ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
|
245
|
18 May 2017, 11:57 |
Jan Grünert | General | Problem | Vacuum issue in XTD9 during cycling of PLC loop yesterday | During the usual recovery procedure after
the planned and announced cycling of the
SASE1 VAC loop yesterday, we observed a serious |
|
258
|
21 May 2017, 17:10 |
Dennis Goeries | XTD2 | Problem | SASE1 Imager FR | Dear all,
we are experiencing constantly crashes
with the photonic science camera in the SA1 |
|
276
|
03 Jun 2017, 22:39 |
Alessandro Silenzi | General | Problem | SOLVED BROKER Problem | A
pile up in the BrokerQueue was detected by |
|
286
|
09 Jun 2017, 21:40 |
Gabriele Giovanetti | XTD2 | Problem | Motor in error | Called at 21.18 for SASE1_XTD2_IMGSR/MOTOR/Y
being in error.
Solved by pressing 'Reset' button |
|
334
|
14 Jul 2017, 12:44 |
Martin Dommach | XTD9 | Problem | Fast Valves in XTD9 | Dear all,
the fast valves in XTD9 were causing
some trouble. From time to time they collect |
|
366
|
22 Aug 2017, 09:48 |
Hugo Silva Santos | General | Problem | Karabo down in tunnel | Dear All,
We have a issue on the control
servers and we are already working on it... |
|
367
|
22 Aug 2017, 10:24 |
Hugo Silva Santos | General | Problem | Karabo down in tunnel | Dear All,
We solved the incident and the
services are running normally. We are still |
|
440
|
09 Jan 2018, 10:32 |
Martin Dommach | General | Problem | Shutdown of compressed air distribution in XTDs today | Dear all,
we got the information from MKK,
that they have to fix a leak in the main |
|
492
|
25 Mar 2018, 10:57 |
Gerd Wellenreuther | XHEXP | Problem | FXE emergency power-off has been triggered | Dear all,
apparently the Emergency Power-Off
at FXE was triggered at around 10:00 - 10:30 |
|
1
|
26 Oct 2016, 13:55 |
Tobias Haas | General | Information | Start of Logbook | Dear Colleagues,
in the future we would like to use
this mechanism to record and exchange information |
|
2
|
26 Oct 2016, 14:26 |
Tobias Haas | General | Information | Minutes of last week's meeting | http://tinyurl.com/gvvv392 |
|
3
|
03 Nov 2016, 12:58 |
Alessandro Silenzi | XTD2 | Information | Current PLC-Karabo Conflict | Tobias
Freyermuth and me |
|
4
|
03 Nov 2016, 17:00 |
Sabine Cunis | XTD2 | Information | overview of required racks | just for reference ... here are pictures
and schematics of the racks which are involved
in the current commissioning. |
|
5
|
04 Nov 2016, 08:03 |
Frederike Wittmaack | General | Information | Minutes of last weeks meeting (Oct 28, 2016) | http://tinyurl.com/jy5rsbx |
|
6
|
04 Nov 2016, 14:22 |
Frederike Wittmaack | General | Information | Minutes - Meeting November 4, 2016 | http://tinyurl.com/jbog6tz |
|
7
|
04 Nov 2016, 18:08 |
Alessandro Silenzi | General | Information | BeckhoffDevices back to responsive | I reproduced the behaviour of the
PLC on beckhoffSim. This reproduces the same
behaviour seen in the tunnel devices (devices |
|
8
|
07 Nov 2016, 19:15 |
Alessandro Silenzi | XTD2 | Information | Karabo Installation back to normal | Karabo to PLC communication has been
tested successfully in the SA1 Vacuum installation.
in attachment: |
|
9
|
09 Nov 2016, 15:36 |
Tobias Haas | General | Information | Update of Component list | I have included the status columns provided
by Alessandro and Sandor in the component
list. Please find it in the usual location |
|
10
|
11 Nov 2016, 15:43 |
Tobias Haas | General | Information | Mandate for the Extension of the Vacuum Controls Commissioning Task Force | The Vacuum Controls Commissioning Task
Force initially helped to get the vacuum
components extending from the gate valve |
|
11
|
14 Nov 2016, 14:10 |
Frederike Wittmaack | General | Information | Meeting Minutes 11 Nov 2016 | http://tinyurl.com/juhjcbf |
|