ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
|
399
|
06 Oct 2017, 14:42 |
Janusz Szuba | General | Information | Online storage update on Monday 9th Oct | After today's discussion with WP75
group, we decided to postpone the update
of the online storage to the next Monday |
|
362
|
17 Aug 2017, 07:59 |
Krzysztof Wrona | XTD10 | Information | Office network in XTD10 | Dear All,
In XTD10 there are now office network
ports available in each rack. These can be |
|
235
|
15 May 2017, 22:17 |
Thomas Michelat | General | Information | OCD CAS | Dear all,
The OCD number for tonight (15/05)
for the CAS group is 98053. |
|
231
|
12 May 2017, 15:37 |
NEREA JARDON | General | Information | OCD AE Group | Dear all,
The OCD numbers for this weekend
and today will be: |
|
234
|
15 May 2017, 11:32 |
NEREA JARDON | General | Information | OCD AE Group | Dear all,
The OCD AE numbers for the following |
|
248
|
18 May 2017, 15:30 |
NEREA JARDON | General | Information | OCD AE Group | Dear all,
The OCD AE numbers for the following |
|
161
|
21 Apr 2017, 15:22 |
NEREA JARDON | General | Information | OCD | Dear all,
The service of On-call Duty will
be available from AE group during weekend |
|
348
|
28 Jul 2017, 11:10 |
Eric Boyd | XHEXP | Information | No Restricted Areas for Radiation Commissioning | Desired parameters where reached for radiation
measurments of the SPB OPT and SPB EXP hutches.
Radiaiton could not be detected inside the |
|
353
|
03 Aug 2017, 10:52 |
Eric Boyd | XHEXP | Information | No Radiation Measurements in SASE 1 This week | Do to repairs that need to be made with
the cold compressor. We will be unable to
perform Radiation Hutch Commissioning for |
|
220
|
11 May 2017, 12:43 |
Alessandro Silenzi | General | Information | New Deployment of Karabo for the SASE1 control machines. | I will ramp down the system and bring it
back up during the lunch break after installing
the |
|
221
|
11 May 2017, 15:08 |
Alessandro Silenzi | General | Information | New Deployment of Karabo for the SASE1 control machines. |
|
|
228
|
12 May 2017, 13:19 |
Alessandro Silenzi | General | Information | New Deployment of Karabo for the SASE1 control machines. |
|
|
305
|
03 Jul 2017, 10:13 |
Krzysztof Wrona | XTD2 | Information | Network upgrade /information and problem | The upgrade of the switches is finished
to the extend that it allows Advanced Electronic
group to work on KMono (Nerea is informed) |
|
304
|
30 Jun 2017, 15:33 |
Janusz Szuba | General | Information | Network and servers maintenance | As discussed offline with NOC, Monday schedule
was already fixed and not movable to Tuesday.
Therefore, the network maintenance will take |
|
286
|
09 Jun 2017, 21:40 |
Gabriele Giovanetti | XTD2 | Problem | Motor in error | Called at 21.18 for SASE1_XTD2_IMGSR/MOTOR/Y
being in error.
Solved by pressing 'Reset' button |
|
86
|
23 Mar 2017, 10:06 |
NEREA JARDON | General | Information | Motion up | Dear all,
The Motion loop is up and running
again. |
|
277
|
06 Jun 2017, 13:46 |
NEREA JARDON | General | Information | Motion loop update | Dear all,
We will start with the Motion loop
update. Will take us a little bit, around |
|
278
|
06 Jun 2017, 17:39 |
NEREA JARDON | General | Information | Motion loop update | Dear all,
The Motion loop is running again.
We have included today the Mc2motor devices |
|
280
|
07 Jun 2017, 12:00 |
NEREA JARDON | General | Information | Motion loop update | Dear all,
Due to some hardware changes needed
in Motion loop, we will last a little bit |
|
281
|
07 Jun 2017, 14:19 |
NEREA JARDON | General | Information | Motion loop update | Dear all,
Motion loop is up and running again,
now with all the PBLMs configured. |
|