Entry   Experiment summary, posted by Naresh Kujala on 28 Jan 2024, 19:55 Screenshot_from_2024-01-28_20-42-59.png
X-ray delivery


0.25nC, 14 GeV, rep rate 2.25 MHz, 9300 eV, 1 to 100 pulses, ~2000 uJ
M1 and M2 mirrors are aligned and beam trajectory to
SPB.


Goal
Entry   Issue, posted by Jan Gruenert on 28 Jan 2024, 13:50 
RC / BKR informs : Beam is down (since 12h10), all beamlines affected

The reason is failure of a quadrupole (power supply) downstream of the dogleg.
The MPS crew is working on recovery, access to XTL ongoing.
Entry   Shift summary, posted by Idoia on 27 Jan 2024, 15:17 
SASE3
Open Issues:
- currently it is not possible to change the number of pulses because of Instruments beam permission interlock