Updated Tunnel component status list, posted by Thomas Tschentscher on 17 Mar 2017, 12:11
|
Updated list of tunnel high priority components after SASE1 Readiness mtg this morning. The list has also been sent for comments/clarifications to the involved
Groups/People. |
Loop status schedule for KW12, posted by Adriano Violante on 17 Mar 2017, 15:21
|
Dear all,
find here the foreseen loop status for KW12. The schedule could change. All changes will be notified by entries in the logbook.
|
Motion Loop, posted by NEREA JARDON on 22 Mar 2017, 15:05
|
FYI. The Motion loop is again up and running. |
Motion loop, posted by NEREA JARDON on 22 Mar 2017, 16:28
|
Dear all,
tomorrow morning at 10h am, we will need the Motion PLC for roughly half hour to do some tests. During this time the PLC will be stop.
|
Pop-In II-45 Karabo test, posted by Andreas Koch on 22 Mar 2017, 16:39
|
Trigger signal now available at imager. First Karabo tests of camera device with trigger successful. Detailed
tests continue. |
Motion up, posted by NEREA JARDON on 23 Mar 2017, 10:06
|
Dear all,
The Motion loop is up and running again.
Thank you! |
Schedule for PLC and Karabo Week 13, posted by Tobias Haas on 24 Mar 2017, 13:21
|
Day
Motion Loop
Vacuum |
Update of component priority list after weekly meeting, posted by Tobias Haas on 24 Mar 2017, 15:24
|
|
Web cameras in SASE1 tunnels, posted by Liubov Samoylova on 31 Mar 2017, 07:24
|
|
Update of component list after weekly meeting, posted by Tobias Haas on 31 Mar 2017, 15:00
|
|
Meeting Minutes 31 March 2017, posted by Frederike Wittmaack on 31 Mar 2017, 15:03
|
http://tinyurl.com/lttzrtm |
SASE1 EPS, posted by NEREA JARDON on 31 Mar 2017, 16:02
|
Dear all,
EPS loop is running with the latest hardware updates. Today, when I was trying to update the loop, I have found that someone has powered off the
EPS crate in XTD2 Rack 1.5. Please, if you have to do some work in any part of SASE 1, let us know about it. |
Schedule for PLC and Karabo 3 April after 09:30 Meeting, posted by Tobias Haas on 03 Apr 2017, 10:03
|
Tunnels closed today and tomorrow
- AE updates Vacuum and motion loop in the morning
- V. Bondar, J. Eidam and H. Sinn test vacuum in the afternoon (emphasis on understanding interlock conditions) |
Schedule after 09:30 Meeting, posted by Tobias Haas on 04 Apr 2017, 11:21
|
Tunnel closed today. Might re-open around 14:00
Note that that we re-convene briefly at 17:00 today in MCR (Mock-up Control Room)
Vacuum Loop: |
Temperatures from EPS loop, posted by Alessandro Silenzi on 04 Apr 2017, 12:28
|
This is the list of data coming directly from the PLC via its TCP client connected to the EPS PLC.
Format:
deviceName temperature status errorCode |
Temperatures from EPS loop, posted by Alessandro Silenzi on 04 Apr 2017, 12:43
|
Alessandro Silenzi wrote:
This is the |
Access to XTD2, posted by Tobias Haas on 04 Apr 2017, 15:11
|
MPS informed me that they hit some problems and that they still need 30 mins to 1 h until we can go to XTD. |
Access to XTD2 and XTD9 is now possible , posted by Tobias Haas on 04 Apr 2017, 16:29
|
Interlocks in the northern fan are broken! |
Meeting at 17:00 should take place at 17:45, posted by Tobias Haas on 04 Apr 2017, 16:31
|
since tunnel access is now possible |
Progress on Vacuum Loop, posted by Tobias Haas on 04 Apr 2017, 18:16
|
J. Eidam, V. Bondor, T. Freyermuth checked Ion pump controller settings in XTD2 and XTD9.
Many controllers were found to have incorrect settings. All pumps in XTD2 now respond and give pressure readings. There remains the problem that
the PLC is looking for the wrong channel in the case where 2 pumps are connected to one controller (Is 1 & 3 and PLC looks for 1 & 2). J. Eidam |