moeller | HED | Shift summary |
stable 18 keV SASE delivery
measurement
of siemens star in the morning
alignment
of phase plate for the nano focussing lenses
testing |
|
14
|
02 Feb 2023, 09:25 |
Peter Zalden | FXE | Shift summary | FXE bring-up, summary of shifts 31.1. and
1.2.:
Beam delivery (11.5 GeV) |
|
51
|
22 Feb 2023, 14:53 |
Peter Zalden | FXE | Stability Issue | Instability observed today at 14:05, reported
to PRC and BKR, including RC: We saw RMS
jitter amplitude of up to 4 mm at FXE imager. |
|
127
|
07 Apr 2023, 23:57 |
Yifeng Jiang | FXE | Issue | After receiving beam from SPB, we noticed
that there is a werid shape of beam in the
FEL imager which was not observed yesterday. |
|
130
|
08 Apr 2023, 23:44 |
Yifeng Jiang | FXE | Issue | We notice that 0.5 mm Silicon ATT in SASE1
causes holo beam profile in FEL imager. Maybe
this silicon att has been damaged. |
|
212
|
28 May 2023, 23:15 |
Fernando Ardana | FXE | Shift summary | User proposal 3273:
X-ray delivary
We
use several deliveraly modes:
Continous |
|
346
|
18 Sep 2023, 19:14 |
Yifeng Jiang | FXE | Issue |
We found that the x-ray pulse energy
dropped a lot when we changed the undulator
from 5.5 keV to 5.45 keV. We called BKR to |
|
349
|
20 Sep 2023, 19:42 |
Peter Zalden | FXE | Issue | Connerning the phase shifter adjustment
after undulator gap scan via karabo:
At 19:30 FXE tested the scan change |
|
358
|
23 Sep 2023, 08:14 |
Peter Zalden | FXE | Issue | FXE interlock in fault state. See photo
attached with original error message from
6:53h. It cannot be reset by acknowledging. |
|
367
|
24 Sep 2023, 09:16 |
Peter Zalden | FXE | Shift summary | Summary for sept., 23rd
6:55 SPB just handed the beam over
to FXE when the power glitch killed the interlocks |
|
368
|
24 Sep 2023, 09:24 |
Peter Zalden | FXE | Shift summary | 7:00 Power glitch during SPB operation
- they were supposed to hand the beam back
at 7:30h |
|
19
|
29 Oct 2022, 11:03 |
Jaydeep Patel | | Jet alignment test- obeserver |
Nozzle
type
Nozzle |
|
21
|
09 Feb 2023, 01:11 |
Jörg Hallmann | | Shift summary Feb 8th | stable beam at 9kev (about 1.1 mJ)
checks of the sample environment
required for the upcoming user experiment |
|
|