ID Date Author Groupdown Subject Text Attachments
  401   21 Oct 2023, 23:34 Sergii, GiacomoSCSLate shift summary 21.10.2023Achievements:
-Collecting TR-RIXS data for different
fluencies and delay range
  
  403   22 Oct 2023, 07:34 Laurent, PhuongSCSnight shift summary, 22.10.2023
Night
shift summary 22.10.2023

Laurent,
Phuong
  
  404   22 Oct 2023, 13:21 Benjamin van KuikenSCSShift summaryMorning shift
Summary 22.10.2023

Achievements


Checked beam alignment
  
  406   23 Oct 2023, 01:38 Sergii , GiacomoSCSLate shift summary 22.10.2023Achievements
-Check XAS and static RIXS after the
beam was back
  
  408   23 Oct 2023, 06:46 Laurent MercadierSCSNight shift summary, 23.10.2023 

  
  414   25 Oct 2023, 15:10 Sergii, TeguhSCSMorning Shift Summary, 24.10.2023
Morning
Shift Summary, 24.10.2023

Achievements:


Re-aligned the beamline
  
  415   25 Oct 2023, 15:18 Sergii, TeguhSCSMorning Shift Summary, 25.10.2023
Morning
Shift Summary, 25.10.2023

Achievements:


Re-aligned FEL beam pointing
  
  417   26 Oct 2023, 07:13 Andreas Scherz / Eugenio ParisSCSnight shift summaryNight shift summary

Achievements:
- Recovered time0 on SiN (time0 moved
  
  418   26 Oct 2023, 15:03 Sergii, TeguhSCSMorning shift summary, 26.10.2023
Morning
shift summary, 26.10.2023

Achievements:


Continued measuring tr-RIXS
  
  420   26 Oct 2023, 23:25 Robert CarleySCSLate shift summary, 26.10.2023
Achievements:


Continued with tr-RIXS


No
problems
  
  444   12 Nov 2023, 07:24 Benjamin van KuikenSCSNight shift summary# Shift Summary

Achievements
 - Found RIXS signal from CuO
 p6696-r59.png 
  445   13 Nov 2023, 07:16 Loic Le GuyaderSCSshift summary# Shift Summary

Achievements
 - Measured elastic line with
  
  3   16 Jan 2023, 19:50 Jan GruenertPRCIssueProblem: Beam operation in SASE2
is prohibited by SEPS / MPS
Origin of problem: HED-CRL3
 JG_2023-01-16_um_16.30.12.pngJG_2023-01-16_um_16.30.50.png 
  4   17 Jan 2023, 10:25 Jan GruenertPRCIssueSASE3 peration issue - SOLVED

 

Controls
issue, the machine cannot make beam in SASE3.

From
BKR / DOOCS the problem description is: Big
 JG_SASE3_no_beam_permission_2023-01-17_09-13-31.png 
  6   22 Jan 2023, 18:40 Jan GruenertPRCIssueSASE1 blocked to 1 bunch/train
by EPS interlock (sic, not 2 but 1)
--- PARTIALLY RESOLVED
 JG_2023-01-22_um_17.43.36.pngJG_2023-01-22_um_18.17.31.pngJG_2023-01-22_um_18.23.20.pngJG_2023-01-22_um_18_1.37.21.png 
  7   23 Jan 2023, 10:43 Jan GruenertPRCStatusStatus of machine SASE tuning
(just before switching off for monday maintenance):

 JG_2023-01-23_um_10.04.56.png 
  8   25 Jan 2023, 08:40 Raśl Villanueva-GuerreroPRCAll SASE's - SEPS Interlock Test - Results, Status & Upcoming ScheduleDear all,

please find here a summary of the
status on this critical topic provided yesterday
  
  9   25 Jan 2023, 08:44 Raśl Villanueva-GuerreroPRCZZ Access on 24th January (19:30h) - Replacement of Motor on SASE2 Undulator - Cell 17 Phase ShifterDear all,

last evening Suren Karabekyan and
myself did a short notice ZZ access to XTD1.
  
  17   05 Feb 2023, 15:18 Harald SinnPRCIssue15:15  SCS called and reported an
issue with one of the motors of the SCS exit
slit. DOC already looked at the problem and
  
  26   11 Feb 2023, 13:55 Andreas GallerPRCStatusGun Modulator Problems

Gun Trip at 11:23 and since then
the Modulator trips after each restart.
  