470
|
30 Jul 2024, 10:38 |
Antje Trapp | | Solid attenuator arm 5 limit switch | On 27th of July, it was reported that arm
5 of the solid attenuator did not stay
in 'out' position when retracted, |
6x |
469
|
18 Apr 2024, 23:19 |
Jan Gruenert | PRC | Issue | 22h55:
HED informs that they have issues
with the HED pulse picker in XTD6. It affects |
|
468
|
26 Nov 2022, 10:40 |
Wolfgang Freund | XPD | Diamond detector / DDM commissioning | beam: 30 keV / 30 uJ
reduce to single bunch for insertion
put FEL imager in |
|
467
|
26 Jan 2024, 15:24 |
Antje Trapp | XRO | end of shift summary | Vertical motors of M3 now calibrated in
first iteration and gemetrical neutral calibrated
to 0 in motor settings!!! |
|
466
|
25 Jan 2024, 14:57 |
Antje Trapp | XRO | end of shift summary | It was possible to align to HED in parasitic
mode to seeding tests
mirror horizontal position (coating |
|
465
|
24 Jan 2024, 14:00 |
Antje Trapp | XRO | scanning for HED beam | We found reflection of M3 on M2 popin,
but could not locate the beam on HED PBLM
nor HED_XTD6_SDLBM-1 |
|
464
|
28 Nov 2023, 19:36 |
Jan Gruenert | XPD | Status | Ramp down activities completed
by XPD. References:
SASE1
https://in.xfel.eu/elog/SASE1+technical+commissioning/2204
https://in.xfel.eu/elog/SASE1+technical+commissioning/2205
https://in.xfel.eu/elog/SASE1+technical+commissioning/2206
SASE2
https://in.xfel.eu/elog/SASE2+technical+commissioning/1206
...until...
https://in.xfel.eu/elog/SASE2+technical+commissioning/1209
SASE3
https://in.xfel.eu/elog/SASE3+technical+commissioning/2220
https://in.xfel.eu/elog/SASE3+technical+commissioning/2221
The |
|
463
|
26 Nov 2023, 23:26 |
Adam Round | SPB | Shift summary | X-ray delivery
16.9 keV, up to 30 pulses
and 1.1 MHz for alignment, 1 pulse for data |
|
462
|
25 Nov 2023, 23:45 |
Chan Kim | SPB | Shift summary | X-ray delivery
16.9 keV, up to 30 pulses
and 1.1 MHz for alignment, 1 pulse for data |
|
461
|
25 Nov 2023, 19:56 |
Chan Kim | SPB | other | Beam drift in the horizontal direction
(XTD9_XGM).
From ~16:00, X-ray beam started |
|
460
|
24 Nov 2023, 23:11 |
Chan Kim | SPB | Shift summary | X-ray delivery
16.9 keV, up to 30 pulses
and 1.1 MHz for alignment, 1 pulse for data |
|
459
|
24 Nov 2023, 20:48 |
Chan Kim | SPB | other | Beam drift in the horizontal direction
(XTD9_XGM x position) started at around 10am
and continuously drifted until 16:00. |
|
458
|
24 Nov 2023, 05:07 |
Bjoern Senfftleben | | Sample Camera got stuck (likely at 11pm) and was only noticed at 5am | After going in and reconnecting the camera,
we observe att. 1.
|
|
457
|
23 Nov 2023, 23:12 |
Adam Round | SPB | Shift end | Staff: AR, MS, DM, KK, RL, RdW
X-ray delivery
16.9 keV, up to 30 pulses |
|
456
|
23 Nov 2023, 22:15 |
Jörg Hallmann | MID | Shift summary |
progress
with the Damnit - XPCS analysis test with
various samples (SiO2, Ludox etc.) |
|
455
|
22 Nov 2023, 23:18 |
Raphael de Wijn | SPB | Shift summary | X-ray delivery
16.9 keV, up to 30 pulses
and 1.1 MHz for alignment, 1 pulse for data |
|
454
|
22 Nov 2023, 22:48 |
Johannes Moeller | MID | Shift summary |
*Tests
for online XPCS pipeline ongoing
*beam optimization with power slits, |
|
453
|
22 Nov 2023, 10:19 |
Johannes Moeller | MID | Issue | The Si 0.5mm absorber of XTD1 attenuator
seems to be damaged. First screenshot is
with that one inserted. In the second screenshot, |
|
452
|
21 Nov 2023, 23:29 |
Adam Round | SPB | Shift end | Staff: AR, MS, DM, RL, RdW
X-ray delivery
16.9 keV, up to 30 pulses |
|
451
|
20 Nov 2023, 07:12 |
Jayanath Koliyadu | SPB | Shift end | X-ray delivery
1.3-1.7 mJ, 10.7 keV, 1-100
pulses, stable delivery
Optical |
|
|