Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
OPERATION-2024 OPERATION-2023 OPERATION-2022 OPERATION-2021 OPERATION-2020 OPERATION-2019 SASE1-2018 SASE1-2017 Experiment data
  OPERATION-2024 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn, Page 4 of 10  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Datedown Author Group Subject Text Attachments
  140   09 Aug 2024, 01:59 Jörg HallmannMIDShift summaryoptimized the SDL alignment

found timing of the upper (-520
ps) and lower branch (-514.5 ps) of the SDL
  
  139   08 Aug 2024, 00:18 Jörg HallmannMIDShift summaryoptimization of seeding (still not as good
as needed)

set position for the two color
  
  138   29 Jul 2024, 23:22 Romain LetrunSPBShift summaryX-ray
delivery


11.0 keV, 1-351 pulses
  
  137   29 Jul 2024, 06:45 Giuseppe MercurioSCSShift summary## Shift summary night July 28th-29th

Achievements:
- we saw signal on both MCPs (with
  
  136   28 Jul 2024, 23:34 Romain LetrunSPBShift summaryX-ray
delivery


11.0 keV, 1-352 pulses
  
  135   27 Jul 2024, 23:42 Romain LetrunSPBShift summaryX-ray delivery
- 9.22 and 11.0 keV, 1-352 pulses
@ 1.1 MHz, 600-1400 uJ.
  
  134   27 Jul 2024, 09:10 Harald SinnPRCIssueSASE1: Solid attenuator att5 is in error.
When it is tried to move it out, the arm
lifts, but does not reach the final position
  
  133   24 Jul 2024, 15:22 Giuseppe MercurioSCSShift summary
Shift
summary (Natalia, Giuseppe)

Achievements:


M1, M2 pitches adjusted
Grating
  
  132   24 Jul 2024, 11:35 Harald SinnPRCIssueThe control rack of the soft mono at SASE3
has some failure. Leandro from EEE will enter
the XTD10 at 12:00. 
  
  131   24 Jul 2024, 10:26 Harald SinnPRCIssueIn SASE2 undualtor cell 10 has issues.
Suren K. will do a ZZ at 11:30 to fix it
(if possible). Estimated duration: 1-3 hours. 
  
  130   23 Jul 2024, 17:17 IdoiaXROShift summary

ZZ
access at XTD10


The
LE PM X and HE PM X motors were checked and
  
  128   22 Jul 2024, 15:27 Antje TrappXROSASE3 end of shift summarythis morning, ZZ was done together with
Sylvia Huynh (EEE) to solve softmono pre-mirror
motor issue https://redmine.xfel.eu/issues/177392
  
  129   22 Jul 2024, 15:20 Antje TrappXROSASE2 end of shift summaryBeam is now aligned back to HED for hand-over
to Naresh (see picture)

points achieved:
 HED_beam__2024-07-22_15-19-15.png 
  127   18 Jun 2024, 13:03 Kelin TascaXROCompensation of M2 RY motor for the case of Piezo offWe plan to put the piezos of M2 off, in
the (unprobable) case that this is the reason
of the "jumps" in SASE3 trajectory.
 Screenshot_from_2024-06-18_13-16-14.pngScreenshot_from_2024-06-18_13-18-15.pngScreenshot_from_2024-06-18_13-20-06.png 
  126   14 Jun 2024, 01:53 Jörg HallmannMIDShift summarycontinue with Tempus tests
continue with PAM commissioning (first
results of the working device at MID)
  
  125   13 Jun 2024, 01:46 Jörg HallmannMIDShift summaryalignment of the instrument including collimation
and beam shaping
test of the tempus detector using
  
  124   11 Jun 2024, 00:43 Abhisakh SarmaSPBShift summary**X-ray delivery**


7.0 keV, up to 202 pulses
at 564 kHz, 1.0 mJ.


**Optical
  
  123   09 Jun 2024, 22:45 Chan KimSPBShift summaryX-ray delivery


7.0 keV, up to 202 pulses
at 564 kHz, 1.0 mJ.


Optical
  
  122   09 Jun 2024, 22:21 Giuseppe MercurioSCSShift summaryLate Shift summary

Achievements:
- recovered the beam overlap
  
  121   08 Jun 2024, 23:20 Abhisakh SarmaSPBShift summaryX-ray delivery
- 7.0 keV, up to 202 pulses at 564
kHz, 1.0 mJ.
  
ELOG V3.1.4-7c3fd00