Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 7 of 30  Not logged in ELOG logo
ID Date Author Locationdown Severity Subject
  11   14 Nov 2016, 14:10 Frederike WittmaackGeneralInformationMeeting Minutes 11 Nov 2016
http://tinyurl.com/juhjcbf
  12   24 Nov 2016, 11:38 Frederike WittmaackGeneralInformationMeeting Minutes 17 Nov 2016
http://tinyurl.com/hxaxdm9
  14   02 Dec 2016, 11:46 Frederike WittmaackGeneralInformationMeeting Minutes 25 Nov 2016
http://tinyurl.com/jydty26
  15   02 Dec 2016, 11:47 Frederike WittmaackGeneralInformationRemote access to control network form
http://tinyurl.com/jskzj2h
  16   07 Dec 2016, 17:09 Frederike WittmaackGeneralInformationMeeting Minutes 02 Dec 2016
http://tinyurl.com/hzq7ats
  17   09 Dec 2016, 15:31 Frederike WittmaackGeneralInformationMeeting Minutes 09 Dec 2016
http://tinyurl.com/gqykf7z
  18   19 Dec 2016, 09:32 Frederike WittmaackGeneralInformationMeeting Minutes 16 Dec 2016
http://tinyurl.com/zzzy7sd
  19   19 Dec 2016, 09:44 Frederike WittmaackGeneralInformationXGM Safe State Definition
as defined by Jan Grünert: available on Alfresco: XGM-safe-state.docx and available at N:\4all\intern\User data\wp74\Devices\11-1_XGMD\03 - Components\XGM-safe-state.docx
  20   03 Jan 2017, 08:46 Frederike WittmaackGeneralInformationMeeting Minutes 23 Dec 2016
Please follow the link to view the minutes: http://tinyurl.com/h3qspzz
  23   24 Jan 2017, 08:21 Tobias HaasGeneralInformationKarabo Names in Vacuum component list

Post on behalf of Harald Sinn:

 for the non-vacuum part of WP73 we have the following situation: 

Last Friday Alessandro and myself had a meeting and agreed to use the names given in the document
 
 
(CAS inbox for software requirement documents)
 
The only change will be in the naming of the power supplies for the hard X-ray mono 
(which will be changes to analog input /output)
 
You can use the names is this document therefore already. However, Alessandro will 
create Excel tables out of it, which will be then used in the future for reference. 
Also the extension to SASE3/2 will be done in this Excel document. 
 
Best regards 
 
Harald
 
  24   24 Jan 2017, 08:23 Tobias HaasGeneralInformation Karabo Names in Vacuum component list

 Post on behalf of Alessandro Silenzi:

 

please find below the link to the first version of the master component list and the link to the direct download:
 
 
 
Please give your comments directly to me to avoid confusion.
 
The next steps after collecting your input, will be to implement a test in the Firmware project generation that will test the deviceIds against this list.
 
Best regards
 
Alessandro Silenzi
 
  25   24 Jan 2017, 18:36 Alessandro SilenziGeneralInformationMore items in the master equipment list

Master Component list is being updated.

https://docs.xfel.eu/share/proxy/alfresco/api/node/content/workspace/SpacesStore/1c6c10cd-d741-410d-bd05-bb00944514dc/MasterEquipmentList.xlsx?a=true

Best regards

Alessandro

  28   27 Jan 2017, 09:25 Tobias HaasGeneralInformationSoftware Report

Post on behalf of S. Brockhauser

 Since I am in Grenoble and visiting ESRF, I will not be able to give you the report in person. Instead Alessandro can give you a Summary.

In fact:
- we did collect the full list of the Karabo names for all the equipments involved
- we have started our sprint and we are on track
As next things:
- we are collecting all the required Karabo(!) default parameters
- we plan to finish the sprint as planned and presented last time.
Until now we have not experienced and obstacle.

