  OPERATION-2024 logbook, Contact: F.Wolff-Fabris, A.Galler, H.Sinn  Not logged in ELOG logo
Message ID: 11     Entry time: 03 Feb 2024, 23:51
Author: Jörg Hallmann 
Group: MID 
Subject: Shift summary 

goals achieved:
alignment of the beam in tunnel and hutches including refinement of the beam in the center of rotation 
check of cameras and optical components
initial check of the mirror chamber (successfully)

issues:
smarACT motors in the DES tricky - some are in error state and the filter wheel is moving and does not stop - positioned it and removed afterwards the cable - EEE intervention next week necessary
camera of Pop-in imager II45-2 in XTD6 went into error - DOC solved the issue