Message ID: 367     Entry time: 24 Sep 2023, 09:16
Author: Peter Zalden 
Group: FXE 
Subject: Shift summary 

Summary for sept., 23rd

6:55 SPB just handed the beam over to FXE when the power glitch killed the interlocks and brought down ACC

11:30 After a lot of communication with PRC, Wolfgang Clement and DOC, the beam is back in SA1. We request change to 5.5 keV

  • It took most time to get the AIBS recovered
  • Interlock was reset by Wolfgang Clement on-site
  • Pandora X-05 in SXP hutch had no power, but recovered after TS restored power in SA3

12:30 We finished alignment and collected some user data (XRD)

16:00 Failure of the optical laser shutter in ILH. Seems not operational.

  • Adhoc procedure is being established to circumvent the faulty laser shutter (coordinated with SLSO, LSO, GL and Management)

18:00 FXE is able to take user data again (XAS)

23:30 Beam handed over to SPB (thanks for the extra time to finish a promising measurement)

 