| ID | Date | Author | Group | Subject | Text |  |  | 369 | 27 Sep 2023, 07:24 | Romain Letrun | SPB | Shift summary | Shift summary for 26.9.2023 
 X-ray delivery
 
 
 6.3 keV, ~4 mJ, 1-352 pulses
 |  |  | 368 | 24 Sep 2023, 09:24 | Peter Zalden | FXE | Shift summary | 7:00 Power glitch during SPB operation - they were supposed to hand the beam back
 at 7:30h
 |  |  | 367 | 24 Sep 2023, 09:16 | Peter Zalden | FXE | Shift summary | Summary for sept., 23rd 
 6:55 SPB just handed the beam over
 to FXE when the power glitch killed the interlocks
 |  |  | 365 | 24 Sep 2023, 08:05 | Jan Gruenert | PRC | Status | 8h05 Beam is switched back on in SASE2. HED ready for taking beam.
 
 8h45 BKR is having problems to
 |  |  | 366 | 24 Sep 2023, 07:49 | Natalia, Justina, Giacomo, Sergey, Ben, Eugenio, Teguh | SCS | summary of 23.09 | Around 6:55 there was a power glitch. Power in the experimental hutch and rack room went
 down in SASE3, error message in Xray interlock
 |  |  | 364 | 24 Sep 2023, 07:28 | Raphael de Wijn | SPB | Shift summary | X-ray delivery 
 
 7 keV 202 pulses 1.6mJ
 stabel across train and throughout the shift
 Beam
 |  |  | 363 | 24 Sep 2023, 07:19 | Jan Gruenert | PRC | Attention | Again: power outage ! 
 As yesterday, at around 7am, power
 was lost in Schendfeld at SASE3. No beam
 |  |  | 362 | 23 Sep 2023, 23:31 | Motoaki Nakatsutsumi | HED | Shift summary | During the morning shift (7am - 3pm), we couldn't take any meaningful data due
 to the issue of power glitch which caused
 |  |  | 361 | 23 Sep 2023, 15:35 | Jan Gruenert | PRC | Issue | SASE2 : The unavailability of karabo and possibly
 missing cooling water is a problem for
 |  |  | 360 | 23 Sep 2023, 14:49 | Jan Gruenert | PRC | Status | Update of power outage aftermath 
 Achieved
 by now / status
 
 
 SASE1
 
 beam
 |  |  | 359 | 23 Sep 2023, 08:50 | Jan Gruenert | PRC | Issue | Updates on power glitch 
 8h50 No feedback from TS-OCD (still
 not arrived at SASE3 / SCS ?). Phone is busy.
 |     |  | 358 | 23 Sep 2023, 08:14 | Peter Zalden | FXE | Issue | FXE interlock in fault state. See photo attached with original error message from
 6:53h. It cannot be reset by acknowledging.
 |   |  | 357 | 23 Sep 2023, 07:59 | Oliver Humphries | HED | Shift summary | Shift summary from Monday 18th 7am until Saturday 7am
 
 MONDAY
 
 
 Aligned
 |  |  | 356 | 23 Sep 2023, 07:31 | Jan Gruenert | PRC | Issue | 7:23: RC info: an electrical power glitch interrupted
 beam operation, machine down. DESY has power
 |  |  | 355 | 23 Sep 2023, 07:04 | Adam Round | SPB | Shift end | Staff:JK, RDW, AR 
 X-ray delivery
 
 
 7 keV 202 pulses 1.7mJ
 |  |  | 354 | 22 Sep 2023, 17:46 | Jan Gruenert | PRC | Status | SASE3 gas supply alarm 
 SCS
 called the PRC at 17h04 due to a loud audible
 alarm in XHEXP1 and contacted also TS-OCD.
 |  |  | 353 | 22 Sep 2023, 07:27 | Raphael de Wijn | SPB | Shift summary | X-ray delivery 
 
 7 keV, 202 pulses, 564
 kHz, ~1.3 mJ, stable delivery
 
 
 Optical
 |  |  | 352 | 22 Sep 2023, 06:51 | Benjamin van Kuiken | SCS | Shift summary | Achievemnets 
 
 Characterized the X-ray
 and laser danage on the STO2LNO2
 
 
 Problems
 |  |  | 351 | 22 Sep 2023, 00:56 | Jan Gruenert | PRC | SA1 status | As agreed beforehand, PRC and SPB/SFX re-assessed the SA1 EPS power limit based on actual performance,
 required number of pulses and rep rate, at
 |  |  | 350 | 21 Sep 2023, 09:24 | Jan Gruenert | PRC | SA1 status | Info by R.Kammering (mail 20.9.23 18h25), related to the SA1 intensity drops
 during large wavelength scans:
 |  |  |