Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 28 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Location Severity Subject
  57   02 Mar 2017, 11:55 NEREA JARDONGeneralInformationVacuum PLC

Dear all,

The Vacuum PLC is up and running and Karaboo guys have already started to work with it.

Thank you and regards

  56   02 Mar 2017, 09:52 NEREA JARDONGeneralInformationPLC work

Dear all,

Right now the Motion PLC is up and running. We are still working in the Vacuum one, today by midday should be also working.

  55   28 Feb 2017, 11:38 Tobias HaasGeneralInformationReminder: Stable operation and development periods

One word of clarification:

The discussion last Friday left some people uncertain over how to define stable operation and development periods. Hence I had a discussion with Nerea and Alessandro and agreed on the following:

PLC development: Tuesday - Thursday

Stable operation with Karabo: Friday - Monday

Handover period is Thursday afternoon between AE and CAS 

 

  54   24 Feb 2017, 16:33 Tobias HaasGeneralInformationUpdate of component list after weekly meeting
  53   24 Feb 2017, 15:22 Frederike WittmaackGeneralInformationMeeting Minutes 24 Feb 2017
http://tinyurl.com/hhu998t
  52   24 Feb 2017, 15:15 Martin DommachXTD9Informationwork on FXE distribution mirror chamber

Dear all,

on Monday, 27th in the morning we will start with preparation work for the mirror installation in XTD9.

The mirror chamber (VS10130) will be vented and opened. This will affect:

V10270G and V10280G: they will be closed and disconnected

P10410I and P10420I: C10902I will be switched to "local" mode and the HV of the pumps will be switched off.

The work will take at least until Friday, March 3rd.

 

  51   24 Feb 2017, 15:14 Martin DommachXTD9Informationwork on FXE distribution mirror chamber

Dear all,

on Monday, 27th in the morning we will start with preparation work for the mirror installation in XTD9.

The mirror chamber (VS10130) will be vented and opened. This will affect:

V10270G and V10280G: they will be closed and disconnected

P10410I and P10420I: C10902I will be switched to "local" mode and the HV of the pumps will be switched off.

The work will take at least until Friday, March 3rd.

 

  50   17 Feb 2017, 12:40 Thomas TschentscherGeneralInformationUpdated Component status list
See the updated component status list for XTD2 and XTD9 tunnels. As discussed at the SASE1 readiness mtg this morning. Yellow fields indicate new/changed entries. Please let me/THaas know if there are errors or further changes to be reported. I also entered the SASE1 instruments now a 'High Priority' items. However, we may need to adapt the table for These entries as the work flow seems different.
  49   17 Feb 2017, 09:56 Alessandro SilenziGeneralFeedbackMotion loop feedback

Quick feedback during the meeting:

- 63 Devices

- 29 Motors

Errors only in 

- SPB_XTD9_IMGPI

- FXE_XTD9_IMGPI

  48   15 Feb 2017, 20:20 Alessandro SilenziGeneralFeedbackMotion loop status

The motion loop is as of 18:40 online.

the current status of the devices as seen by the Karabo is shown in the attachment:

In summary 63 devices (29 Motors):

18 in error

- 14 in error 0x8004 (Terminal unavailable)

- 4 in error 0x8003 (Terminal unavailable)

This is the list of motor that are behaving according to karabo

SA1_XTD2_MIRR-2/MOTOR/HMRZ Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_RIGHT Success State.OFF
SA1_XTD2_IMGFEL/MOTOR/SCREEN Success State.OFF
SA1_XTD2_FLT/MOTOR/TARGET Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMRZ Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_LEFT Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMTX Success State.OFF
SA1_XTD2_IMGSR/MOTOR/TARGET_X Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMRX Success State.OFF
SA1_XTD2_IMGSR/MOTOR/IRIS Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMRY Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_BOTTOM Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMRY Success State.OFF
SA1_XTD2_IMGSR/MOTOR/FOCUS Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMTX Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMTY Success State.OFF
SA1_XTD9_IMGPII45/MOTOR/SCREEN Success State.OFF
SA1_XTD2_MIRR-1/MOTOR/HMRX Success State.OFF
SA1_XTD2_PSLIT/MOTOR/BLADE_TOP Success State.OFF
SA1_XTD2_IMGPII45/MOTOR/SCREEN Success State.OFF
SA1_XTD2_IMGFEL/MOTOR/FILTER Success State.OFF
SA1_XTD2_MIRR-2/MOTOR/HMTY Success State.OFF
 

