119
|
07 Apr 2017, 17:54 |
Tobias Freyermuth | General | Feedback | Hotfix for all loops (VAC, MOV, EPS) deployed |
|
|
121
|
10 Apr 2017, 09:36 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
I will update the Vacuum loop in
order to add the XGM XTD9 into it. It will |
|
122
|
10 Apr 2017, 10:09 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
The Vacuum loop is running again,
now with XGM XTD9 included. We will be testing |
|
123
|
10 Apr 2017, 10:47 |
Tobias Haas | General | Information | Schedule after 09:30 Meeting | Tunnel
Open. |
|
124
|
10 Apr 2017, 12:31 |
Alessandro Silenzi | General | Information | KARABO Update maintainance | The karabo services will be down for an
upgrade for an hour.
The access will resume at 13:30. |
|
125
|
10 Apr 2017, 18:13 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
Right now both XGMs are into the
loop and would be running. The loop must |
|
126
|
10 Apr 2017, 19:19 |
Tobias Freyermuth | General | Information | update of the EPS loop | Dear cllougues,
|
|
127
|
10 Apr 2017, 20:05 |
NEREA JARDON | General | Information | EPS & Motion | Dear all,
EPS and Motion loop have been updated
to the last framework version with the last |
|
128
|
11 Apr 2017, 11:48 |
NEREA JARDON | General | Information | Vacuum Loop | Dear all,
Vacuum loop is up and running, we
would wait till Raul check the interlock |
|
129
|
11 Apr 2017, 12:51 |
Tobias Haas | General | Information | Status after 0930 meeting | Tunnel |
|
130
|
11 Apr 2017, 13:24 |
NEREA JARDON | General | Information | Motion Loop | Dear all,
Motion loop is running again with
the last update (names for PSLIT and LVDT |
|
131
|
11 Apr 2017, 13:32 |
NEREA JARDON | General | Information | Motion loop | Dear all,
Sorry for disturbing again, I will
do a small update to put one missing coupler |
|
132
|
11 Apr 2017, 13:48 |
Alessandro Silenzi | General | Information | Script to install the latest karabo | Please find in attachment the dowload bash
script for the latest Karabo.
if your system has a "karabo" |
|
134
|
11 Apr 2017, 15:38 |
NEREA JARDON | General | Information | EPS loop | Dear all,
The EPS loop would be stopped, in
order to correct some issues with the hardware |
|
139
|
12 Apr 2017, 09:16 |
Andreas Koch | General | Information | Imager status |
Normal
0
|
|
140
|
12 Apr 2017, 12:52 |
Tobias Haas | General | Information | Status and plans after 09:30 meeting | Tunnel
Closed. |
|
141
|
13 Apr 2017, 10:15 |
Alessandro Silenzi | General | Problem | EtherCAT loop broken for Vacuum loop | The EtherCAT loop for the vacuum PLC is
interrupted at crate 1.6 (XTD2).
This triggered all Beckhoff Terminals |
|
142
|
13 Apr 2017, 12:07 |
Tobias Haas | General | Information | Status and Plans after 09:30 meeting | Tunnel
Closed until approx 1300, Open over the Easter |
|
143
|
13 Apr 2017, 13:19 |
Tobias Haas | General | Information | Status Interlock Tests Today | Radiation Interlock Tests are finished.
Tunnels XTD9 and XTD10 up to the fence at
the dump can be accessed right now. Magnet |
|
144
|
13 Apr 2017, 14:09 |
Tobias Haas | General | Information | Interlock tests are finished in Northern Fan | All northern tunnels XTD2/4/9/10 are fully
accessible again! |
|
|