*IMPORTANT* Change of plans re Access tomorrow, posted by Tobias Haas on 03 May 2017, 13:29
|
Due the recent results from XFEL, the urgent maintenance is shiftet from Thursday 4th to Friday 5th. On Thursday,
there will be operation till 14:00, after 14:00 the machine will be switched to standby. All the work planned will
shift accordingly by one day. No ZZ before Thursday 14:00. |
Accelerator Schedule for the next days, posted by Tobias Haas on 03 May 2017, 13:38
|
Author: Decking
|
Info from H. Sinn, posted by Tobias Haas on 04 May 2017, 11:36
|
Hallo allerseits
|
CAS support during the afternoon: 9-6776, posted by Sandor Brockhauser on 04 May 2017, 12:14
|
Dear All,
During the afternoon CAS has a group activity. Any support can be requested via my phone number: 9-6776. |
VAC loop up and running again, posted by Tobias Freyermuth on 05 May 2017, 09:44
|
The vacuum loop is up and running again, with the version 1.11.4.
Denis Finze will connect the shutter signals of the XS3 shutter to the vacuum loop in rack 1.7.
|
AE OCD Mai 5 -- Mai 8, posted by Nicola Coppola on 05 May 2017, 14:35
|
AE on call service:
Contact person:
Nicola Coppola |
WP74 OCD contacts for this weekend, posted by Jan Grünert on 06 May 2017, 14:50
|
WP74 OCD for the weekend 6.5.-7.5.2017:
Saturday: Jan, jan.gruenert@xfel.eu, 9-5777
Sunday: Theo, theophilos.maltezopoulos@xfel.eu, 9-6792 |
Status after the 9.30 Meeting, posted by Adriano Violante on 08 May 2017, 15:18
|
Vacuum (M. Dommach):
Systematic tests of ion pumps in XTD9 almost
finished - ongoing
Interface with MPS has to be tested
Problem with the fast valve in XTD2 and 9 - it is possible to close |
EPS loop, posted by NEREA JARDON on 09 May 2017, 16:43
|
Dear all,
I will make an update on the EPS loop, it will take only a moment.
Thank you |
EPS loop, posted by NEREA JARDON on 09 May 2017, 17:04
|
EPS loop in SASE1 is running again |
Vacuum loop, posted by NEREA JARDON on 10 May 2017, 10:59
|
Dear all,
The update of the Vacuum loop will take place in the next few minutes, later on, you would have access again to it.
Thank you. |
Vacuum Loop, posted by NEREA JARDON on 10 May 2017, 11:06
|
Sorry for disturbing you, but I will have to wait till WP74 group finish a training in order to be able to put the XGM up again . |
Vacuum Loop, posted by NEREA JARDON on 10 May 2017, 12:34
|
Vacuum is up and running again.
Thank you |
CAS OCD, posted by Gero Flucke on 10 May 2017, 18:52
|
CAS on call service for the night:
Gero Flucke: 9-8053
|
New Deployment of Karabo for the SASE1 control machines., posted by Alessandro Silenzi on 11 May 2017, 12:43
|
I will ramp down the system and bring it back up during the lunch break after installing the
tag 2.1.10.
To install a new version of Karabo use the script attached on your terminal |
New Deployment of Karabo for the SASE1 control machines., posted by Alessandro Silenzi on 11 May 2017, 15:08
|
Alessandro Silenzi wrote:
I will ramp down the system and bring it back up during the lunch break after installing the |
Motion loop, posted by NEREA JARDON on 11 May 2017, 16:41
|
Dear all,
I will update the Motion loop to include the mc2 motors, it will be running again in few minutes.
Thank you! |
XTD10 not open on Monday, posted by Harald Sinn on 11 May 2017, 18:26
|
Dear all,
contrary to the rumor that I spread last Tuesday in the PBS meeting, the magnet tests in XTD2/4 will be NOT done coming Monday and therefore the
XTD10 will be be NOT open. It is still the plan to have one access day in XTD10 per week in the future (Monday or Wednesday to be clarified with the magnet |
WP74 OCD contacts, posted by Jan Grünert on 11 May 2017, 19:12
|
Plan of WP74 OCD contacts for May.
Assignments are subject to change.
Initially availability is 10h-18h on the given days. |
Restart vacuum loop now, posted by Harald Sinn on 12 May 2017, 08:21
|
We are in the BRK and corrected the vacuum interlock condition.
We will restart the SA1 vacuum loop in a few minutes
|