206
|
04 May 2017, 12:14 |
Sandor Brockhauser | General | Information | CAS support during the afternoon: 9-6776 |
Dear All,
During the afternoon CAS has a group activity. Any support can be requested via my phone number: 9-6776.
See you,
Sandor |
207
|
04 May 2017, 19:40 |
Jan Grünert | General | Problem | Slow loading in karabo GUI |
The current slow response times in the karabo GUI are the following (some measured times for reference):
- opening a project from the project manager : 45sec (just loading, not yet touching any device or scene)
- opening a scene and receiving the status for all devices e.g. XGM@XTD2 : between 90 and 120 sec
- beyond that, it's never clear if the displayed gauge values are true/actual and must be separately read.
- reading explicitly a gauge value (with command READ in configurator) gives currently an updated value after about 10 sec (should be almost immediate when requested)
-----> working with this (getting actual work done) is practically almost impossible
- this is using the "new" gui server "sa1-br-sys-con-gui2"
- this is after 19h30 (shouldn't less traffic help the performance ?)
|
208
|
05 May 2017, 09:44 |
Tobias Freyermuth | General | Information | VAC loop up and running again |
The vacuum loop is up and running again, with the version 1.11.4.
Denis Finze will connect the shutter signals of the XS3 shutter to the vacuum loop in rack 1.7.
|
209
|
05 May 2017, 14:35 |
Nicola Coppola | General | Information | AE OCD Mai 5 -- Mai 8 |
AE on call service:
Contact person:
Nicola Coppola
Phone:
9 - 5627
|
210
|
06 May 2017, 14:50 |
Jan Grünert | General | Information | WP74 OCD contacts for this weekend |
WP74 OCD for the weekend 6.5.-7.5.2017:
Saturday: Jan, jan.gruenert@xfel.eu, 9-5777
Sunday: Theo, theophilos.maltezopoulos@xfel.eu, 9-6792
|
211
|
08 May 2017, 15:18 |
Adriano Violante | General | Information | Status after the 9.30 Meeting |
Vacuum (M. Dommach):
- Systematic tests of ion pumps in XTD9 almost finished - ongoing
- Interface with MPS has to be tested
- Problem with the fast valve in XTD2 and 9 - it is possible to close it remotely but not possible to open it again. Checking of the cabling is ongoing by Vacuum group
- After restart of the vacuum loop many pumps in XTD 9 and 2 show an unknown error and some of them are not readble - CAS working on that.
PLC (P. Gessler, T. Freyermuth):
- Implementation of shutters in Karabo ongoing -XS3 shutter in the VAC loop now. XTD9 to do.
Karabo (A. Silenzi):
- GUI stability improved with a temporary solution. This should be enough to guarantee the proper functioning of images acquisition.
- Update of devices list ongoing
- Library for motors (base device), elmo and technosoft, being worked out.
Plans for today:
- XGM work on gas injection
- Bring back Karabo and clear XGM error codes
- Perform systematic test of DPS in XTD9
Other topics:
- No 09:30 meeting tomorrow - next meeting will be on Wednesday
|
212
|
09 May 2017, 16:43 |
NEREA JARDON | General | Information | EPS loop |
Dear all,
I will make an update on the EPS loop, it will take only a moment.
Thank you |
213
|
09 May 2017, 17:04 |
NEREA JARDON | General | Information | EPS loop |
EPS loop in SASE1 is running again |
214
|
10 May 2017, 10:59 |
NEREA JARDON | General | Information | Vacuum loop |
Dear all,
The update of the Vacuum loop will take place in the next few minutes, later on, you would have access again to it.
Thank you. |
215
|
10 May 2017, 11:06 |
NEREA JARDON | General | Information | Vacuum Loop |
Sorry for disturbing you, but I will have to wait till WP74 group finish a training in order to be able to put the XGM up again . |
216
|
10 May 2017, 12:34 |
NEREA JARDON | General | Information | Vacuum Loop |
Vacuum is up and running again.
Thank you |
219
|
10 May 2017, 18:52 |
Gero Flucke | General | Information | CAS OCD |
CAS on call service for the night:
Gero Flucke: 9-8053
|
220
|
11 May 2017, 12:43 |
Alessandro Silenzi | General | Information | New Deployment of Karabo for the SASE1 control machines. |
I will ramp down the system and bring it back up during the lunch break after installing the
tag 2.1.10.
To install a new version of Karabo use the script attached on your terminal
move your the karabo directory to a backup or remove it.
to backup:
$ mv ~/karabo ~/karabo.bkp
to remove:
$ rm -fr ~/karabo
then execute:
$ bash PATHTO/download.sh |
Attachment 1: download.sh
|
#!/bin/bash
if [ -z ${outfilename} ]
then
outfilename=.karabo.sh
fi
echo $outfilename
git clone https://xfel.redmine:K9Sss5CmWtQ_nbx3gyt2@git.xfel.eu/gitlab/Karabo/commissioning-guidelines .temp-commissioning --depth=1
cp -f .temp-commissioning/project_generation/install.sh .install.sh
rm -fr .temp-commissioning
. .install.sh
rm ${outfilename}
rm .install.sh
|
221
|
11 May 2017, 15:08 |
Alessandro Silenzi | General | Information | New Deployment of Karabo for the SASE1 control machines. |
Alessandro Silenzi wrote: |
I will ramp down the system and bring it back up during the lunch break after installing the
tag 2.1.10.