Best wishes
Sandor

  31   01 Feb 2017, 17:42 Jan GrünertGeneralProblemXGM resistor issue - analysis progress

This is the current (w5) progress at DESY concerning the analysis of the serious XGM resistor issue (summary; a detailed report by DESY is available):

  • The new “pulser test” was verified at an operational XGMD at FLASH. The test method is (unfortuately) OK. This means that the test results with issues from last week on all our XGMs are REAL.
  • 25% of all resistors in XBPMs affected, 0% of resistors in HAMPs affected, no capacitors affected.
  • Since no HAMP resistors are damaged, damage by environmental conditions (venting, humidity etc.) can be excluded. The main differences to the affected resistors are the HV-conditioning and the experienced HV-values of the resistors (typically XBPM resisotors are tested up to 12kV, HAMP resistors each see much lower voltages).
  • An XGMD chamber at FLASH was tested-to-destruction-of-resistor by applying a large differential voltage (>3kV) between neighboring electrodes, e.g. on mesh_e and FC_e. These resistors (Caddock MS220) have a nominal voltage breakthrough rating of ~500V but never had issues. They are used in all our XGMs.
  • New, other resistors (Ohmite MOX-1N-13) with higher voltage breakthrough rating of 10kV were procured and arrived tuesday
  • The new resistors were built into the tested-to-destruction XGMD at FLASH, unit is now pumping, will be retested with applying pulsed HV (on both Caddoc and Ohmite resistors) when at suitable pressure.

Further plan (w5end + w6) concerning the XGM resistor issue:

  • If the new resistors survive the test, then next monday the XGM01 at HERA-S will be opened, the tested-defect resistors will be checked and replaced with the new resistors.
  • If all tests on XGM01 are then ok including an acceptable RGA, all other XGMs (XBPM chambers) will be opened and resistors exchanged. Even ok-tested resitors would be exchanged to avoid future unexpected failures. HAMP chamber resistors will not be exchanged (large number >20 of resistors, no failures).
  • If the RGA is not acceptable, the resistor Ohmite MOX-1N-16 is another alternative, but has increased delivery time.
  33   02 Feb 2017, 16:56 Tobias HaasGeneralInformationInstallation List Update

 Updates as of 2 Feb 16:30

Attachment 1: Components-XTD2-9.xlsx
  34   02 Feb 2017, 17:46 Tobias HaasGeneralInformationStatus of component list as of 17:45
Attachment 1: Componets-XTD2-9.xlsx
  35   02 Feb 2017, 17:54 Jan GrünertGeneralInformationXGM resistors - progress w5

Presentation for SASE1readiness-Meeting

on XGM resistor issue progress (w5) and plan (w6)

Attachment 1: XGM-resistors.pptx
  38   03 Feb 2017, 14:22 Frederike WittmaackGeneralInformationMeeting Minutes 03 Feb 2017
http://tinyurl.com/hwu4esq
  39   09 Feb 2017, 13:57 Tobias HaasGeneralInformationUpdate of installation list for tomorrow's S1R Meeting

 Please check if correct. I mark all newly done things in yellow!

Attachment 1: Componets-XTD2-9.xlsx
  40   09 Feb 2017, 17:16 Tobias HaasGeneralInformationStatus of Differential Pumping

Post on behalf of R. Villanueva

please find attached the updated status of the Differential Pumping
Modules in SASE 1. Just a few comments.

1. As you can imagine, no progress after KW4 in XTD2: system is ready to
deploy Karabo.
2. In XTD9, we have been pushing forward to finish the local test with AE.
Right now, everything has passed the local test except 3 vacuum gauges
that will be rechecked after the meeting. The main reasons for the little
progress (84%----->87%) are:

  a) more problems than expected with the cabling.
  b) a faulty Beckhoff Terminal.
  c) prioritization of  manpower (AE and VG) in other devices in the
tunnel.
  d)....the usual "sigmoidal" behavior of this kind of process.... ;)

3. In any case we aim to leave the system ready tomorrow so next week the
interlock code can be deployed safely.


Have a nice evening,

R.