  47   15 Feb 2017, 20:10 Alessandro SilenziGeneralFeedbackCurrent Vacuum Status

The PLC is still not completely error free.

It is considerably better performing than the last days:

the current average pressure as measured by the Ion Pumps is 4.21e-09 mBar

there are Currently 96 ion pumps in the Tunnels as seen by the PLC:

3 cannot properly communicate with the PLC

SA1_XTD9_VAC/IPUMP/P10510I

SA1_XTD9_VAC/IPUMP/P11130I

SA1_XTD9_VAC/IPUMP/P12120I

3 have an ambiguous control name:

SA1_XTD2_VAC
SA1_XTD9_VAC2
SA1_XTD9_VAC0
 

And 4 have no channel assigned in the Karabo inteface (CAS to solve this)

SA1_XTD2_VAC/IPUMP/P10340I
SA1_XTD2_VAC/IPUMP/P10350I
SA1_XTD9_VAC/IPUMP/P10370I
SA1_XTD2_VAC/IPUMP/P10360I

The remaining 86 replied and:

Average pressure is  4.210e-09 mBar

Maximum pressure is  2.60-08 mBar

Minimum pressure is  8.90e-10 mBar

  46   14 Feb 2017, 09:59 Alessandro SilenziGeneralProblemBeckhoff loop status

2017.02.13 19:30 Status:

- Self-Description back in shape.

- Bad SelfDescription reproduced in BeckhoffSim (Karabo implemented PLC communication) and solved in BeckhoffCom (Karabo "PLC Client").

- The build status of the Firmware is not ok. roughly 90% of the PLC soft devices are in error. It is a fault in the automatic Firmware build procedure.

Nerea and Jan will work on this until it is fixed.

 

  45   12 Feb 2017, 14:02 Alessandro SilenziGeneralProblemCurrent Status

 Vacuum loop:

- Interface between PLC and Karabo is not functioning.

The fault currently resides in the PLC behaviour, the self-description sent out is badly formatted (due to a buffer overrun)

The misbehaviour is confirmed, the PLC TCP Client from AE is also ailed by the same problem.

Motion Loop:

- As of Friday, the motor parameters were not completely sent to AE. In attachment the data collected by N. Jardon (AE). Input needed for PSLIT motors.

 

 

 

  44   10 Feb 2017, 16:34 Tobias HaasGeneralInformationUpdated Components List
  43   10 Feb 2017, 15:15 Frederike WittmaackGeneralInformationMeeting Minutes 10 Feb 2017
Follow the link below to view the minutes and relating material on Alfresco. http://tinyurl.com/zc3nvn9
  42   10 Feb 2017, 15:07 Tobias HaasGeneralInformationUpdated Components List

 Added Diagnostic Screen for SPB and changed PRIO for DPS - XGM - DPS in XTD9 to high as discussed during the S1R meeting

  41   10 Feb 2017, 08:31 Tobias HaasGeneralInformationProgress Beam Transport

Post on behalf of Harald Sinn

Fortschritte, die ich letzte Woche beobachten konnte, sind: 