To install a new version of Karabo use the script attached on your terminal
move your the karabo directory to a backup or remove it.
to backup:
$ mv ~/karabo ~/karabo.bkp
to remove:
$ rm -fr ~/karabo
then execute:
$ bash PATHTO/download.sh
|
The system is up.
The users using virtual machines will encounter problems installing karabo 2.1.10 in the way that was described.
Further instructions will come later in the day |
222
|
11 May 2017, 16:41 |
NEREA JARDON | General | Information | Motion loop |
Dear all,
I will update the Motion loop to include the mc2 motors, it will be running again in few minutes.
Thank you! |
224
|
11 May 2017, 19:12 |
Jan Grünert | General | Information | WP74 OCD contacts |
Plan of WP74 OCD contacts for May.
Assignments are subject to change.
Initially availability is 10h-18h on the given days.
This might be adapted as well for later weeks. |
Attachment 1: WP74-OCD-5-2017.xlsx
|
225
|
12 May 2017, 08:21 |
Harald Sinn | General | Information | Restart vacuum loop now |
We are in the BRK and corrected the vacuum interlock condition.
We will restart the SA1 vacuum loop in a few minutes
|
227
|
12 May 2017, 12:26 |
Monica Aresté | General | Information | Update of Instrument component priority list |
Find attached the Instrument Component priority list discussed this morning.
Regards,
Monica |
Attachment 1: 170512_Instrument_Components-Priority-list.xlsx
|
228
|
12 May 2017, 13:19 |
Alessandro Silenzi | General | Information | New Deployment of Karabo for the SASE1 control machines. |
Alessandro Silenzi wrote: |
Alessandro Silenzi wrote: |
I will ramp down the system and bring it back up during the lunch break after installing the
tag 2.1.10.
To install a new version of Karabo use the script attached on your terminal
move your the karabo directory to a backup or remove it.
to backup:
$ mv ~/karabo ~/karabo.bkp
to remove:
$ rm -fr ~/karabo
then execute:
$ bash PATHTO/download.sh
|
The system is up.
The users using virtual machines will encounter problems installing karabo 2.1.10 in the way that was described.
Further instructions will come later in the day
|
for Users with a VM:
- use the download script
- Remove the karabo directory:
$ rm -fr ~/karabo
- then execute:
$ bash PATHTO/download.sh
Sorry for the delayed instructions
|
229
|
12 May 2017, 13:33 |
Tobias Haas | General | Information | Status and plans after SASE1 Readiness Meeting |
Focus of meeting is on SASE1 Instruments, Laser and Detectors
SPB (B. Weinhausen)
- All motors in the SPB tunnel loop have been commissioned except for one TECHNOSOFT motor where the updated driver was not yet available
- Comment by P. Gessler:
- The updated MC2 lib was deployed yesterday evening. Testing should be possible now
- The second camera of the screen broke. Concern exists over possible overvoltage in the power that comes directly from the PLC
- All encoders are working
- The vacuum in the Optics hutch is closed
- Info by A. Violante:
- All cabling in D02/D03 is done
- There are a few damaged connectors that prevent pushing in the modules. This should be fixed on Monday
- Pins are swapped in one connector. Will be fixed locally
- Comment by P. Gessler:
- This week AE was busy with AGIPD and tunnels
- Next week resources should be available to support start of commissioning loop 1
FXE (A. Galler)
- E2E tests are progressing
- A recent update of the Beckhoff firmware generated new problems with encoders
- Info from T. Korsch:
- The vacuum in the hutch is closed and has reached 5e-7 mb
- There is a minor leak in one of the bellows
- Compressed air is working to operate the gate valves
- Vacuum gauges can be read out remotely
- Attention should be paid to being able to read out detectors, e. g. diodes
Laser (D. Kane/M. Lederer)
- Slides were provided in INDICO with a detailed account of the status. Only Key points are summarised here:
- Hutch infrastructure is working in general and temperature stability is ok but laser group is lacking access to controlling the parameters, humidity is oscillating and smoke detectors are not connected
- Pre-assembly of PP laser is 75% done
- Beam delivery to instruments is on the list now
- Synchronisation with optical system might not be available before October
- Control are generally working and software has improved a lot but some stages cannot be controlled and Karabo appears still to have some resource leaks
Detectors (M. Kuster)
- LPD is in E2E tests and AGIPD is still being integrated into the XFEL environment
- This week it was possible to run the DAQ chain on LPD for the first time
- All tests on LPD including data taking in the X-Ray chamber in HERA-S should be done by end June
- Situation with AGIPD is more difficult as basic integration is still not complete
Discussion
- Follow up on progress with instruments, laser and detectors will continue in S1R meeting from now on
- The S1R dispatch meeting takes place on Mondays 09:00 in BKR and on Wednesday 09:30 in XHQ
- Groups that require help from AE and CAS and that need to coordinate with other activities should attend
|
Attachment 1: AttendanceS1R120517.pdf
|
|