1.) Die Spiegelkammern wurden weiter lokal getestet. Benoit hat gestern abend den 
letzten Encoder am XTD9 vercrimmt. Wahrscheinlich muss der dann noch mal getestet werden, 
aber dann sollte das abgeschlossen sein. 
2.) Gestern haben wir zusammen mit Jan Tolkiehn den SRA und Filterkammer getetstet. 
SRA ist OK (incl. der Encoder), die Filterkammer auch, aber Wolfgang meinte, er müsste die 
LImit.switches noch mal etwas nachstellen (dafür sollte dann aber Karabo funktionieren, s.u.)
3.) Die PBLMs in XTD2 und die letzten beiden in XTD9 sich verkabelt und könnten von uns aus lokal 
getestet werden. Jan meinte allerdings, dass an den Elmo/technosoft (PBLM hat Elmo) Treibern noch etwas Arbeit
nötig ist, um zuverlässig Tests zu machen (MCI Library)
4.) Andreas Block hat mit Maik Neumann ausgemacht, dass sie sich Montag treffen und alle fehlenden Wasserverbindungen in 
SASE1 durchgehen und am besten sofort machen,. 
5.) Makus Schlösser hat bestätigt, dass nächste Woche (wohl leider nur) ein Team für uns arbeiten kann. 
Das wird zunächst aber in SASE3 hinten anfangen, weil wir da schnon einen Arbeitsstau in der Vakuumgruppe 
aufgebaut haben. Die relativ wenigen Komponenten in SASE1 werden natürlich auch fertig, aber Markus meinte, er würde vorhar 
lieber noch einige Daten konsolidieren. 
 
Zum lokalen testen: Das ist schon sehr wichtig, allerdings sollte es noch nicht mit dem technical commissioing 
verwechselt werden. Beim lokalen Testen wird nur festgestellt, ob sich der Motor in die richtige Richtung dreht 
und ob am Terminal die richtige LED leuchtet, wenn man den entsprechenden Endschalter drückt 
(Jan weiss dann, welche LED leuchten muss). Man sollte aber z.B. nicht auf den Endschalter fahren, weil in diesem 
Modus kein automatischer Stopp stattfindet, sondern man muss manuell eine Stopp Taste drücken. 
Auch werden nicht Motorgeschwindigkeit etc. optimiert oder gespeichert. 
Deswegen ist es wichtig, dass wir möglichst schnell Beckhoff+Karabo zum Laufen bringen, weil diese Tests 
essentiell sind und von den Komponentenverantwortlichen gemacht werden müssen. 
Falls die MCI Library tatsächlich ein Problem darstellt, was etwas dauert, würde ich vorschagen, die 
Beckhoff Motion Loop jetzt schon in Betrieb zu nehmen, mit den Motoren, die wir getestet haben. 
 
Grüße 
 
Harald 
 
 
  40   09 Feb 2017, 17:16 Tobias HaasGeneralInformationStatus of Differential Pumping

Post on behalf of R. Villanueva

please find attached the updated status of the Differential Pumping
Modules in SASE 1. Just a few comments.

1. As you can imagine, no progress after KW4 in XTD2: system is ready to
deploy Karabo.
2. In XTD9, we have been pushing forward to finish the local test with AE.
Right now, everything has passed the local test except 3 vacuum gauges
that will be rechecked after the meeting. The main reasons for the little
progress (84%----->87%) are:

  a) more problems than expected with the cabling.
  b) a faulty Beckhoff Terminal.
  c) prioritization of  manpower (AE and VG) in other devices in the
tunnel.
  d)....the usual "sigmoidal" behavior of this kind of process.... ;)

3. In any case we aim to leave the system ready tomorrow so next week the
interlock code can be deployed safely.


Have a nice evening,

R.

  39   09 Feb 2017, 13:57 Tobias HaasGeneralInformationUpdate of installation list for tomorrow's S1R Meeting

 Please check if correct. I mark all newly done things in yellow!

  38   03 Feb 2017, 14:22 Frederike WittmaackGeneralInformationMeeting Minutes 03 Feb 2017
http://tinyurl.com/hwu4esq